Attachment 7 - DKGV 1137999 Asbestos Lead Report.pdf
PDF 5 MB Posted
- Solicitation number
- FA441826R0013
About this file
This document is a Contracting Officer's Representative (COR) memorandum transmitting asbestos and lead paint survey results for Naval Reserve Center Building B3370 at Joint Base Charleston, South Carolina, along with a comprehensive Asbestos & Lead Paint Inspection Report dated January 10, 2025.
The asbestos survey, conducted December 2-3, 2024, identified asbestos-containing material (ACM) in exterior caulking associated with white window caulking around the northeast exterior door, measuring approximately 10 linear feet and containing 2% chrysotile asbestos. The survey determined that removal of this asbestos is not required for the project as the amount is minimal and will not be disturbed during construction. Lead paint sampling identified lead above laboratory detection limits in gray exterior door paint (0.052% by weight) and gray exterior roof paint (0.018% by weight), but neither exceeded South Carolina Department of Environmental Services (SCDES) regulation limits of 0.06% by weight. The COR noted that contractors will be notified of the lead-painted areas on the roof. The inspection report documents 46 bulk asbestos samples and 6 lead paint samples collected from the 20,000 square-foot building. Laboratory analysis was performed by EMSL Analytical, Inc. using Polarized Light Microscopy (PLM) for asbestos and atomic absorption for lead. The report includes detailed regulatory overviews of NESHAP, SCDES, and OSHA standards; photographic documentation; and laboratory analytical reports. The recommendation is to inform contractors of lead-containing paints and ensure OSHA lead-in-construction standards are followed during renovation activities.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
HEADQUARTERS 628TH AIR BASE WING (AMC)
JOINT BASE CHARLESTON SC
13 March 2026
MEMORANDUM FOR 628 CONS
FROM: 628 CES/CENMP
628th Civil Engineering Squadron Joint Base Charleston SC 29404
SUBJECT: Contracting Officer’s Representative (COR) Data, DKGV 1137999- Repair Naval
Reserve Center - B3370
As part of the design process for this project, an asbestos and lead paint survey was conducted on December 2 and 3, 2024. The results indicate that asbestos is present in the exterior caulking associated with the white window caulking around the northeast exterior door, measuring approximately 10 linear feet. Additionally, lead was identified in the gray exterior door and the gray exterior roof paint. Removal of the asbestos is not required for this project, as the amount found is minimal and will not be disturbed during construction. Similarly, the lead-painted areas are also minimal, so we will only need to notify the contractor of their existence on the roof.
Please see the attached report for further details.
Jonnathan Vargas-Sanchez, DAF Project Manager / COR 628 Civil Engineering Squadron
Asbestos & Lead Paint Inspection Report JBC Building 3370
1050 Remount Road, North Charleston, SC
January 10, 2025 | Report Number: EN247340
Prepared for:
Pond & Company 3500 Parkway Ln Suite 500 Norcross, GA 30092
1800 Reynolds Avenue Charleston, SC 29405
P (843) 277-8461 F (843) 277-1234
Terracon.com
January 10, 2025
Pond & Company 3500 Parkway Ln Suite 500 Norcross, GA 30092
Attn: Mr. Glenn Martin P: (706) 255-0852 E: MartinGI@pondco.com
Re: Asbestos & Lead Paint Inspection Report JBC Building 3370 North Charleston, South Carolina 29406 Terracon Project No. EN247340 Survey Conducted: December 2, 2024 and December 3, 2024
Dear Mr. Martin:
Terracon Consultants, Inc. (Terracon) is pleased to present the results of the asbestos and lead paint inspection performed on the above referenced site. We understand that this survey was requested due to future planned renovations of the building.
Terracon appreciates the opportunity to provide environmental consulting services for the Pond & Company. If you should have any questions regarding this report, or if you need assistance with bid documents or project oversight during the building renovation, please contact the undersigned at
(843) 277-8461.
