Questions and Answers - Round 2.pdf

PDF 92 KB Posted

Attached to
Repair Fuel System Generators Federal contract opportunity
Solicitation number
FA442721R0012
Issued by
Department of the Air Force Air Mobility Command

About this file

This document contains questions and answers regarding Solicitation FA442721R0012 from the Department of the Air Force Air Mobility Command for repair of fuel system generators. The solicitation requires contractors to provide all materials, labor, supervision and equipment to complete repairs to fuel system generators in accordance with specifications outlined in the Statement of Work. Notice to Proceed will be issued after payment and performance bonds are received from the awardee, and additional time for performance will be granted if needed due to long lead times on materials. A site visit was scheduled for February 23, 2021, with requests to attend due no later than February 22. No hazardous materials survey is needed due to the age of the buildings.

View the file

Other files for this federal contract opportunity

Other files attached to Repair Fuel System Generators, newest first.
File Type Posted
(ANS) XDAT 14-1031 PRE-BID RFI 12 -Follow Up RFI_Battery.pdf PDF
(ANS) XDAT 14-1031 PRE-BID RFI 13 -Switchgear.pdf PDF
(ANS) XDAT 14-1031 PRE-BID 04 B1041 Wire Designation.pdf PDF
(ANS) XDAT 14-1031 PRE-BID 09 Triple Switch Elevations.pdf PDF
(ANS) XDAT 14-1031 PRE-BID 05 B1733 Wire Designation.pdf PDF
(ANS) XDAT 14-1031 PRE-BID 06 Specified Generator Manufacturer (2.0).pdf PDF
(ANS) XDAT 14-11031 PRE-BID 03 Multiple Conduits on exterior.pdf PDF
Questions and Answers - Round 3.pdf PDF
Solicitation Amendment FA442721R00120001 SF 30.pdf PDF
(ANS) XDAT 14-1031 PRE-BID 01 Fuel Tank Responsibility.pdf PDF
(ANS) XDAT 14-1031 PRE-BID 06 Specified Generator Manufacturer.pdf PDF
(ANS) XDAT 14-1031 PRE-BID 07 Requirements for Utilizing Crane.pdf PDF
(ANS) XDAT 14-1031 PRE-BID 08 Contractors Responsibility in Demolished Equipment.pdf PDF
(ANS) XDAT 14-1031 PRE-BID 02 Drivers Training_Driving Privileges_Security Escorts.pdf PDF
XDAT 14-1031 PRE-BID RFI 11 Removal of Fuel.pdf PDF
XDAT 14-1031 PRE-BID RFI 10 Demolished Items.pdf PDF
48 - ED-2 - TANK DETAILS.pdf PDF
6 - B-6 - PUMPHOUSE ELEVATIONS.pdf PDF
3 - B-3 - PUMPHOUSE BUILDING SECTION.pdf PDF
33 - T-2 - APPURTENANCES AND FITTINGS.pdf PDF
5 - B-5 - PUMPHOUSE BUILDING SECTION.pdf PDF
29 - T-1 - FOUNDATION DETAILS.pdf PDF
43 - EU-1 - ELECTRICAL SITE PLAN AREA A.pdf PDF
20 - S-1 - VALVE VAULT DETAILS.pdf PDF
0 - C - 1 EXISTING SITE CONDITIONS AREA A.pdf PDF
4 - B-4 - PUMPHOUSE BUILDING SECTION.pdf PDF
8 - B-8 - CONNECTION DETAILS.pdf PDF
1 - B - 1 PUMPHOUSE FLOOR PLAN AND DETAILS.pdf PDF
7 - B-7 - CONNECTION DETAILS.pdf PDF
2 - B-2 - PUMPHOUSE BUILDING PLAN.pdf PDF
Attendance Sheet - Site Visit - Signed.pdf PDF
Questions and Answers - Round 1.pdf PDF
Attach 4a - B1041 Final Drawings.pdf PDF
Attach 2 - B1733 Final Design Analysis Report.pdf PDF
Attach 2a. - B1041 Final Design Analysis Report.pdf PDF
Attach 8 - WD CA20200007 27 November 2020.pdf PDF
Attach 5a - Submittal Register Generator B1041.pdf PDF
Attach 3a - B1041 Final Specifications.pdf PDF
Attach 11 - Contract Security Clause 29 Apr 19.pdf PDF
Solicitation - FA442721R0012.pdf PDF
Attach 7 - Travis Facilities Excellence Guide.pdf PDF
Attach 9 - Travis Specifications Section 01000.pdf PDF
Attach 1 - B1733 SOW Dated 23 Mar 2020.pdf PDF
Attach 6a - Bid Schedule B1041.xlsx XLSX spreadsheet
Attach 6 - Bid Schedule B1733.xlsx XLSX spreadsheet
Attach 1a - B1041 SOW Dated 23 Mar 2020.pdf PDF
Attach 4 - B1733 - Final Drawings.pdf PDF
Attach 3 - B1733 - Final Specifications.pdf PDF
Attach 5 - Submittal Register Generator B1733.pdf PDF
Attach 10 - Past Performance Questionnaire.docx DOCX document
Show all 50

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation FA442721R0012 – Questions and Answers – Round 2

Question #1: Section L, item 3.0, e Financial Institution Information indicates to Complete the attached Financial Institution Reference Sheet in Section J and return with the proposal.

However, this attachment is not included with the RFP. Please provide.

Answer: Financial Institution Reference Sheet will be required of the awardee only.

Question #2: The SF 1442 block 11 indicates the period of performance to be 180 CD after receiving the NTP. Due to the long lead time of the equipment (Generators and switchgear) and the manufacturing issues with COVID-19, MX Construction, Inc. is requesting the NTP to be issued after submittals are approved. Or, add additional days to the period of performance.

Answer: Notice to Proceed is issued after payment and performance bonds are received from the awardee. If additional time is required due to long lead time on materials the performance time shall be extended accordingly.

Question #3: Are there any as-built drawings available? If so, please provide.

Answer: As-builts have been posted to beta.sam

Question #4: Will the site visit attendee’s sign-in sheet be posted to Sam Beta?

Answer: Site visit sign in sheet has been posted to beta.sam

Question #5: The RFP clearly states that the Site Superintendent can act as the Quality Control Manager, one person wearing a dual hat. Will a separate Site Safety Health Officer be required?

Or, can the Site Superintendent act as the SSHO as well as the QCM (one person wearing a triple hat)?

Answer: Site Superintendent can act as the Quality Control Manager, one person wearing a dual hat. Site Safety Health Officer must be independent person/ position.

Question #6: Please confirm that security escorts are not required during construction. If escorts are required, is the contractor to include these costs in their proposal?

Answer: Escorts will be required for construction, but at no extra cost to the contractor.

Question #7: The drawings indicate to demolish and remove the existing underground conduits located between the existing generator and switchgear located inside each Bldg. Are these conduits concrete encased? Are there details on the existing duct bank? If so, please provide.

Answer: Refer to sheet A2.0 and sheet E3.3, detail 2

Question #8: Are there any known hazardous materials? Is there a Hazardous Materials Survey report? If so, please provide.

Answer: Based on the age of the building, a Hazardous Material Survey will not be required.

File details come from the government source that posted it. Updated .