Attachment 3 - DKGV 1137999 - NRC B3370 Performance Time.pdf
PDF 147 KB Posted
- Solicitation number
- FA441826R0013
About this file
This is a Performance Time Tabulation Form for a federal construction repair contract (DKGV 1137999) to repair the Naval Reserve Center - B3370, prepared by Jonathan Vargas Sanchez, CES, COR and digitally signed on March 13, 2026.
The contract establishes a comprehensive performance schedule spanning 302 total calendar days from estimated project award on August 3, 2026, through estimated completion on May 31, 2027. The timeline includes 60 days for mobilization and submittal preparation, 150 days for special order materials lead time, and construction commencing on March 1, 2027. The construction phase comprises 167 actual construction days and 45 inclement weather days (referenced in Specification 01 32 00, paragraph 3.3.8.1), with 30 additional days allocated for closeout activities. The form provides a month-by-month breakdown from August 2026 through December 2027, indicating that construction occurs during winter months (October 2026 through September 2027) when inclement weather is anticipated, with average inclement weather days per month ranging from 3 to 5 days depending on the month. The construction time calculation totals 502 days, while the Period of Performance spans 302 days.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
3-Aug-26
1-Mar-27
28-Sep-27
31-May-27
Month Days In Month
Average Inclement Weather
Days/Month (Ref. Spec 01 32 00, para
3.3.8.1)
Number of Construction Days/Month
% of Days of Month
Construction
Possible Inclement
Weather Days Per Month
Aug-26 30 5 0 0% 0 Sep-26 31 5 0 0% 0 Oct-26 30 3 30 100% 3 Nov-26 31 4 31 100% 4 Dec-26 31 4 31 100% 4 Jan-27 28 4 28 100% 4 Feb-27 31 3 31 100% 3 Mar-27 30 3 30 100% 3 Apr-27 31 3 31 100% 3 May-27 30 3 30 100% 3 Jun-27 31 5 31 100% 5 Jul-27 31 5 31 100% 5 Aug-27 30 5 30 100% 5 Sep-27 31 5 31 50% 3 Oct-27 30 3 30 0% 0 Nov-27 31 4 31 0% 0 Dec-27 31 4 31 0% 0
Total: 457 Total: 45
Jonnathan Vargas Sanches, CES, COR 302
"Construction Time" = Period of Performance (PoP) =
Estimated Project Award Mobilization & Submittal Preparation:
Special Order Materials Lead Time:
Estimated Contract Completion Date:
Total Contract Days:
Number of Construction Days:
Number of Inclement Weather Days:
Construction Complete Number of Closeout Days:
Construction Start Date:
Performance Time Tabulation Form
DKGV 1137999- Repair Naval Reserve Center - B3370 13-Mar-26
| 2026-03-13T11:32:49-0400 | |
| Jonnathan Vargas Sanchez |
File details come from the government source that posted it. Updated .