Sincerely, Terracon Consultants, Inc.
Andrew Mitroka Norman E. (Gene) Partin, Jr., CHMM Project Manager Department Manager
Facilities | Environmental | Geotechnical | Materials i
TABLE OF CONTENTS
EXECUTIVE SUMMARY........................................................................................................................................... ii
1.0 INTRODUCTION
2.0 BUILDING DESCRIPTION
3.0 ASBESTOS INPSECTION
3.1 Regulatory Overview
3.2 Visual Assessment
3.3 Physical Assessment
3.4 Sample Collection
3.5 Sample Analysis
3.6 Findings
3.7 Recommendations
4.0 LEAD PAINT SAMPLING
4.1 Regulatory Overview
4.2 Sampling and Analytical Protocol
4.3 Sample Collection
4.4 Findings
5.0 LIMITATIONS / GENERAL COMMENTS
TABLES
Table 1 - Asbestos Sample Summary Table 2 - Lead Paint Sample Summary
FIGURES
Figure 1 - Sample Location Diagram
APPENDIX A – PHOTO DOCUMENTATION
APPENDIX B – LABORATORY REPORTS
Asbestos Analytical Laboratory Data Lead Paint Analytical Laboratory Data
APPENDIX C – INSPECTOR CREDENTIALS
Asbestos & Lead Paint Inspection Report JBC Building 3370 N. Charleston, South Carolina January 10, 2025 Terracon Project No. EN247340
Facilities | Environmental | Geotechnical | Materials ii
EXECUTIVE SUMMARY
This executive summary is intended as an overview for the convenience of the reader. The report should be reviewed in its entirety prior to making any decisions regarding this site.
Terracon Consultants Inc. (Terracon) conducted an asbestos and lead paint inspection of Building 3370 on Joint Base Charleston in North Charleston, South Carolina. The site structure is approximately 20,000 square-feet (SF). It was our understanding that Pond & Company has planned renovations of the building. The purpose of this inspection was to sample and identify suspect asbestos-containing materials (ACM) and provide information regarding the identity, location, condition and approximate quantities of ACM in both interior and exterior building components. An ACM is defined as containing asbestos at a concentration greater than 1%. The objective of the lead paint inspection was to identify lead containing paint systems on building components that may require special handling and disposal considerations upon demolition of the structure.
The inspection was performed on December 2, 2024 and December 3, 2024 by a South Carolina Department of Environmental Services (SCDES) licensed asbestos inspector in general accordance with our Proposal dated Task Order dated November 7, 2024, and the sampling protocols established in EPA 40 CFR 763 (Asbestos Hazard Emergency Response Act, AHERA) and the SCDES Regulation 61-86.1 Standards of Performance for Asbestos Projects. Paint samples were collected from visible and accessible building components and paint systems and submitted to an Environmental Laboratory Accreditation Program (ELAP) approved laboratory for analysis of lead.
Forty-six (46) bulk samples were collected from homogeneous areas of suspect ACM. Six (6) paint-chip samples were collected from the components of the structure on the site.
Findings
Based on the results of laboratory analysis:
Asbestos
Exterior Caulking (2% Chrysotile) associated with white window caulking of the exterior door on the northeast side of the building, approximately 10 linear-feet (LF).
Lead Paint
Lead was not identified above SCDES regulation limits in any of paint chip samples. However, lead was identified above laboratory detection limits in the following samples
Gray exterior door paint (0.052% by wt) Gray exterior roof paint (0.018% by wt)
January 10, 2025 Terracon Project No. EN247340
Facilities | Environmental | Geotechnical | Materials iii
Recommendations
Based on the scope of services, limitations, and findings of this assessment:
Terracon recommends removal of the asbestos-containing materials by a South Carolina licensed asbestos abatement contractor.
Inform contractors of lead containing paints. The OSHA lead in Construction Standard will need to be followed to protect workers during renovation activities that may disturb lead painted systems.
