Attachment 11 - JB Lindsey Graham Offeror Question and Answer Form.xlsx

XLSX spreadsheet 46 KB Posted

Attached to
Repair Taxiway Alpha & Bravo - North Auxiliary Airfield
Solicitation number
FA441827R0002
Issued by

About this file

This is a Question and Answer (Q&A) document addressing offeror inquiries regarding the Repair Taxiways Alpha & Bravo solicitation (FA441827R0002) at Joint Base Lindsey Graham – North Auxiliary Airfield in Orangeburg County, South Carolina.

The project involves mill and overlay of two taxiways, joint sealing, airfield lighting upgrades, pavement markings, and incidental related work over a 172-calendar-day period of performance measured from Notice to Proceed. Work is organized into two areas: Work Area 1 (taxiway mill and overlay) operates Tuesday through Saturday during regular hours (0700–1900), while Work Area 2 (Friday–Sunday no-fly day work) is restricted to weekends only and cannot be conducted concurrently with Work Area 1. The contract includes a base bid (CLIN 0001, lump sum) covering mobilization, submittals, 30 days of construction, a 25-day asphalt cure period, and turf establishment, plus six estimated-quantity line items (CLINs 0002–0007) for unsatisfactory excavation removal and replacement (2,000 CY), cement-stabilized subgrade (4,000 SY), geogrid (4,000 SY), asphalt crack repair (20,000 LF), Type I reflective media markings (6,250 SF), and Type III reflective media markings (6,250 SF). Payment for CLINs 0002–0007 is based on actual quantities installed and accepted, not the estimated quantities. The 172-day period already includes anticipated adverse weather delays; excusable, non-compensable time extensions are available only if actual weather delays exceed monthly thresholds on the critical path. The proposal due date is 12:00 PM Eastern Standard Time on 2 December 2026, submitted electronically via DoD SAFE with separate PDF files for price and past performance information. The solicitation is a competitive small business set-aside using trade-off procedures with past performance significantly more important than cost. Offerors must provide a 20 percent bid guarantee (SF 24), performance and payment bonds (SF 25/25-A) within 10 calendar days of award, and documentation demonstrating workforce access to the base facility. Key submittals include a Construction Safety and Phasing Plan, preconstruction certifications, daily quality control reports compiled weekly, and airfield coordination including FAA Form 7460-1/7460-2 filing by the contractor and NOTAM filing coordination with Airfield Management. Work is subject to 72-hour excavation notification, mandatory contractor-furnished security guards at the main gate during working hours, airfield driving training for all personnel, and dual/triple-hatted supervision positions (Quality Control Manager/Site Safety and Health Officer/COSPP monitor) where qualified. The contractor must retain a South Carolina-registered Professional Engineer for erosion and sediment control oversight and final certification. No CADD/BIM files will be released to offerors during solicitation; all quantity takeoffs must use the official sealed PDF drawings and specifications. The wage determination has been amended to include missing classifications for electrical, painting, marking, and CIPP lining work.

View the file

Other files

File Type Posted
Solicitation Amendment FA441827R00020004 SF 30.pdf PDF
JBLG QandA NAAF Taxiways Alpha and Bravo 20261125.xlsx XLSX spreadsheet
Solicitation Amendment FA441827R00020003.pdf PDF
Attachment 13 - Transformer NAAF.png PNG image
Attachment 12 - Geotech Report NAAF.pdf PDF
Attachment 14 - SWPPP NAAF.pdf PDF
Attachment 9 - Wage Determination - SC20260001.pdf PDF
Attachment 10 - Past Performance Customer Questionnaire.pdf PDF
Solicitation Amendment FA441827R00020002.pdf PDF
Solicitation Amendment FA441827R00020001.pdf PDF
NAAF Site Visit Sign In Sheet 20261104.pdf PDF
JB Lindsey Graham - Question and Answer Form.xlsx XLSX spreadsheet
NAAF Repair Taxiway Alpha and Bravo SV - List of Contractors.xlsx XLSX spreadsheet
Attachment 7 - SBML 1052018 - Combined Specifications.pdf PDF
Attachment 4 - SBML 1052018 - 100 percent drawings part 1.pdf PDF
Attachment 3 - SBML 1052018 - Submittal Register.pdf PDF
Attachment 6 - SBML 1052018 - 100 percent drawings part 3.pdf PDF
Attachment 8 - Wage Determination - SC20260040.pdf PDF
Attachment 5 - SBML 1052018 - 100 percent drawings part 2.pdf PDF
Attachment 1 - SBML 1052018 - Total Performance Time.pdf PDF
Solicitation - FA441827R0002.pdf PDF
Attachment 2 - SBML 1052018 - Recovered Material Certification.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1 JB Lindsey Graham Offeror Question and Answer Form NOTICE TO OFFERORS Any offeror desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all offerors before the submission of their proposals. Oral explanations or instructions given before the award of a contract will not be binding. Answers to offeror questoins concerning a solicitation will be posted to sam.gov, if that information is necessary in preparing proposals or if the lack of it would be prejudicial to others.

