Attachment_7_Performance_Requirements.pdf

PDF 21 KB Posted

Attached to
Airfield Paving IDIQ MAPC Federal contract opportunity
Solicitation number
FA4497-17-R-0005
Issued by
Department of the Air Force Air Mobility Command

View the file

Other files for this federal contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Airfield Pavements IDIQ 1 Oct 16

Solicitation Number: FA4497-17-R-0005 Contract Number:

Attachment 7

PERFORMANCE REQUIREMENTS

PROJECT NUMBER: 141086

1. No work is anticipated to be required between the dates of 15 December and 1 March.

However, work may be required if weather permits.

2. Work requests will be issued individually. The Contractor must request acceptance by the Government upon completion.

3. The Contractor shall have a minimum of ten (10) calendar days to mobilize upon receipt of the first work request that will include time for approval of material submittals. Anytime during the contract period when there is an interruption of work for more than two days, the Contractor will be authorized two (2) additional work days for remobilization. In the event the Contractor is issued a work request after completion of all work from a previous work request and has departed the jobsite, an additional ten (10) working days shall be added to such work request for remobilization.

4. The total allowable performance time will be negotiated with each task order regardless of work request amount.