January 10, 2025 Terracon Project No. EN247340
Facilities | Environmental | Geotechnical | Materials 1
1.0 INTRODUCTION
Terracon Consultants, Inc. (Terracon) conducted an asbestos and lead paint inspection of Building 3370 on Joint Based Charleston in North Charleston, South Carolina. The inspection was conducted on December 2, 2024 and December 3, 2024, by a SCDES licensed building inspector in general accordance with our proposal dated November 7, 2024. We understand the asbestos and lead paint inspection was requested due to the planned renovation of the structure.
2.0 BUILDING DESCRIPTION
The referenced building is a single-story approximately 20,000 SF office space located on Joint Base Charleston in Charleston, South Carolina. The exterior of the building is a brick façade with metal exterior doors and windows. The roof is a flat rolled roofing system with metal capped parapet walls. Interior flooring consists of carpeted areas, vinyl floor tiling, and ceramic floor tiling. The walls consisted of CMU block and gypsum wallboard system with a cove base finish. The ceiling is generally a drop ceiling tile system underneath a gypsum ceiling with a spray-applied texture in the halls. Multiple roof-mounted HVAC systems were observed with metal ductwork running throughout the building and above the drop-ceiling.
3.0 ASBESTOS INPSECTION
The asbestos inspection was conducted by SCDES licensed Asbestos Building Inspector Mr. Andrew Mitroka;
(License No. BI-01871, exp. 7/13/25). A copy of Mr. Mitroka’s license is included in Appendix C. The inspection was conducted on December 2, 2024 & December 3, 2024, in general accordance with the sampling protocols established by EPA Regulation 40 CFR 763 Subpart E 763.86, AHERA and SCDES R61-86.1. A summary of inspection activities is provided below.
3.1 Regulatory Overview
NESHAP
Environmental Protection Agency (EPA) regulation 40 CFR 61, Subpart M, National Emission Standards for Hazardous Air Pollutants (NESHAP), prohibits the release of asbestos fibers to the atmosphere during renovation/demolition activities. NESHAP requires that potentially regulated asbestos-containing building materials be identified, classified and quantified prior to planned disturbances or demolition activities. An ACM is defined as any material containing asbestos of any type in an amount greater than one percent (1%). The asbestos NESHAP regulates asbestos fiber emissions and asbestos waste disposal practices. Under NESHAP, asbestos-containing building materials are classified as either friable, Category I non-friable or Category II non-friable ACM. Friable materials are those that, when dry, may be crumbled, pulverized or reduced to powder by hand pressure. Non-friable materials contain asbestos fibers which have been “locked in” by a bonding agent, coating, binder or other materials so that the asbestos is bound and will not readily release fibers during normal handling or use. Category I non friable ACM includes packing materials, gaskets, resilient floor coverings and asphalt roofing products containing more than 1 percent (%) asbestos. Category II non-friable ACM are non-friable materials other than Category I materials that contain more than 1% asbestos.
Regulated Asbestos Containing material (RACM) includes all friable ACM; Category I non-friable ACM that has become friable or will be or has been subjected to sanding, grinding, cutting, or abrading; and Category II non-
January 10, 2025 Terracon Project No. EN247340
Facilities | Environmental | Geotechnical | Materials 2 friable ACM that has a high probability of becoming or has become crumbled, pulverized, or reduced to powder in the course of renovation or demolition activity. RACM must be removed prior to renovation or demolition activities.
South Carolina In the state of South Carolina, asbestos activities are regulated by the SCDES under the SCDES Regulation 61-
86.1 Standards of Performance for Asbestos Projects. The SCDES require that any asbestos-related activity conducted in a public building be performed by personnel licensed by the SCDES. The owner or operator must provide the SCDES with written notification of planned abatement and removal activities prior to the commencement of those activities. The SCDES requires 4-day notification for non-friable projects and 10 day notification for RACM projects. Asbestos abatement must be performed by SCDES -licensed asbestos abatement contractors. A SCDES -licensed Project Designer shall prepare a written abatement design for each abatement renovation project involving the removal of greater than 3,000 square, 1,500 linear, or 656 cubic feet of RACM.