Solicitation NumberFA441827R0002
Project Name:Repair Taxiways Alpha & Bravo - North Auxiliary Airfield
#Specification Reference (Section & Paragraph Reference, i.e. 23 00 00, para 1.3)Drawing Reference (Sheet and Detail or Note Reference, i.e. M-101, Detail 2)Solicitation Reference (Section, paragraph, sub-paragraph Reference, i.e. Section M, Paragraph 2.3)Attachments or Other (i.e. Submittal Register, Wage Determination, Site Visit Note, etc.)
1Question
Section H, Site Visit Instructions, para 1Amendment 0001, SF 30 Block 14(a)QUESTION DEADLINE / PROPOSAL DUE DATE: Given that the design documents are dated April 2017 and several scope items (CLINs 0003 and 0004) have no specification or drawing coverage, will the Government consider extending the 02 December 2026 proposal due date so that answers can be issued by amendment with adequate time for offerors to incorporate them into pricing?
Answer
The 02 December proposal due date is a hard deadline for proposals for this project.CONS concurs - DT
2Question
01 32 16.00 20, para 1.2.2.4G203, Project Duration ChartSF 1442 Item 11; Section F; Section I (52.211-12)Attachment 1 - Total Performance TimePERIOD OF PERFORMANCE CONFLICT: The documents state different performance periods: (a) SF 1442 Item 11 - begin within 60 calendar days and complete within 172 calendar days after 'award / notice to proceed' (neither box clearly selected); (b) Section F - 172 calendar days from Date of NTP Receipt; (c) Attachment 1 - 172 days made up of 112 days mobilization/submittals (the note in the same row says 60 calendar days), 30 days construction, and 30 days closeout (the note says 45 calendar days per 01 78 00); (d) Sheet G203 - 116 calendar days total (60 days preparation/submittals, 30 days construction, 25-day asphalt cure, permanent markings, final inspection). Please confirm: (1) the governing contract duration; (2) whether the clock starts at award or at receipt of NTP; (3) whether the 30 construction days include the 25-day asphalt cure period before permanent markings and the weekend-only Work Area 2 restriction; and (4) whether FAR 52.211-10, referenced in SF 1442 Item 11, is incorporated (it is not listed in Section I).
Answer
Period of performance is 172 calendar days from Date of NTP Receipt. This is to include preconstruction submittals, 30 construction days, 25-day asphalt cure period, and any weekend-only work. FAR 21.211-10 is explicitly cited and incorporated via the SF 1442.
3Question
01 32 16.00 20, para 1.2.2.4Attachment 1 - Total Performance TimeANTICIPATED ADVERSE WEATHER DAYS CONFLICT: Attachment 1 lists average inclement weather days per month (e.g., Jun 4, Jul 6, Aug 6) and cites 'Spec 01 32 00, para 3.3.8.1,' which is not included in the specifications. Specification 01 32 16.00 20, para 1.2.2.4 lists different anticipated adverse weather days (e.g., Jun 8, Jul 9, Aug 9). Attachment 1 also contains apparent errors (a row labeled 'July 2009'; September shown as 28 days, January as 30 and February as 31; construction days per month and weather days calculate to zero). Please confirm that the table in 01 32 16.00 20 para 1.2.2.4 governs for scheduling and weather time-extension purposes, and whether the contract duration already includes the anticipated weather days.
Answer
In accordance with Specification 01 32 16.00 20, paragraph 1.2.2.4 and Sheet G203 Note 3, the 172-calendar-day PoP already includes the anticipated adverse weather delay days tabulated in Section 01 32 16.00 20 (e.g., Jun 8, Jul 9, Aug 9). As stipulated in paragraph 1.2.2.4, an excusable, non-compensable time extension will be considered via contract modification only if actual adverse weather delays exceed the monthly anticipated non-workdays established in the specification and directly impact activities on the critical path.
4Question
01 14 00, paras 1.2.2 and 1.2.3; 01 32 16.00 20, para 1.2.2.3; 01 35 23, COSPP Section I.A.2G200, Work Area Closure Table and KeynotesWORK DAYS / WORKING HOURS CONFLICT: 01 14 00 para 1.2.2 establishes regular working hours as a 12-hour period between 0700 and 1900, Tuesday through Saturday, with no work on Mondays. The COSPP (01 35 23, Section I.A.2.b) and the G200 Work Area Closure Table require all Work Area 2 work (within the displaced threshold of RWY 06/24) to be performed only on Friday, Saturday and Sunday. 01 32 16.00 20 para 1.2.2.3 requires schedule calendars that treat Saturdays and Sundays as non-work days. Please confirm: (1) Sunday work is permitted for Work Area 2 as regular hours and does not require the 15-day 'work outside regular hours' request under 01 14 00 para 1.2.3; (2) Saturdays and Sundays are work days for scheduling purposes; (3) whether night work is permitted or anticipated in either work area; and (4) Work Area 1 may be worked continuously Tuesday through Saturday with RWY 05/23 and Taxiways A and B closed for the full construction duration.
Answer
1) Confirmed, Sunday work is permitted for Work Area 2 as regular hour and does not require a 15-day request.

2) Confirmed, Saturdays and Sundays are work days for scheduling purposes.

3) Night work is permitted within authorized closure windows provided all airfield safety, operational, and portable floodlighting criteria are met in accordance with the COSPP and Section 01 14 00 paragraph 1.2.3. Lighting plans must be coordinated with Airfield Management to prevent glare or hazard to operating aircraft. Coordinate Night Work with CO at least 14 days ahead of work.

4) Aircraft operations have priority at North Auxilliary Airfield. There is no gaurantee that work can occur continuously Tuesday through Saturday, and RWY 05/23 and TWYs A and B will not close for the full construction duration.Wouldn't taxiways A and B have to close during mill and overlay?
5Question
01 35 23, COSPP Sections I.A and I.BG200; G201; G202; G203 (Airspace / 7460 / NOTAM notes)PHASING AND AIRFIELD OPERATIONS: The COSPP and G200-series sheets are dated April 2017 and are based on Friday-Sunday 'no fly days' and closure of RWY 05/23 (ALZ). Please confirm: (1) the current NAAF flying schedule and that Friday-Sunday remain no-fly days; (2) whether Work Areas 1 and 2 may be worked concurrently; (3) the maximum number of weekends RWY 06/24 may be closed for Work Area 2; (4) whether the Government/Airfield Manager or the contractor will file FAA Forms 7460-1/7460-2 and NOTAMs (G203 requires contractor submittal at least 45 days before construction) and whether that 45-day period is accounted for in the mobilization period; and (5) whether an updated, Government-approved CSPP will be issued to reflect current operations.
Answer
1) Current NAAF flying schedule is fluid and cannot be released to the public, however Friday-Sunday remain no-fly days with limited exceptions. These will be coordinated on a case-by-case basis.

2) Work Areas 1 and 2 may not be worked concurrently

3) Friday-Sunday are no-fly days. There is no maximum number of weekends that RWY 06/24 may be closed.

4) Contractor will be responsible for filing FAA Forms 7460-1/7460-2. Airfield Managment will be responsible for filing NOTAMs with the help of the contractor. 45-day submittal period is required.

5) The current Construction Safety and Phasing Plan (CSPP) drawings (G200–G203) and specification Section 01 35 23 represent the Government's governing operational plan for this project. If operational adjustments are required by Airfield Management prior to award, they will be promulgated via an official amendment on SAM.gov. (2) could these be worked concurrently on the weekends?

