Attach 1a - B1041 SOW Dated 23 Mar 2020.pdf

PDF 239 KB Posted

Attached to
Repair Fuel System Generators Federal contract opportunity
Solicitation number
FA442721R0012
Issued by
Department of the Air Force Air Mobility Command

About this file

This document contains a Statement of Work and related federal contract opportunity solicitation for repairing fuel system generators at Travis Air Force Base in California. The contractor shall provide all materials, labor, supervision, and equipment to complete the repairs according to specifications outlined in the Statement of Work. A mandatory site visit is scheduled for February 23, 2021 at 9:00AM Pacific Time to inspect the project location. Attendees must RSVP in advance and comply with base security and COVID-19 protocols, such as wearing face coverings. The solicitation was issued by the Department of the Air Force Air Mobility Command for repairs in accordance with the Statement of Work. The response deadline is not specified.

View the file

Other files for this federal contract opportunity

Other files attached to Repair Fuel System Generators, newest first.
File Type Posted
(ANS) XDAT 14-1031 PRE-BID RFI 13 -Switchgear.pdf PDF
(ANS) XDAT 14-1031 PRE-BID RFI 12 -Follow Up RFI_Battery.pdf PDF
(ANS) XDAT 14-1031 PRE-BID 05 B1733 Wire Designation.pdf PDF
(ANS) XDAT 14-1031 PRE-BID 04 B1041 Wire Designation.pdf PDF
(ANS) XDAT 14-1031 PRE-BID 09 Triple Switch Elevations.pdf PDF
(ANS) XDAT 14-1031 PRE-BID 06 Specified Generator Manufacturer (2.0).pdf PDF
(ANS) XDAT 14-11031 PRE-BID 03 Multiple Conduits on exterior.pdf PDF
Questions and Answers - Round 3.pdf PDF
Solicitation Amendment FA442721R00120001 SF 30.pdf PDF
(ANS) XDAT 14-1031 PRE-BID 08 Contractors Responsibility in Demolished Equipment.pdf PDF
(ANS) XDAT 14-1031 PRE-BID 02 Drivers Training_Driving Privileges_Security Escorts.pdf PDF
(ANS) XDAT 14-1031 PRE-BID 01 Fuel Tank Responsibility.pdf PDF
(ANS) XDAT 14-1031 PRE-BID 06 Specified Generator Manufacturer.pdf PDF
(ANS) XDAT 14-1031 PRE-BID 07 Requirements for Utilizing Crane.pdf PDF
XDAT 14-1031 PRE-BID RFI 11 Removal of Fuel.pdf PDF
XDAT 14-1031 PRE-BID RFI 10 Demolished Items.pdf PDF
48 - ED-2 - TANK DETAILS.pdf PDF
6 - B-6 - PUMPHOUSE ELEVATIONS.pdf PDF
3 - B-3 - PUMPHOUSE BUILDING SECTION.pdf PDF
1 - B - 1 PUMPHOUSE FLOOR PLAN AND DETAILS.pdf PDF
7 - B-7 - CONNECTION DETAILS.pdf PDF
2 - B-2 - PUMPHOUSE BUILDING PLAN.pdf PDF
33 - T-2 - APPURTENANCES AND FITTINGS.pdf PDF
5 - B-5 - PUMPHOUSE BUILDING SECTION.pdf PDF
29 - T-1 - FOUNDATION DETAILS.pdf PDF
43 - EU-1 - ELECTRICAL SITE PLAN AREA A.pdf PDF
20 - S-1 - VALVE VAULT DETAILS.pdf PDF
0 - C - 1 EXISTING SITE CONDITIONS AREA A.pdf PDF
4 - B-4 - PUMPHOUSE BUILDING SECTION.pdf PDF
8 - B-8 - CONNECTION DETAILS.pdf PDF
Questions and Answers - Round 2.pdf PDF
Attendance Sheet - Site Visit - Signed.pdf PDF
Questions and Answers - Round 1.pdf PDF
Attach 4a - B1041 Final Drawings.pdf PDF
Attach 2 - B1733 Final Design Analysis Report.pdf PDF
Attach 2a. - B1041 Final Design Analysis Report.pdf PDF
Attach 8 - WD CA20200007 27 November 2020.pdf PDF
Attach 5a - Submittal Register Generator B1041.pdf PDF
Attach 4 - B1733 - Final Drawings.pdf PDF
Attach 3 - B1733 - Final Specifications.pdf PDF
Attach 5 - Submittal Register Generator B1733.pdf PDF
Attach 10 - Past Performance Questionnaire.docx DOCX document
Attach 3a - B1041 Final Specifications.pdf PDF
Attach 11 - Contract Security Clause 29 Apr 19.pdf PDF
Solicitation - FA442721R0012.pdf PDF
Attach 7 - Travis Facilities Excellence Guide.pdf PDF
Attach 9 - Travis Specifications Section 01000.pdf PDF
Attach 1 - B1733 SOW Dated 23 Mar 2020.pdf PDF
Attach 6a - Bid Schedule B1041.xlsx XLSX spreadsheet
Attach 6 - Bid Schedule B1733.xlsx XLSX spreadsheet
Show all 50