Third-party air monitoring must be conducted during the abatement of friable (regulated) ACM. The SCDES asbestos regulations can be found at https://scdhec.gov/environment/your-home/asbestos/asbestos-regulations.
The SCDES defines a renovation as, “altering a facility or one or more facility components in any way, including the stripping or removal of RACM from any facility component.” A demolition is defined as, “Wrecking or taking out any load-supporting structural member of a facility together with any related handling operations, the burning of any facility, or moving of a structure.”
OSHA
The Occupational Safety and Health Administration (OSHA) Asbestos Standard for Construction Industry (29 CFR 1926.1101) regulates workplace exposure to asbestos. The OSHA standard requires that employee exposure to airborne asbestos fibers be maintained below 0.1 asbestos fibers per cubic centimeter of air (0.1 f/cc). The OSHA standard classifies construction and maintenance activities, which could disturb ACM, and specifies work practices and precautions which employers must follow when engaging in each class of regulated work. A full copy of the OSHA asbestos standard for general industry may be found at OSHA’s website (www.osha.gov) and should be referenced for specific information.
3.2 Visual Assessment
Our inspection activities began with visual observation of the interior and exterior of the building to identify apparent homogeneous areas of suspect ACM. A homogeneous area consists of building materials, which appear similar throughout in terms of color, texture and date of application. Building materials which were not identified as concrete, glass, wood, masonry, metal or rubber were considered suspect ACM. Although reasonable effort was made to survey accessible suspect materials, additional suspect but un-sampled materials could be located in walls, in voids or in other concealed areas.
3.3 Physical Assessment
A physical assessment of each homogeneous area of suspect ACM was conducted to assess the friability and condition of the materials. A friable material is defined by the EPA as a material, which can be crumbled, pulverized or reduced to powder by hand pressure when dry. Non-friable materials contain asbestos fibers which have been “locked in” by a bonding agent, coating, binder or other materials so that the asbestos is bound and will not readily release fibers during normal handling or use. Friability was assessed by physically touching suspect materials.
January 10, 2025 Terracon Project No. EN247340
Facilities | Environmental | Geotechnical | Materials 3
3.4 Sample Collection
Based on the results of the visual sampling, bulk samples of suspect ACM were collected in general accordance with the sampling protocols outlined in EPA Regulation 40 CFR 763 Subpart E763.86 (Asbestos Hazard Emergency Response Act, AHERA) and SCDES sample collection protocols. Random samples of suspect materials were collected in each homogeneous area. Bulk samples were collected using wet methods as applicable to reduce the potential for fiber release. Samples were placed in sealable containers and labeled with unique sample numbers using an indelible marker. The SCDES bulk sampling requirements are defined as follows:
Category Quantity of Suspect
Material
Required Minimum Samples
Surfacing
< 1,000 ft2 or < 1,000 ft 3 >1,000 ft2 and < 5,000 ft2 OR
> 1,000 ft and < 5,000 ft
> 5,000 ft2 OR > 5,000 ft 7 Thermal System Insulation
N/A 3
Miscellaneous N/A 3
The selection of sample locations and frequency of sampling was based on Terracon’s observations and the assumption that materials in the same area are homogeneous in content.
Forty-six (46) bulk samples were collected from fourteen (14) homogeneous areas of suspect ACM in the building.
A summary of the suspect ACM samples collected during the survey is presented in Table 1. Sample locations are depicted on the Sample Location Diagram (Figure 1).
3.5 Sample Analysis
Bulk samples were submitted under chain of custody to EMSL Laboratories (EMSL) of Pineville, North Carolina for analysis by Polarized Light Microscopy (PLM) with dispersion staining techniques per EPA EPA/600/R-93/116. The percentage of asbestos, where applicable, was determined by microscopical visual estimation. EMSL is accredited under the National Voluntary Laboratory Accreditation Program. Layered analysis of samples was conducted by the lab to separate the tile and ceramic tile, grout, and mortar.