- I took this to mean working the areas at the same time. Work Area 1 is weekday work, Work Area 2 is weekend work, there isnt really a day that they could do both. But they could work Area 1 and Area 2 in the same 7 day week. Dont know how to intelligently state that. SMC

6Question
Project Table of Contents (cover dated 21 Apr 2017); 01 35 26, para 1.1; 01 30 00, para 1.6G001 Title Sheet and all sheets (dated 4/21/2017, SBML 12-1100)Section B, CLIN 0001 (SBML 1052018)Attachments 3 through 7DESIGN CURRENCY AND PROJECT NUMBER: All drawings, specifications and the submittal register are the 100% Design Submittal dated April 21, 2017 under JBC Project No. SBML 12-1100, while the solicitation identifies the project as SBML 1052018. Referenced criteria are outdated (e.g., UFC 3-260-01 2008 edition, EM 385-1-1 2014, FAA AC 150/5300-13A Change 1). Please confirm: (1) these documents are the complete and final design for SBML 1052018 and no later revision exists; (2) whether existing pavement, crack and drainage conditions have been re-surveyed since the 2016 geotechnical exploration, and whether any repairs or overlays have been performed on Taxiways A and B since 2017; (3) which edition of EM 385-1-1 governs (2014 as cited, or the current edition); and (4) whether the Government will release CADD files to offerors before the proposal due date to support quantity takeoff.
Answer
This project was originally designed in 2017 and sat on the shelf until authority to advertise in 2026.

1) Confirmed. These documents are complete and final design for this project and no later revisions exist.

2) Existing pavement, crack and drainage conditions have NOT been re-surveyed since 2016 geotechnical exploration. And no repairs or overlays have been performed on TWYs Alpha or Bravo since 2017.

3) Current edition of EM385-1-1 (at the time of contract solicitation) governs.

4) Government CADD/BIM design files will not be released to prospective offerors during the active solicitation phase. Offerors must perform all quantity takeoffs, estimating, and proposal pricing utilizing the official sealed contract PDF drawing set and specifications provided on SAM.gov.

7Question
No specification section provided; 02 01 00 (S&ME Geotechnical Report, 2 Dec 2016, p. 2)C620, Details A-D; C320-C323Section B, CLIN 0003CLIN 0003 - CEMENT STABILIZED SUBGRADE (4,000 SY): The specifications contain no section for cement-stabilized subgrade, and the drawings show no location, depth or typical section for it (C620 shows 8-inch aggregate base on subgrade only). The geotechnical report states lime-soil stabilization testing was performed with results 'to be provided in an addendum'; that addendum is not included. Please provide: (1) the governing specification (cement content, treatment depth, mixing method, compaction/strength acceptance criteria); (2) the locations and typical section where stabilization will be used; (3) the method of measurement (SY at what treated depth); (4) the geotechnical addendum with stabilization test results; and (5) confirmation of whether cement or lime stabilization is intended.
Answer
(1 + 5) As established under General Bid Item Note 3 on Sheet C001, stabilization shall be performed utilizing Portland cement (not lime). The subgrade shall be stabilized with Portland cement to a depth of 12 inches, with the specific cement dosage (percentage by dry unit weight of soil) to be determined in the field based on proof rolling evaluations and soil testing. Mixing, aeration/moisture conditioning, and compaction shall conform to Section 31 00 00 (Earthwork), requiring compaction of the top 12 inches to a minimum of 95% of maximum dry density for cohesive materials or 100% for cohesionless materials per ASTM D 1557. Reference spec 03 30 53.

(2 + 3)CLINs 0002-0007 are bid options / estimated quantities. Payment will be based on actual quantities installed and accepted. CLIN 0003 is an estimated quanity of cement stabilized subgrade in the event that unsuitable subgrade is found during excavation/milling operations and needs to be resolved using stabilization methods.

(4) The referenced addendum will be uploaded with these drawings. It provides baseline laboratory soil pH and lime-soil proportion stabilization data (ASTM C977 / Eades and Grim method), confirming the subgrade soils are reactive (natural pH 4.1 to 5.0 reaching pH 12.3+ with 2% to 3% stabilizer). This testing was exploratory during design; the contract documents establish Portland cement as the governing stabilizing agent under CLIN 0003.

8Question
No specification section providedC620 (no geogrid shown)Section B, CLIN 0004CLIN 0004 - 1200 BX TENSAR GEOGRID OR APPROVED EQUAL (4,000 SY): No specification section or drawing detail identifies the geogrid placement elevation, overlap, anchorage, or locations. Please provide: (1) the specification and installation detail; (2) the intended locations (e.g., shoulders, undercut areas, or in combination with CLIN 0003); (3) the method of measurement (SY in place, with or without overlaps); and (4) the salient characteristics an 'approved equal' must meet, and confirmation that current-generation geogrids meeting those characteristics will be accepted.
Answer
CLINs 0002-0007 are bid options / estimated quantities. Payment will be based on actual quantities installed and accepted. CLIN 0004 is an estimated quanity of geogrid in the event that unsuitable subgrade is found during excavation/milling operations and needs to be resolved using geogrid methods.

Installation shall follow the manufacturer's written installation guidelines and standard subgrade stabilization practices. The geogrid shall be placed flat and taut directly on prepared, rolled subgrade beneath the 8-inch aggregate base course (or select granular fill in undercut areas), anchored with U-shaped sod staples or pins, and overlapped a minimum of 24 inches along longitudinal and transverse roll joints. Measurement and payment for CLIN 0004 is based on the actual plan area of stabilized subgrade surface coverage in square yards (SY) up to the estimated contract quantity of 4,000 SY.

The salient physical and mechanical characteristics are established by the referenced baseline product, including minimum aperture dimensions, rib thickness, junction efficiency, true tensile strength and strain, and ultimate tensile strength. Current-generation multi-axial/triaxial or equivalent biaxial geogrids meeting or exceeding these structural subgrade stabilization characteristics will be evaluated and accepted as approved equals via the standard submittal process (Section 01 33 00).

9Question
31 00 00, paras 3.13.1 and 3.13.2Section B, CLINs 0002-0007; Section M, Factor 1CLIN 0002 UNSATISFACTORY EXCAVATION vs. BASE BID: 31 00 00 para 3.13.1 states 'Prepare bids to include the removal of unsuitable material and replacement with select granular material as indicated on the drawings,' which implies inclusion in the CLIN 0001 lump sum, while CLIN 0002 provides a separate unit price for 2,000 CY. Please confirm: (1) all undercut and select granular replacement is paid solely under CLIN 0002 and is not to be included in CLIN 0001; (2) the CLIN 0002-0007 quantities are Government estimates for evaluation and payment will be based on actual quantities installed and accepted; (3) whether FAR 52.211-18, Variation in Estimated Quantity, applies (it is not listed in Section I); (4) the CLIN 0002 measurement method (pre- and post-excavation survey of in-place volume, and by whom); and (5) whether any undercut locations or depths are shown on the drawings.
Answer
1) All removal of unsuitable material and replacement with select granular material that is indicated on the drawings shall be included in the BASE BID, CLIN 0001.

2) CLINs 0002-0007 estimated quantity CLINS. Payment will be based on actual quantities installed and accepted.

3) FAR 52.211-18 (Variation in Estimated Quantity) no longer exists and is "Reserved" in the Revolutionary FAR Overhaul clause set.

4) Measurement methods for estimated quantity for CLIN 0002 will be average end area using pre and post excavation surveys by the contractor's licensed surveyor as reviewed by The Government.

5) No specific undercut locations or depths are delineated by station on the drawings. As indicated on Sheet C001 (General Bid Item Note 2) and Section 31 00 00 paragraph 3.13.1, undercut areas are contingent and will be identified and approved in the field by the Contracting Officer based on proof rolling.

10Question
32 17 23, para 2.2.2.1C211, C212, C220Section B, CLINs 0006 and 0007CLINs 0006/0007 - TYPE I AND TYPE III REFLECTIVE MEDIA (6,250 SF each): Specification 32 17 23 para 2.2.2.1 allows 'FS TT-B-1325, Type I, Gradation A or Type III' without assigning a type to any marking, and Sheets C211/C212/C220 identify markings only as 'reflective' or 'non-reflective.' Please clarify: (1) which markings receive Type I beads and which receive Type III beads; (2) whether the CLINs are measured per SF of completed marking (paint and beads included) or bead material only; (3) whether waterborne paint, non-reflective black outlines, and the reapplication after the 25-day asphalt cure period (G203) are included in CLINs 0006/0007 or in CLIN 0001; and (4) whether temporary markings are required on new pavement before permanent markings are applied.
Answer
(1) Drawing Sheets C211 and C212 designate reflective and nonreflective requirements. Per Sheet C001 (General Bid Item Notes 6 and 7), the specific locations receiving Type I versus Type III reflective media shall be approved by the Contracting Officer prior to performing the work.

(2) CLINs 0006 and 0007 are measured and paid per square foot (SF) of completed painted marking with the designated reflective media applied, as stated in Section B and Sheet C001 Notes 6 and 7 ("for the marking of 6,250 square feet of paint with Type I [or Type III] reflective media").

(3) Completed reflective markings (paint and reflective media, any necessary recoats) are paid under CLINs 0006 and 0007. This includes the non-reflective black borders.

(4) The contract specifications (Section 32 17 23) do not specify or require temporary markings; pavement markings shall be applied in accordance with the contract drawings, phasing plan, and Section 32 17 23.

11Question
32 01 17.16, para 3.5C620, Bituminous Pavement Crack Repair Detail and Joint/Crack Reseal NotesSection B, CLIN 0005CLIN 0005 - ASPHALT CRACK REPAIR (20,000 LF): Taxiways A and B are shown to be milled and overlaid (C620 Details A and B), so the location of crack repair is unclear. C620 Joint/Crack Reseal Note 4 states cracks wider than 2 inches shall be repaired using pothole repair techniques, which has no CLIN. Please clarify: (1) where crack repair applies (existing surface prior to milling, milled surface prior to overlay, or pavements not being overlaid); (2) whether wide-crack/pothole repair is paid under CLIN 0005, included in CLIN 0001, or excluded; (3) the method of measurement; and (4) that the 200 LF test section required by 32 01 17.16 para 3.5 is paid under CLIN 0005.
Answer
1) Crack repair is to occur on the milled surface prior to the overlay.

2) Wide crack/pothole repairs will be paid under CLIN 0005.

3) Per Section B (page 4) and Sheet C001 (General Bid Item Note 5), measurement is by the Linear Foot (LF) of cracks routed, cleaned, and sealed with hot-applied sealant up to the estimated contract quantity of 20,000 LF.

4) When the test section meets the requirements, it may be incorporated into the permanent work and paid for at the contract unit price per linear foot for sealing items scheduled under CLIN 0005.

12Question
32 12 15.13, paras 1.1.2 and 1.2C620, Detail B (leveling course); C310, C320-C323Section B, CLIN 0001HMA PAYMENT AND QUANTITIES: 32 12 15.13 para 1.1.2 uses a unit price of $120 per ton to calculate pay-factor reductions; this value dates from the 2017 design. Please confirm the $120/ton value applies or provide a current value. In addition, C620 Detail B shows a variable-depth leveling course (1.5-inch minimum / 3-inch maximum lifts) and 'mill as required.' Please provide the estimated surface and leveling course HMA tonnage and the milling area/depth used for the Government estimate, or confirm that cross sections C320-C323 are the sole basis for quantities.
Answer
Confirmed. Unit price of $120/ton value will be used to calculate pay-factor reductions.

Confirmed - cross sections of C320-C323 are the sole basis for quantities.

13Question
Not addressed in specificationsG203, Security notes; G200, Keynote 2Section C, Contractor Consent to Background ChecksCONTRACTOR-FURNISHED SECURITY GUARDS: Sheet G203 Security notes and G200 Keynote 2 require the contractor to provide a professional (bonded) security firm with a minimum of two guards at each contractor access gate for the duration of use, guard attendance at a 2-hour workshop at Joint Base Charleston, and vehicle/badge logs. This requirement does not appear in the specifications. Please confirm: (1) whether contractor-furnished security guards are still required; (2) the number and location of contractor access gates (Main Gate only per G200?); (3) the hours guards must be posted (working hours only or 24/7); and (4) whether Government security forces will control access instead.
Answer
1) Confirmed. Contractor-furnished security guards are required.

2) Main Gate will be the primary entrance for contractors. Deviations/alternatives can be addressed on a case-by-case basis.

3) Guards must be present during working hours to allow contractors access to the site.

4) Government Security Forces WILL NOT controll access.

14Question
01 14 00, para 1.2.1.2; 01 35 23, COSPP Sections I.C.7 and I.EG203, Safety notes 13-14 and Airfield Access notesSection C, Passes for Employees; Contractors Working in Controlled or Restricted Areas; Section H, Contractor AccessBASE ACCESS, ESCORTS AND PARKING: Section C references JB Charleston/JBLG-AB/WS worksheets, the Dorchester gate, and escort by the requesting unit within controlled areas. The COSPP prohibits POVs at the project site and requires contractor transport of workers, and G203 requires a flight-line driver briefing with escorts for non-badged haulers. Please confirm: (1) the badging and access process and issuing office specific to NAAF; (2) whether the work area is a controlled/restricted area requiring Government escorts and, if so, whether escort availability will limit work hours (including Sundays); (3) the designated employee parking location; and (4) whether HMA and aggregate truck drivers may be escorted by contractor personnel holding flight-line certification.
Answer
1) Badging and access to the site will be controlled by the contractor-furnished security guards.

2) Work area is not a restricted area, but is controlled and requires Airfield Driving Training. This will need to be accomplished before construction begins.

3) Designated employee parking will be submitted/approved much like contractor laydown locations.

4) HMA and aggregate truck drivers may be escorted by contractor personnel that are Airfield Driving trained.

15Question
01 57 19.00 31, para 3.4.1; 01 57 20.00 31, para 1.11C701-C741 (Erosion Control); G203, Laydown note 10 and Haul Route note 6STORMWATER / LAND DISTURBANCE PERMIT CONFLICT: 01 57 19.00 31 para 3.4.1 states the Contracting Officer has already obtained a Land Disturbance Permit and approved SWPPP, with the contractor registering as co-permittee. 01 57 20.00 31 para 1.11 states the contractor must complete the NOI, with Joint Base Charleston as primary permittee. Given the 2017 design date, please confirm: (1) whether a current, valid SCDES (formerly SCDHEC) land disturbance permit and SWPPP exist for this project and will be furnished; (2) which party prepares and submits the NOI and pays permit fees; (3) whether retention of an SC-registered PE for erosion control oversight and final certification (para 3.4.1) is required; and (4) the anticipated permit timeline relative to NTP.
Answer
The contractor must complete the NOI and permit on the behalf of the Gov't. The Gov't does not have an approved Land Disturbance Permit, but has a DOR SWPPP plan that can be provided. Section 01 57 19.00 31, paragraph 3.4.1 explicitly requires the Contractor to retain a South Carolina Registered Professional Engineer (PE) to oversee erosion and sediment control implementation, conduct required reviews/inspections, and provide final certification for submission to the regulatory agency upon project completion. All stormwater permitting submittals, regulatory approvals, and NOI processing must be executed promptly following contract award and completed prior to ground-disturbing activities. This review and approval timeline is accommodated within the upfront 60-day mobilization and pre-construction submittal period preceding on-site physical construction.
16Question
26 56 20.00 10; 22 05 83.63E000-E408Attachment 8 - Wage Determination SC20260040WAGE DETERMINATION: Attachment 8 (SC20260040, Construction Type: Highway) does not include electrician or other classifications required for the airfield lighting work (Section 26 56 20.00 10, E-series sheets) or CIPP lining (Section 22 05 83.63). Please confirm whether an additional wage determination (e.g., Heavy) will be incorporated for this work, or whether the missing classifications will be added by conformance (SF 1444) after award, so that all offerors price labor on the same basis.
Answer
SC WD for Heavy will be added to the solicitation by modification.
17Question
26 56 20.00 10, Part 1 and paras 2.4.11, 2.4.12E000-E408; G200AIRFIELD LIGHTING: Spec 26 56 20.00 10 para 2.4.11 marks Constant Current Regulators as 'Not Used,' para 2.4.12 calls for lamps 'of size and type indicated,' and guidance signs are specified as LED. Please confirm: (1) whether new edge/centerline fixtures are LED or incandescent; (2) that existing CCRs and vault equipment remain and are compatible with the new fixtures and LED signs; (3) whether existing light bases, cable and duct are reused or replaced; (4) that the contractor provides and maintains temporary 'jumpers' for active pavement lighting during closures (COSPP I.A.4.c); and (5) whether the one-day on-base airfield electrical workshop is still required and its location.
Answer
(1) All new taxiway edge fixtures are semi-flush LED, and all new airfield guidance signs are LED , as indicated on Sheets E000, E201, E202, E401, and the specifications.

(2) Confirmed. Regulators are marked "Not Used" because no new CCRs or vault work are included in the contract scope; circuits tie into existing infrastructure.

(3) As shown on Sheets E101, E102, E201, E202, and E301, existing fixtures, bases, wiring, and duct banks within the project limits are demolished and replaced with new base cans, cabling, counterpoise, and conduits.

(4) Confirmed. Per Sheet E000 Note 33 and the COSPP, the contractor shall furnish and maintain temporary jumpers and connections to keep lighting systems outside the active work zone operational.

(5) Confirmed. Per Section 26 56 20.00 10 and Sheet E000 Note 7, the contractor's electrical personnel shall attend the mandatory airfield electrical workshop on base prior to performing work.

18Question
22 05 83.63; 02 01 00 (Geotechnical Report - Storm Drain Pipe Crossing)C301, C302, C630, C631Section B, CLIN 0001CIPP LINING SCOPE: Specification 22 05 83.63, Cured-In-Place Pipe Lining, is included and the geotechnical report references a Taxiway Alpha storm drain pipe crossing, but no CLIN or clear quantity is provided. Please identify the drawing sheet(s) showing the CIPP work, the host pipe material, diameter, length and number of runs, confirm the work is included in the CLIN 0001 lump sum, and state whether pre- and post-lining CCTV inspection is required.
Answer
Drawing sheet C301, Keynote 2 shows locations with CIPP work. Confirmed, this work is included in CLIN 0001. Specifications Section 22 05 83.63, Para 3.1.4 states "Perform a final CCTV inspection to verify that the composite liner has cured and that the integrity of the liner is maintained."
19Question
01 50 00, paras 3.5.2 and 3.6.1G200 (Laydown Area); G203, Laydown notes 2-4 and 13GOVERNMENT FIELD OFFICE AND TEMPORARY UTILITIES: 01 50 00 para 3.6.1 requires an approximately 200 SF Resident Engineer's office with heat, power, and toilet facilities connected to water and sewer. G203 Laydown notes 2-4 require the contractor to bear all costs to bring electrical, water and sewer service to the laydown area and state that the capacity of the existing power source is unknown. Please confirm: (1) the Government field office is required for this project; (2) whether sewer service is available near the laydown area or whether a self-contained restroom-equipped office trailer is acceptable; and (3) the location and characteristics (voltage/phase) of the nearest available power source.
Answer
1) Confirmed. Government field office is required.

