This document contains a bid schedule and statement of work for a federal contract solicitation. The solicitation seeks a contractor to provide all materials, labor, supervision and equipment to complete repairs to fuel systems for generators at Travis Air Force Base in California. Work will include removing an existing generator and transfer switchgear, replacing an above ground fuel tank, removing electrical ductbank, installing a new generator rated at 450 kW with an enclosure, installing a transfer switchgear rated at 1200 amps, installing a new electrical ductbank, installing triple switch and remote annunciator panels, and commissioning and testing the system. The bid schedule outlines line items for sawcutting, removing hardscape, installing a concrete equipment pad, labor and materials for patchwork and painting, selective demolition work, and general conditions. A mandatory site visit is scheduled for February 23, 2021 at 9:00AM PST, with RSVP required by February 22 at 4:00PM PST.
View the file
Other files for this federal contract opportunity
Show all 50
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 FOR OFFICIAL USE ONLY Bid Schedule Repair Fuel System Generator, B1733 Travis AFB CA
Description Quantity Unit Line Total
Div 2 - Existing Conditions
| Sawcut hardscape | lf |
| Remove hardscape | sf |
Div 3 - Concrete
Concrete Equipment Pad, 17" thick sf
Div 9 - Finishes
| Labor to provide patchwork and paint associated with electrical upgrades | hr |
| Materials for patchwork and paint | ls |
Div 26 - Electrical
| Selective Demolition | |
| Remove Generator and transfer switchgear | ea |
| Above ground fuel tank | ea |
| Remove existing electrical ductbank | lf |
| Safe off | loc |
| Misc selective demolition | hr |
| Service and Distribution | |
| Generator, 450 kW | ea |
| Generator enclosure | ea |
| Transfer switchgear, 1200 amp | ea |
| New electrical ductbank | lf |
| ESL triple switch | ea |
| Grounding connection | ea |
| Remote annunciator panel | ea |
| Commissioning | hr |
| Testing | hr |
| Metering | ls |
| Subtotal | |
| General Conditions | % |
| Subtotal | |
| Overhead | % |
| Subtotal | |
| Profit | % |
| Subtotal | |
| Bonds and Insurance | % |
TOTAL CONSTRUCTION COST