Per the SCDES Regulation 61-86.1 Standards of Performance for Asbestos Projects, negative results for non-friable organically bound (NOB) materials such as flooring, mastics, and roofing shall be verified with at least one TEM analysis. The additional analysis was performed by TEM in accordance with EPA/600/R-93/116 Section 2.5.5.1.
Fourteen (14) NOB materials tested negative for asbestos by PLM analysis and thus were submitted and analyzed by TEM analysis. Samples requiring TEM analysis are identified on Table 1.
3.6 Findings
Based on the results of laboratory analysis, the following materials were identified as asbestos containing materials (ACMs) defined as containing >1% asbestos:
January 10, 2025 Terracon Project No. EN247340
Facilities | Environmental | Geotechnical | Materials 4
Exterior Caulking (2% Chrysotile) associated with white window caulking of the exterior door on the northeast side of the building, approximately 10 LF.
Table 1 summarizes the results of the visual inspection, estimated quantities, and laboratory analyses. Asbestos laboratory analytical reports are included in Appendix B.
3.7 Recommendations
Based on the scope of services, limitations, and findings of this assessment:
Terracon recommends removal of the asbestos-containing materials by a South Carolina licensed asbestos abatement contractor.
In accordance with OSHA's Asbestos Standard, the employer shall notify affected employees and contractors of the presence and location of asbestos-containing materials and test results. A full copy of the OSHA asbestos standard for general industry may be found at OSHA’s website (www.osha.gov) and should be referenced for specific information.
It should be noted that suspect materials, other than those identified during the December 2, 2024 and December 3, 2024 survey may exist within the structure. Should suspect materials other than those which were identified during this survey be uncovered during or prior to the abatement and demolition process, those materials should be assumed asbestos-containing until sampling and analysis can confirm or refute their asbestos content. Should future sampling indicate that the other material is asbestos containing, Terracon recommends removal of the asbestos-containing materials by a South Carolina licensed asbestos abatement contractor prior to renovation/demolition of the building.
4.0 LEAD PAINT SAMPLING
The objective of the lead paint sampling was to identify lead containing paint systems on building components that may require special handling and disposal considerations upon renovation of the structure. SCDES regulates solid waste disposal under Regulation 61-107.19 as noted below. Testing was performed to meet specific State disposal requirements and does not comply with all parts of the Occupational Health and Safety Administrations (OSHA) lead regulations. Testing to comply with OSHA regulations are not covered in our scope of work since it is the responsibility of the contractor to protect its employees.
4.1 Regulatory Overview
Lead is regulated by the EPA, SCDES and OSHA. The EPA and SCDES regulate lead use, removal, and disposal, and OSHA regulates lead exposure to workers. The EPA defines LBP as paint, varnish, stain, or other applied coating that contains lead equal to or greater than 1.0 mg/cm2, 5,000 mg/kg, or 0.5% by dry weight as determined by laboratory analysis. The SCDES regulations 61-107.19 require that painted demolition debris with a lead concentration greater than 0.06% by weight be disposed in a permitted Class II landfill. For the purpose of the OSHA lead standard, lead includes metallic lead, all inorganic lead compounds, and organic lead soaps. The complete OSHA standard for compliance can be found on OSHA’s website (www.osha.gov). A synopsis of the OSHA regulations (29 CFR 1926.62) and the applicability are as follows:
January 10, 2025 Terracon Project No. EN247340
Facilities | Environmental | Geotechnical | Materials 5