2) Self-containted restroom-equipped office trailer is acceptable.

3) Location and characteristics of nearest available power source is unknown and will need be coordinated after submittal of site plan but before install of temporary facilities.

20Question
SF 1442 Items 12b and 13b; Section C, Performance and Payment Bond Requirements; Section L, para 2.d and 4.e; 52.228-1(c) and (d)BID GUARANTEE AND BOND TIMING: SF 1442 Item 12b requires performance and payment bonds within 10 calendar days after award; Section C states within 15 days of award; 52.228-1(d) states within 10 days after receipt of forms. 52.228-1(c) reads '20 percent of the bid price or $____, whichever is less' with the dollar amount left blank, and SF 1442 Item 13b does not indicate whether an offer guarantee is required. Please confirm: (1) the bid guarantee is 20% of the total of CLINs 0001-0007 with no dollar cap; (2) whether performance and payment bonds are due in 10 or 15 calendar days; and (3) whether a scanned SF 24 uploaded through DoD SAFE is acceptable, or whether the original bid bond must be physically delivered before the proposal due time and, if so, to what address.
Answer
1. Confirming the bid guarantee is 20% of the total of CLINS 001-0007.

2. Performance and payment bonds are due in 10 calendar days.

3. A scanned SF 24 uploaded through DoD SAFE is acceptable.

21Question
SF 1442 Item 13a; Section L, paras 1.a, 2 and 4.cPROPOSAL SUBMISSION METHOD: Section L para 2 requires the Price Proposal in an 'original and one (1) copy,' SF 1442 Item 13a refers to sealed offers delivered to the Item 8 address, and Section L para 4.c requires submission through DoD SAFE. Please confirm that proposals will be accepted electronically through DoD SAFE only, whether Part I and Part II must be separate files, any file size or format limits, and that the 12:00 PM local time, 02 December 2026 deadline applies to receipt of the DoD SAFE upload.
Answer
1. Proposals will be accepted electronically through DoD SAFE only. Offerors are cautioned not to wait until the 11th hour to request a DoD drop off code from the Contract Specialist and C.O.

2. Part I and Part II must be separate files. No listed file size or format limits, other than the page limit stated herein.

3. The 12:00 PM EST, 02 December 2026 deadline applies to the receipt of the DoD SAFE upload.

22Question
Section L, paras 2.b and 3.b; Section M, Basis of Award and Factor II(e)SECTION L/M CLARIFICATIONS: (1) Section L para 2.b references pricing 'all Bid Options,' but Section B contains no option CLINs. Please confirm there are no options. (2) Section M states past performance is 'significantly more important than cost or price,' while Factor II(e) describes evaluating offers in price order and awarding to the first offeror rated Substantial Confidence. Please confirm the award methodology. (3) Section L para 3.b limits submissions to three contracts total for the prime and major subcontractors and asks offerors to 'show ability to provide a work force capable of gaining clearance into a secure facility.' Please clarify the type of clearance contemplated (e.g., NCIC/installation access vs. a personnel security clearance) and what documentation is expected.
Answer
1. CLINS 0002-0007 are Estimated Quantity CLINS and will be awarded at the proposed price. The Solicitation shall be amended to reflect EST for each CLINS.

2. Correct, this will not be a low price, technically acceptable award evaluation. Insted it will be a best value award decision, where past performance is significantly more important than price.

3. No requirements other than typical JBLG Base access will be required.

23Question
Section C, Business License Tax - South Carolina; Section C, Contractors Responsibilities while Working within Controlled or Restricted AreasBUSINESS LICENSE / ADMINISTRATIVE CARRYOVER: Section C states that City of North Charleston and Goose Creek business license taxes apply to work at JBLG-Air Base and Weapons Station. This project is at North Auxiliary Airfield in Orangeburg County. Please confirm whether these municipal business license requirements apply to this project, or identify the applicable local jurisdiction. Section C also contains the text 'FA441826R00130006 Page 5 of 51' within a paragraph; please confirm this is an administrative carryover from another solicitation and has no effect on this RFP.
Answer
Contractors are advised to confirm permitting requirements, if any, with Orangeburg county and the city of North, SC.

Solicitation to be amended to remove 'FA441826R00130006 Page 5 of 51'

24Question
01 11 00, paras 1.4.1 and 1.4.2; 01 14 00, para 1.3.5.1.2; 01 45 00, paras 1.3 and 1.9.1; 01 35 26, para 1.5.2.1.a; 01 32 16.00 20, Part 1DIVISION 01 ADMINISTRATIVE CONFLICTS: Please resolve the following: (a) 01 11 00 para 1.4.1 requires 72-hour notice before excavation, while 01 14 00 para 1.3.5.1.2.d requires 48 hours; (b) 01 11 00 para 1.4.2 requires outage/road closure requests 21 days in advance, while 01 14 00 requires dig permit requests 14 days in advance; (c) 01 45 00 para 1.3 requires CQC and Production Reports weekly by 10:00 AM the following week, while 01 45 00 para 1.9.1 and 01 35 26 para 1.5.2.1.a refer to daily CQC reports - please confirm reports are prepared daily and state the required submission frequency; and (d) 01 32 16.00 20 references schedule coordination with 'Galley Management/CENMP' - please confirm the Government office that will review schedules and submittals.
Answer
a) 01 14 00 para 1.3.5.1.2.d outlines the JB Charleston Dig Permit Process which requires 48 hours notice for excavation. This project, as stated in 01 11 00 para 1.4.1 requires 72-hour notice before excavation. 72 hours notice WILL BE REQUIRED before excavation.

b) Nothing to resolve or deconflict here. Both are accurate, outage and road closure requests are required 21 days in advance and dig permit requests are required 14 days in advance.

c) Confirmed. CQC reports are completely daily, compiled, and are submitted weekly by 10:00 AM the following week.

d) Schedule coordination will occur with 628 CES/CENMP - Project Execution Section.

