This is a Statement of Work (SOW) for the Department of the Air Force, Headquarters 628th Air Base Wing (AMC), Joint Base Charleston, South Carolina, dated 18 February 2026 with Revision 1 effective 06 May 2026.

The project requires the contractor to provide all plant, labor, material parts, and equipment necessary to replace standpipes, bases, and guide rails on the sewer lift station at Building 509. Sewer Lift Station Contractor Requirements include: performing OSHA Permitted Confined Space Entry (CSE) setup; plugging the manhole and installing a contractor-provided bypass pump; pulling pump #1 and performing CSE to remove the #1 guide rail, standpipe, and base; installing a new base, standpipe, and guide rail with new guide rail brackets; repeating this process for the other three existing pumps; and testing all components for functionality upon completion. The Water and Fuel Shop (CE) Requirements specify disconnecting and locking out power to the pumps and control panel before work begins, and restoring power after installation is complete and coordinated with the contractor. All products and materials must be installed per manufacturer's technical instructions and specifications, with all excess material turned over to the government. A one-year warranty against defective workmanship and material failure is required from the completion date. The contractor must comply with all OSHA safety regulations and Toxic Substances Control Act of 2016 requirements, prohibiting Class I ozone-depleting substances, asbestos-containing materials, and lead paints. The work site must be maintained in clean and orderly condition daily, returned to existing conditions upon completion, and the contractor bears responsibility for any damage to government property resulting from construction procedures.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

HEADQUARTERS 628TH AIR BASE WING (AMC)

JOINT BASE CHARLESTON SC

Statement of Work

Joint Base Charleston Air Base

South Carolina 18 February 2026 - Revision 1, 06 May 2026

Statement of Work: The project consists of providing all plant, labor, material parts, and equipment necessary to replace standpipes, bases, and guide rails on the sewer lift station at building 509 on Joint Base Charleston Air Base, South Carolina. The project requirements include, but are not limited to the following major items of work:

Sewer Lift station Contractor Requirements:

• Set-up to perform OSHA Permitted Confined Space Entry (CSE).

• Plug manhole and install contractor-provided bypass pump.

• Pull pump #1 and perform CSE to remove #1 guide rail, standpipe and base.

• Set new base, new standpipe, and new guide rail using new guide rail brackets.

• Repeat process for other bases, standpipes, and guide rails on the other 3 existing pumps.

• Once installed, all components will be tested for functionality to ensure normal operations.

Water and Fuel Shop (CE) Requirements:

• Following OSHA safety standards, disconnect power to pumps and control panel. Lock out and tag out pumps at the panel.

• After all equipment has been installed and in coordination with contractor for timing, all locks will be removed, and power will be turned back on.

Required Warranty Period:

All products and materials used under this project requirement shall be warranted against defective workmanship and material failure for a period of one year from the completion date.

Products:

All products and materials shall be installed in accordance with the manufacturer’s technical instructions and specifications. All excess material and products shall be turned over to the government.

Replace Standpipes, Bases, & Guardrails at Bldg 509 Sewer Lift Station

Applicable Instructions:

Work areas around project site will be occupied by the using activity during the course of work. Caution must be taken to ensure all safety work practices are adhered to while construction work requirements are performed at the facility work site.

Caution must be taken in all work areas of the site to avoid physical or cosmetic damage to existing government property. Any damage to government property resulting from construction procedures shall be the responsibility of the contractor.

Special Instructions:

Project site shall be kept clean and orderly daily.

Work methods and practices shall be accomplished in a safe manner abiding by work safety and base safety standards. Work site is subject to OSHA inspections.

Work site areas shall be returned to existing conditions at completion of work requirements.

D. ENVIRONMENTAL: The contractor shall comply with all applicable requirements stated in the Toxic Substances Control Act of 2016. All materials used in the performance of this contract shall be applied in strict accordance with manufacturer’s printed label instructions and all applicable standards.

The use of Class I ozone depleting substances, asbestos containing materials, and lead paints are strictly prohibited.

E. SAFETY: The contractor shall comply with all OSHA safety regulations during the performance of this delivery order. Install and maintain barricades and barriers as needed. Lay down areas are to be as designated by the Contracting Officer. Work methods and practices shall be accomplished in a safe manner complying with work safety and base safety standards.