The OSHA Lead Standard for Construction (29 CFR 1926.62) applies to all construction work where an employee may be occupationally exposed to lead. All work related to construction, alteration, or repair (including painting and decorating) is included. The lead-in-construction standard applies to any detectable concentration of lead in paint, as even small concentrations of lead can result in unacceptable employee exposures depending upon on the method of removal and other workplace conditions. Under this standard, construction includes, but is not limited to, the following:
Demolition or salvage of structures where lead or materials containing lead are present
Removal or encapsulation of materials containing lead
New construction, alteration, repair, or renovation of structures, substrates, or portions containing lead, or materials containing lead
Installation of products containing lead
Lead contamination/emergency clean-up
Transportation, disposal, storage, or containment of lead or materials containing lead on the site or location at which construction activities are performed
Maintenance operations associated with construction activities described above
4.2 Sampling and Analytical Protocol
Mr. Andrew Mitroka of Terracon conducted the lead paint (LP) sampling on December 2, 2024 and December 3, 2024. The LP sampling was conducted by collecting paint chip samples. The paint chip samples were collected from painted or lacquered surfaces of building components likely to contain LP, based on apparent date of application. The paint samples were collected down to the surface substrate so as to include any underlying paint systems in the analysis. The random paint chip samples were selected based on current paint schemes and may not be inclusive of old paint systems covered with paneling, or existing painted systems. The paint chip samples were submitted to an ELAP approved laboratory for analysis of lead by NIOSH Method 7082M (atomic absorption).
4.3 Sample Collection
Six (6) paint samples were collected from interior and exterior painted surfaces on the buildings. Paint sampled included:
Interior Walls (White)
Interior (Beige)
Exterior (Yellow)
Exterior Door (Gray)
Roof (Gray)
HVAC (Yellow)
4.4 Findings
Based on the results of laboratory analysis, lead was not identified above SCDES regulation limits in any of paint chip samples. However, lead was identified above laboratory detection limits in the following samples
January 10, 2025 Terracon Project No. EN247340
Facilities | Environmental | Geotechnical | Materials 6
Gray exterior door paint (0.052% by wt) Gray exterior roof paint (0.018% by wt)
5.0 LIMITATIONS / GENERAL COMMENTS
Terracon did not perform sampling which required demolition or destructive activities such as knocking holes in walls, ceiling and dismantling of equipment or removal of protective coverings. Reasonable efforts to access suspect materials within known areas of restricted access (e.g. crawl spaces and attics) were made; however, confined spaces or areas which may pose a health or safety risk to Terracon personnel were not sampled.
Sampling did not include materials which could not be safely reached with available ladders.
This survey was conducted in a manner consistent with the level of care and skill ordinarily exercised by members of the profession currently practicing under similar conditions in the same locale. The results, findings, conclusions and recommendations expressed in this report are based on conditions observed during our survey of the building. The information contained in this report is relevant to the date on which this survey was performed and should not be relied upon to represent conditions at a later date.
This report has been prepared on behalf of and exclusively for use by Pond & Company for specific application to their project as discussed. Terracon does not warrant the work of regulatory agencies, laboratories or other third parties supplying information, which may have been used in the preparation of this report. No warranty, express or implied is made.
This report is not a bidding document. Contractors or consultants reviewing this report must draw their own conclusions regarding further investigation or remediation deemed necessary.
HA
Sample
ID
Approx.
Quantity* Samples Collected Description Material Location Lab Result Category Condition
WB-
01/05 4,000 SF 5 Wallboard and Joint Compound Interior Walls NAD W.B.-Misc.