25Question
01 30 00, paras 1.3.1 and 1.3.2; 01 45 00, paras 1.4, 1.5.1 and 1.5.2; 01 35 26, paras 1.5.1.1 and 1.5.1.2; 01 35 23, para 1.3.c-d; 01 35 13, para 3.1.8; 26 56 20.00 10, Part 1G203, Safety note 3 (Radios & ATC) and Construction Workshop notesSITE SUPERVISION AND DUAL/TRIPLE-HATTED POSITIONS: Please clarify the minimum on-site supervision and which positions may be combined for this project. (a) 01 35 26 para 1.5.1.2 states the 'Contractor Quality Control Person can be the SSHO on this project.' Please confirm the QC Manager may also serve as the SSHO (dual-hatted), provided the individual meets both the EM 385-1-1 SSHO requirements and the 01 45 00 para 1.5.1.2 qualifications. (b) 01 45 00 para 1.5.1.1 states the QC Manager may not perform superintendent duties. Please confirm the Superintendent may serve as the SSHO or alternate SSHO if qualified, so that either a Superintendent/SSHO + QCM or a Superintendent + QCM/SSHO organization is acceptable. (c) Please confirm whether one individual may serve as QC Manager, SSHO, and the COSPP/SPCD compliance monitor required on site during active construction (01 35 23 para 1.3.d) (triple-hatted), and whether the English-speaking tower radio operator (01 35 13 para 3.1.8; G203 Safety note 3) may be one of these individuals or must be a dedicated person while work is in the landing area. (d) Because Work Area 1 is Tuesday-Saturday and Work Area 2 is Friday-Sunday, work may occur six days per week; 01 45 00 para 1.4 prohibits work unless the QC Manager is on site, and para 1.5.2 limits the Alternate QC Manager to 30 workdays per year. Please confirm the Alternate QCM may cover scheduled weekend shifts without counting against that limit. (e) Please confirm whether a qualified subcontractor superintendent may serve as the Contractor's superintendent under 01 30 00 para 1.3.2 when that subcontractor is the only trade on site, and whether the 10-year/5-year experience requirement also applies to an alternate superintendent. (f) Please confirm whether the Project Manager may be off site. (g) Please confirm the location (JB Charleston or NAAF) of the one-day asphalt and one-day electrical workshops (G203; 26 56 20.00 10 Part 1) and which personnel must attend.
Answer
a) Confirmed. QC Manager may also serve as the SSHO (dual-hatted), provided the individual meets both the EM 385-1-1 SSHO requirements and the 01 45 00 para 1.5.1.2 qualifications.

b) Confirmed. Superintendent may serve as the SSHO or alternate SSHO if qualified, so that either a Superintendent/SSHO + QCM or a Superintendent + QCM/SSHO organization is acceptable.

c) Confirmed. One individual may serve as QC Manager, SSHO, and the COSPP/SPCD compliance monitor required on site during active construction (01 35 23 para 1.3.d) (triple-hatted), and the English-speaking tower radio operator (01 35 13 para 3.1.8; G203 Safety note 3) may be one of these individuals.

d) Confirmed. The Alternate QCM may cover scheduled weekend shifts without counting against that limit.

e) A qualified subcontractor superintendent MAY NOT serve as the Contractor's superintendent under 01 30 00 para 1.3.2 when that subcontractor is the only trade on site.

e.2) Confirmed. The 10-year/5-year experience requirement also applies to an alternate superintendent.

f) Confirmed. The Project Manager may be off site.

g) Confirmed. The location of the one-day asphalt and one-day electrical workshops will be at NAAF. G203 clearly lays out the required attendees.

"Workshops: Contractor shall send primary participants of the construction team to attend construction workshop (one day asphalt paving, one day electrical).

Attendees: At a minimum, the project superintendent, qulaity control personnel, testing laboratory personnel, inspectors, plant operators, paving foreman, pavement placement and pavement equipment operators shall attend all applicable workshops."

