Attach 1 - B1733 SOW Dated 23 Mar 2020.pdf
PDF 239 KB Posted
- Attached to
- Repair Fuel System Generators Federal contract opportunity
- Solicitation number
- FA442721R0012
About this file
This document includes a statement of work and related federal contract opportunity for repair work on fuel system generators at Travis Air Force Base in California. The statement of work provides specifications for removing an existing generator and transfer switchgear, installing a new 450kW diesel backup generator on a concrete pad, and installing a new manual transfer switchgear. It references attachments that include a final design analysis, specifications, drawings, design guides, and a bid schedule. The related federal contract opportunity is solicitation number FA442721R0012 issued by the Department of the Air Force Air Mobility Command to provide all materials, labor, supervision and equipment to complete the repair work according to the statement of work specifications. A mandatory site visit is scheduled for February 23, 2021 at 9:00AM PST, with an RSVP deadline of February 22 at 4:00PM PST. Compliance with Real ID and COVID-19 protocols is required to attend.
View the file
Other files for this federal contract opportunity
Show all 50
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Repair Fuel System Generator, B1733
TRAVIS AFB, CALIFORNIA
Project Number: XDAT 20-2001
TRIRIGA Number: 1096362 DATE: 23 Mar 2020
1.0 DESCRIPTION OF WORK: The contractor is to provide all supplies, materials, tools, equipment, and qualified labor necessary to repair by replacement servicing Hydrant System at facility 1733 per Development One, Inc., Final Design Submittals. Attach 2 Final Design Analysis Report, Attach 3 Final Specifications, and Attach 4 Final Drawings. The overall project includes the removal of existing generator and transfer switchgear. The installation of a new 450kW/562kVA diesel backup generator on new concrete pad and the installation of a new manual transfer switchgear.
2.0 STATEMENT OF WORK: See “Attach 2 – B1733 - Final Design Analysis” pages 3-6.
3.0 Equipment Cut Sheets: See “Attach 2 – B1733 -Final Design Analysis” on pages 7-16 of the Project package
4.0 Project Specifications: See “Attach 3 – B1733 - Final Specifications” of Project package
5.0 Project Drawings: See “Attach 4 – B1733 - Final Drawings” of Project package
6.0 Travis Design Guide: See Attach 7 of Project package
7.0 Travis Specifications: Section 01000
8.0 Submittal Register: See Attach 5 of Project package
9.0 Bid Schedule: See Attach 6 of Project package
10.0 Environmental Requirements (Additional):
The contractor shall comply with all applicable federal, state, local air district and Section 01 56 00 Environmental General Requirements, including but not limited to:
a. Notify 60 CES/CEIE at least two weeks prior to modify or remove the existing permitted generators.
b. The contractor is responsible for complying with the Bay Area Air Quality
Management District (BAAQMD) Regulation 2-1 permit requirements.
c. The contractor is responsible for submitting a permit applications and fees for the new generators. Permit applications must be coordinated with
60 CES/CEIE for review prior being submitted to BAAQMD.
d. The new generators/engines shall meet the BAAQMD permit requirements without adding additional abatement devices.
e. The contractor is responsible for obtaining an Authority to Construct and Permit to Operate from the BAAQMD.
f. The contractor shall notify and submit/email the Start-Up Notification form to
60 CES/CEIE at least two weeks prior to start up the new generators.
11.0 Process: Contractor is to use the “Project Phase Listing,” below as a general Guideline for project sequence.
Project Phase Listing **Phase elements and components listed are for description purposes and are performed as contracted** Phase I: Pre-project
Engineer – Site inspection, validation, certified design submitted for approval Project Safety – Validation of utility service isolation (natural gas, electricity, and water) Administration – Authorization to proceed and list of required submittals Project Manager – Coordination of end-user/vendor schedule, site access, and project milestone plans Project Manager – Submit all required pre-project submittals as instructed Operations Lead – Element material acquisition and start necessary fabrication Phase 2: Build
Inspection – Building site for necessary access, materials Layout – Site layout (marking), grading and excavation Subsurface – Build infrastructure Infrastructure – Install generator concrete pad, ductbank, grounding connection, enclosure Surface – Install generator concrete pad as designed, curbs and pavements Connect – Connect all elements, components, devices, assets into a comprehensive system Test – Complete validation, commissioning, testing, metering and certification Phase 3: Post-Project
Inspection – Formal walkthrough with project manager/end-user for verification and acceptance
Warrantee – Provide service warranty (12-months w/ additional 24-month telephone consultation)
Real Property – Process DD 1354 Survey – Perform customer satisfaction survey
STATEMENT OF WORK