J.C.-Surf. Good
PC-
01/05 2,000 SF 5 Popcorn Ceiling Ceiling - Halls NAD Surf. Good
EC-
01/03 10 SF 3 Exterior Caulking Northeast Door 2% Chrys. Cat. II Good
PW-
01/03 500 LF 3 Pipe Wrap Roof mechanical room NAD Misc. Good
FT1-
01/03 5,000 SF 3 Floor Tile and Mastic Interior Floor NAD Misc. Good
CFT-
01/03 2,000 SF 3 Ceramic Floor Tile
Interior Floor, Restrooms NAD Misc. Good
CT1-
01/03 10,000 SF 3 Ceiling Tile 2x4 Ceiling - Halls NAD Misc. Good
CT2-
01/03 2,000 SF 3 Ceiling Tile Ceiling - Halls NAD Misc. Good
RB1-
01/03 20,000 SF 3 Roof Bottom Layer Roof NAD Misc. Good
RF-
01/03 5,000 SF 3 Roof Flashing Roof Flashing NAD Misc. Good
RM-
01/03 2,000 SF 3 Roof Mastic Roof NAD Misc. Good
RC-
01/03 20,000 SF 3 Roof Core Roof NAD Misc. Good
SP-
01/03 5,000 SF 3 Silver Paint Roof Seams NAD Misc. Good
CB-
01/03 5,000 LF 3 Covebase and Mastic Base of Walls NAD Misc. Good
Notes Due to planned renovation all materials have a high potential for disturbance
* Quantities should not be used for bidding purposes.
Materials hidden and not observed due to access restrictions and/or enclosed spaces can change actual quantities. Contractors are strongly encouraged to collect their own measurements prior to submitting bids to verify quantities provided above.
Homogeneous Materials 3, 4, 5, 9, 10, 11, 12, 13, 14 are NOB materials.
Negative PLM results were confirmed with TEM analyses.
Refer to Figure 1 for approximate sample locations HA Homogeneous Area
NAD No Asbestos Detected Surf. Surfacing Material Misc. Miscellaneous Material
F Friable NF Non-Friable LF Linear Feet SF Square Feet
Cat. I asbestos-containing packings, gaskets, asphaltic roofing products, resilient flooring, pliable sealants and pliable mastics Cat. II non-friable materials other than Category I RACM Regulated Asbestos-Containing Material
TABLE 1 - Asbestos Sample Summary JBC Building 3370
North Charleston, South Carolina Project No. EN247340
Sample Number Description Location Lab Result
LP-1 Yellow Exterior <0.008 % wt
LP-2 Gray Door Exterior 0.052 % wt
LP-3 Beige Interior <0.010 % wt
LP-4 White Interior Wall <0.008 % wt
LP-5 Gray Exterior Roof 0.018 % wt
LP-6 Yellow HVAC <0.009 % wt
North Charleston, South Carolina Project No. EN247340
TABLE 2 - Lead Paint Sample Summary JBC Building 3370
Project No.
Scale:
File Path:
Date:
PM:
Drawn By:
Checked By:
Approved By: 1800 Reynolds Avenue
Phone: (843) 277 8461
North Charleston, SC 29405
Fax: (843) 884 9234
Sample Location Diagram Figure
JBC Building 3370 North Charleston, South Carolina 1
12/17/2024GP
GP
AJM
AJM
N.T.S
EN247340Asbestos Sample (Positive) Asbestos Sample (Negative) Lead Based Paint (Positive) Lead Based Paint (Negative)
N
WB-01
WB-02
WB-03
WB-04
WB-05
PC-01
PC-02
PC-03
PC-04
PC-05
EC-01
EC-02
EC-03
PW-01
PW-02
PW-03
FT1-01
FT1-02
FT1-03
CFT-01
CFT-02
CFT-03
CT1-01
CT1-02
CT1-03
CT2-01
CT2-02
CT2-03
RB1-01
RB1-02
RB1-03
RF-01
RF-02
RF-03
RM-01
RM-02
RM-03
RC-01
RC-02
RC-03
SP-01
SP-02
SP-03
CB-01
CB-02
CB-03
LP-01
LP-02
LP-03
LP-04
LP-05
LP-06
Building 3370 Terracon Project No. EN247340 Date Photos Taken: 12/2/24
#4 View of LP-04: Gray Door Paint
#1 View of Site. #2 View of HA-03: Exterior Caulk
#3 View of Roof.
#5 View of LP-05: Gray Roof Paint
OrderID: 412414031
OrderID: 412414031
THIS PAGE INTENTIONALLY LEFT BLANK
Blank Page