26Question
32 92 19, paras 2.1.2-2.1.4; 32 92 23, paras 2.1.4 and 3.x (final acceptance - sod rooted to withstand jet blast)C620, Detail C (New TWY Shoulder) and Detail D; C701-C722 (Erosion Control Plans)SEEDING vs. SODDING LIMITS AND TURF ESTABLISHMENT: Both Section 32 92 19 (Seeding - Common Bermuda / rye mixtures by season) and Section 32 92 23 (Sodding - 100% Tifway 419 Bermuda) are included, but the drawings do not clearly delineate which disturbed areas receive sod and which receive seed. C620 Details C and D show a 4-inch topsoil strip with a '1.5-inch drop after sodding' at pavement edges, and 32 92 23 requires sod sufficiently rooted to withstand jet blast for final acceptance. Please clarify: (1) the limits and estimated quantity (SY) of sod vs. seed, including whether sod is required only within a specified width of pavement edges (shoulders, access road) and seed elsewhere; (2) whether temporary seeding is acceptable where permanent planting falls outside the specified planting season; and (3) the turf establishment period and acceptance criteria that must be met before final acceptance, and whether that establishment period is included within the contract performance period shown on G203 ('All Turf Fully Established').
Answer
Reference Drawing Sheets C201 and C202. These drawings CLEARLY delineate which areas receive sod and which receive seed. Final acceptance criteria can be found in Sections 32 92 19 and 32 92 23.
2702 41 00, para 1.8; 32 17 23, para 3.4.1Question
Section 02 41 00, paragraph 1.8 requires removal of debris that may appear on operational aircraft pavements due to the Contractor's operations, and Section 32 17 23, paragraph 3.4.1 requires the aircraft operating area to be vacuum swept before it is opened for aircraft operations. Please confirm what FOD removal equipment the Contractor is expected to use on haul routes and paved surfaces, whether a towed friction mat or rotary brush sweeper is acceptable, including for the sweep in paragraph 3.4.1, and clarify by amendment. For reference, FAA AC 150/5370-2G paragraph 2.11 requires FOD to be continuously removed during construction on civil airports, and AC 150/5210-24A describes friction mat and rotary brush sweepers as FOD removal equipment.
Answer
Confirmed. Towed friction mat and rotary brush sweepers are acceptable means of FOD removal.
28Section H, Site Visit Instructions, Para 1 (Pre-Proposal Conference/Site Visit)Amendment 0001, SF 30 Block 14 Continuation Page, Summary of Changes, Item (a)Question
Section H, Site Visit Instructions, Paragraph 1 of the solicitation states that the deadline for all questions is 12 November 2026 at 9:00 AM EST. Amendment 0001, Block 14, Item (a) states that questions are due back to the Government on or before 10 November at 1200, with no time zone stated. Please confirm which deadline governs. If the 10 November date governs, will the Government accept and answer questions received after 10 November but before 12 November 2026 at 9:00 AM EST?
Answer
The deadline that governs is 12 November 2026 at 9:00 AM EST. The Government will accept and answer questions received after 10 November but before 12 November at 9:00 AM EST.
29Contract drawings - general (applies to multiple sheets)Question
The scaling on the plans appears to be off. Please confirm the scales and revise drawings where applicable.
Scales do not appear to be incorrect. Drawings will not be revised.
30SF 1442 Block 13a; Section L, Paras 1.a, 2, and 4.cQuestion
SF 1442 Block 13a calls for sealed offers delivered to the place specified in Item 8, but Item 8 is blank. Section L, Para 1.a calls for two separately bound parts, and Para 2 calls for an original and one copy of the Price Proposal. Section L, Para 4.c says proposals shall be submitted via DoD SAFE. Please confirm that DoD SAFE is the only acceptable submission method and that no hard copies are required. Please also confirm whether Part I (Price) and Part II (Past Performance) should be uploaded as separate PDF files, and whether there are any file naming or file size requirements.
Answer
1. Confirming DoD SAFE is the only acceptable submission method and no hard copies are required. Part I and Part II shall be uploaded as separate PDF files. See previous answer relative to file size requirements. Avoid file names longer than 100 characters and special characters like a colon or pound sign.
31Section C, Proposal Bond; Section L, Para 2.dStandard Form 24Question
Section C and Section L, Para 2.d require a Proposal Bond (SF 24) at 20% of the proposal price. With electronic submission via DoD SAFE, will a scanned copy of the executed bond be accepted? If the original bond with wet signatures and surety seal is required, please provide the delivery address, the deadline, and whether it must arrive by the proposal due date and time.
Answer
A scanned copy of the executed bond will be accepted.
32SF 1442 Block 12b; Section C, Proposal Bond paragraphQuestion
SF 1442 Block 12b states performance and payment bonds are due within 10 calendar days after award. Section C states the Performance Bond (SF 25) and Payment Bond (SF 25-A) are due within 15 days of award. Please confirm which timeframe governs.
Answer
Performance and payment bonds are due within 10 calendar days after award.
33Section B, CLINs 0001-0007; Section L, Para 2.b; Section M, Factor 1Question
Section L, Para 2.b instructs offerors to price all Bid Options, but Section B contains only CLINs 0001 through 0007 and no option CLINs. Please confirm there are no options. Please also confirm that the work in CLINs 0002 through 0007 is excluded from the CLIN 0001 Base Bid, so that offerors do not price the same work twice.
Answer
Confirmed. No bid options. CLINs 0002-0007 quantities are Government estimates for evaluation and determination of a unit price. Payment will be based on actual quantities installed and accepted. These are seperate from the CLIN 0001 Base Bid.
34Section K; Section L, Para 2.cSAM.gov Representations and CertificationsQuestion
Section L, Para 2.c states that Section K shall be returned in its entirety. Will the Government accept the offeror's current SAM.gov representations and certifications in place of provisions already covered in SAM, so that only the Section K fill-ins not covered by SAM must be completed and returned?
Answer
Section K is to be completed and returned only if the existing SAM registration conflicts.
35Section L, Para 3, 3.a, and 3.b; Section JQuestion
Section L, Para 3 limits Past Performance Information to three pages per contract. Please confirm (1) any font size, margin, and page size requirements; (2) whether customer letters, metrics, and surveys provided under Para 3.a count toward the three-page limit; and (3) whether offerors should send a Government Past Performance Questionnaire to references, since Para 3.b refers to Past Performance Surveys but no questionnaire is listed in Section J.
Answer
Times new roman or similar font, 12 pt or equal, 8 1/2" x 11" page or equivalent. Customer letters, metrics and surveys count towards the page limit and a past performance questionnaire will be added to the solicitation. Offerors are advised to state if a CPAR exists for past work.
3601 14 00, Para 1.2.1.2Section L, Para 3.bQuestion
Section L, Para 3.b requires offerors to show the ability to provide a workforce capable of gaining clearance into a secure facility. What documentation will satisfy this requirement (for example, a narrative, a statement of compliance, or evidence of prior base access on other DoD projects)? Does this refer only to standard installation access credentials, or to a personnel security clearance?
Answer
The past performance evaluation will determine relevancy of past work, which includes the ability to gain access to and work effectively on Base.
37SF 1442 Block 13aQuestion
SF 1442 Block 13a states offers are due by 12:00 PM local time on 02 Dec 2026. Please confirm that local time means Eastern Time, the time zone of the issuing office.
Answer
Confirming that local time means Eastern Standard Time.
38Combined Specifications cover page and headersAttachment 7 - Combined SpecificationsQuestion
The Combined Specifications (Attachment 7) are dated April 21, 2017, are labeled 100% Design Submittal, and carry JBC Project No. SBML 12-1100, while the solicitation references SBML 1052018. The Construction Phasing Plan cites the 2008 edition of UFC 3-260-01. Please confirm that the 2017 specifications and drawings are the final, current documents for this project and that no updated or sealed issued-for-construction set will be provided.
Answer
This project was originally designed in 2017 and sat on the shelf until authority to advertise in 2026.

1) The original design proejct number was SBML 12-1100. The current construction project number is SBML 1052018. They are the same project.

2) Current edition of UFC 3-260-01 governs.

3) Confirmed. These documents are complete and final design for this project and no later revisions exist.

3931 00 00; 32 11 23Section B, CLINs 0003 and 0004Attachment 7 - Combined SpecificationsQuestion
Section B includes CLIN 0003 (Cement Stabilized Subgrade, 4,000 SY) and CLIN 0004 (1200 BX Tensar Geogrid or approved equal, 4,000 SY), but the Combined Specifications contain no section for cement-stabilized subgrade or geogrid. Please provide the specification requirements for these items (cement content, depth, mix design, testing, and geogrid installation). Please also confirm where these items apply on the drawings, or whether they are contingency items to be used only as directed by the Contracting Officer.
Answer
1) CLIN 0003 is an estimated quanity of cement stabilized subgrade in the event that unsuitable subgrade is found during excavation/milling operations and needs to be resolved using stabilization methods. CLIN 0004 is an estimated quanity of geogrid in the event that unsuitable subgrade is found during excavation/milling operations and needs to be resolved using geogrid methods.

2) CLINs 0002-0007 quantities are Government estimates for evaluation and determination of a unit price. Payment will be based on actual quantities installed and accepted.

3) FAR 52.211-18 Variation…