Attachment 1 - SBML 1052018 - Total Performance Time.pdf
PDF 94 KB Posted
- Solicitation number
- FA441827R0002
About this file
This is a Performance Time Tabulation Form for a federal construction contract titled "SBML 1052018: REPAIR NAAF TAXIWAY ALPHA & BRAVO." The form establishes the contract performance schedule and timeline for a taxiway repair project at a naval air facility.
The project award is estimated for 1-Mar-27, with a Notice to Proceed (NTP) guesstimate three months following award. The mobilization and submittal preparation period is 112 calendar days, including pre-construction submittals per Division 01 specifications and mobilization activities. An additional period is allocated for special order materials (AHUs, chillers, PEMBs, and equipment) with a lead time of 21-Jun-27. The construction start date is 21-Jun-27, with zero construction days currently calculated and zero inclement weather budget days allocated. The DOR calculated calendar days of construction, including inclement weather contingency, total 30 days. Construction completion is scheduled for 21-Jul-27, followed by a 30-day closeout period with 45 calendar days allocated for closeout submittals in accordance with specification section 01 78 00, concluding on 20-Aug-27. The total contract days are 172 calendar days, and the period of performance is 172 days. The form includes a monthly breakdown from March 2027 through August 2028 showing inclement weather day averages per specification 01 32 00, paragraph 3.3.8.1, though currently no inclement weather days are factored into the schedule. Performance time data is linked to the Liquidated Damages tab for coordination with the contracting office.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1-Mar-27 Insert a safe NTP guesstimate (ToT + 3 months) 112 Insert # days for Pre-Construction Submittals (Division 01) & Mobilization (60 Calendar Days)
Insert # days for Special Order Materials (AHUs, Chillers, PEMBs, Equipment, etc.)
21-Jun-27
Number of Construction Days: 0 Excludes weekends, holidays, etc.
0 Inclement Weather Budget DOR Calculated Calendar Days of Construction, Including Inclement Weather 30
Construction Complete 21-Jul-27
Number of Closeout Days: 30
Insert # days for Closeout Submittals IAW 01 78 00 (45 Calendar Days)
20-Aug-27
Month
Days In
Month
Average Inclement Weather
Days/Month (Ref.
Spec 01 32 00, para
3.3.8.1)
Number of Construction Days/Month
% of Days of Month
Construction
Possible Inclement Weather Days Per
Month
Non-constructi on days.
(Holidays, weekends, etc.)
Verify the # Days in Month & # of Inclement Weather Days correctly coorelates to the # of Days per month in 01 32 00, para 3.3.8.1
July 2009 31 14 0 0% 0 Mar-27 31 9 0 0% 0 Apr-27 30 7 0 0% 0 May-27 31 5 0 0% 0 Jun-27 30 4 0 0% 0 Jul-27 31 6 0 0% 0 Aug-27 31 6 0 0% 0 Sep-27 28 5 0 0% 0 Oct-27 31 5 0 0% 0 Nov-27 30 5 0 0% 0 Dec-27 31 5 0 0% 0 Jan-28 30 8 0 0% 0 Feb-28 31 9 0 0% 0 Mar-28 31 9 0 0% 0 Apr-28 30 7 0 0% 0 May-28 31 5 0 0% 0 Jun-28 30 4 0 0% 0 Jul-28 31 6 0 0% 0 Aug-28 31 6 0 0% 0
Total: 0 Total: 0 0
Insert current date (data linked to Liquidated Damages tab).
Performance Time Tabulation Form
SBML 1052018: REPAIR NAAF TAXIWAY ALPHA & BRAVO
21-Jul-26
Instructions:
Insert Project Number and Title (data linked to Liquidated Damages tab).
Special Order Materials Lead Time:
Insert estimated NTP.
Insert number of Mobilization & Submittal Preparation days you are allowing.
Insert number of days for any Special Order Materials Lead Time you are allowing.
Insert the Number of Construction Days/Month for each month without consideration of inclement weather days.
Insert the % of Month Impacted by Inclement Weather Total number of Contract Days is displayed below.
Construction Complete Date is displayed below.
Performance Time tab data is linked to the Liquidated Damages tab. Coordinate current LD rates with Contracting.
Project Award Mobilization & Submittal Preparation:
"Construction Time" = Period of Performance (PoP) =
Construction Start Date:
Number of Inclement Weather Days:
Total Contract Days:
Estimated Contract Completion Date: