Three (3) Secondary Containment Above Ground Storage Tanks (SCATs)
Solicitation number
FA4419-24-Q-0037
Issued by

About this file

This document is an attachment to a federal contract opportunity for the acquisition of three (3) 10,000-gallon Secondary Containment Above Ground Storage Tanks (SCATs). The key requirements are:

The tanks must meet UFC 3-460-01 and NFPA 30/30A specifications, be UL 2085 certified, and have double-wall construction. They must have an underneath skid support, "M" class fuel filtration, automatic tank gauge with high-level alarm, and turnkey operation with pump and filtration capability. The tanks cannot exceed 40 feet in length by 12 feet in width, and must have a 300 GPM flow rate with 30-foot hoses. A canopy is required over the added system components. Additionally, a 300 GPM EL 1581 filter/separator unit is needed.

The related federal contract opportunity is Solicitation Number FA4419-24-Q-0037 issued by the 97th Contracting Squadron, Altus Air Force Base, for delivery to Ebbing ANG Base, Fort Smith, Arkansas. This opportunity falls under NAICS code 332420, and prospective contractors must be registered in the System for Award Management (SAM) database prior to proposal submission.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Requirement: THREE (3 EA) standalone 10K GALLON SCATS for issue of Jet A fuel to Air Force R-11 6,000-gallon refueler a/o 7,000 gallon commercial variant that has recently been stock-listed. (All connection points NATO standard as with R-11) meeting specifications below:

Specifications:

THREE (3 EA) standalone 10K GALLON SCATS

‐ DECIDING FACTOR: SINGLE, STANDALONE

‐ REQUIRED: tanks meet and in adherence to UFC 3-460-01, Table 8.1 and

NFPA 30/30A.

‐ REQUIRED: UL 2085 - REQUIRED

‐ REQUIRED: Double wall tanks (eliminates need for containment – thus no

Environment impact) ‐ REQUIRED: Tank must have underneath skid support (not saddles) for equal weight distribution (No ground or soil disruption) ‐ REQURIED: “M” class filtration for additive fuel ‐ REQUIRED: Port for Automatic Tank Gauge (ATG) and install a high-level alarm ‐ REQUIRED: Turnkey operation, to include pump and filtration capability

(only requires power and will have appropriate connection for power hookup) o NOTE: Power has been validated. Three transformers surrounding the compound (350KvA to 500Kva).

‐ REQUIRED: Cannot exceed 40FT LENGTH x 12 FT WIDTH.

‐ REQUIRED: “NO” brass fittings ‐ REQUIRED: Single point of issue from each tank ‐ REQUIRED: Flow Rate for fueling is 300GPM ‐ REQUIRED: 30ft hose length ‐ REQUIRED: Canopy installed over added system components. Must have sufficient clearance to perform maintenance or be easily removed/reinstalled to accommodate system repairs/component replacement.

‐ REQUIRED: Provide a 300 GPM EL 1581 filter/separator unit as specified in UFC 3-460-01 that qualifies for use in an ANSI 150 piping system with a