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Repair Fuel System Generator, B1041

TRAVIS AFB, CALIFORNIA

Project Number: XDAT 14-1031

TRIRIGA Number: 1023212 DATE: 23 Mar 2020

1.0 DESCRIPTION OF WORK: The contractor is to provide all supplies, materials, tools, equipment, and qualified labor necessary to repair by replacement servicing Hydrant System at facility 1041 per Development One, Inc., Final Design Submittals. 2a. Final Design Analysis Report, 2b. Final Specifications, 2c. Final Drawings. The overall project includes the removal of existing generator and transfer switchgear. The installation of a new 450kW/562kVA diesel backup generator on new concrete pad and the installation of a new manual transfer switchgear.

2.0 STATEMENT OF WORK: See item# “2a. TAFB Generator - Final Design Analysis” pages 3-6.

3.0 Equipment Cut Sheets: See item# “2a. TAFB Generator-Final Design Analysis” on pages 7-16 of the Project package

4.0 Project Specifications: See item# “2b. Final Specifications” of Project package

5.0 Project Drawings: See item# “2c. Final Drawings” of Project package

6.0 Travis Design Guide: See item#15 of Project package

7.0 Travis Specifications: Section 01000

8.0 Submittal Register: See item#5 of Project package

9.0 Bid Schedule: See item#18 of Project package

10.0 Environmental Requirements (Additional):

The contractor shall comply with all applicable federal, state, local air district and Section 01 56 00 Environmental General Requirements, including but not limited to:

a. Notify 60 CES/CEIE at least two weeks prior to modify or remove the existing permitted generators.

b. The contractor is responsible for complying with the Bay Area Air Quality

Management District (BAAQMD) Regulation 2-1 permit requirements.

c. The contractor is responsible for submitting a permit applications and fees for the new generators. Permit applications must be coordinated with

60 CES/CEIE for review prior being submitted to BAAQMD.

d. The new generators/engines shall meet the BAAQMD permit requirements without adding additional abatement devices.

e. The contractor is responsible for obtaining an Authority to Construct and Permit to Operate from the BAAQMD.

f. The contractor shall notify and submit/email the Start-Up Notification form to

60 CES/CEIE at least two weeks prior to start up the new generators.

11.0 Process: Contractor is to use the “Project Phase Listing,” below as a general Guideline for project sequence.

Project Phase Listing **Phase elements and components listed are for description purposes and are performed as contracted** Phase I: Pre-project

Engineer – Site inspection, validation, certified design submitted for approval Project Safety – Validation of utility service isolation (natural gas, electricity, and water) Administration – Authorization to proceed and list of required submittals Project Manager – Coordination of end-user/vendor schedule, site access, and project milestone plans Project Manager – Submit all required pre-project submittals as instructed Operations Lead – Element material acquisition and start necessary fabrication Phase 2: Build

Inspection – Building site for necessary access, materials Layout – Site layout (marking), grading and excavation Subsurface – Build infrastructure Infrastructure – Install generator concrete pad, ductbank, grounding connection, enclosure Surface – Install generator concrete pad as designed, curbs and pavements Connect – Connect all elements, components, devices, assets into a comprehensive system Test – Complete validation, commissioning, testing, metering and certification Phase 3: Post-Project

Inspection – Formal walkthrough with project manager/end-user for verification and acceptance

Warrantee – Provide service warranty (12-months w/ additional 24-month telephone consultation)

Real Property – Process DD 1354 Survey – Perform customer satisfaction survey

STATEMENT OF WORK

File details come from the government source that posted it. Updated .