Statement of Work Summary

This is a Statement of Work for DKFX Replace Standpipes & Bases at Building 509 Sewer Lift Station at Joint Base Charleston Air Base, South Carolina, dated 18 February 2026. The project requires replacement of standpipes and bases on the sewer lift station, with all necessary plant, labor, material parts, and equipment to be provided by the contractor. The work encompasses four major standpipes and involves OSHA-permitted confined space entry procedures, manhole plugging, bypass pump installation, removal of existing equipment, installation of new bases and standpipes with new guide rail brackets, and functionality testing. The Water and Fuel Shop (CE) will coordinate bypass pump setup, power disconnection with lockout/tagout procedures, removal of four existing sewage pumps using heavy equipment, disconnection of power cables, and installation of four new sewage pumps. All products and materials must comply with manufacturer's technical instructions and specifications, with excess materials turned over to the government. A one-year warranty period is required covering defective workmanship and material failure from the completion date.

Additional requirements include strict adherence to OSHA safety regulations, daily site cleanliness, work site restoration to existing conditions upon completion, compliance with the Toxic Substances Control Act of 2016, and prohibition of Class I ozone-depleting substances, asbestos-containing materials, and lead paints. The contractor assumes responsibility for any damage to government property resulting from construction procedures. The work site is subject to OSHA inspections and must maintain barricades and barriers as needed, with lay-down areas designated by the Contracting Officer.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CUI

DEPARTMENT OF THE AIR FORCE

HEADQUARTERS 628TH AIR BASE WING (AMC)

JOINT BASE CHARLESTON SC

CUI

Statement of Work

DKFX Replace Standpipes & Bases at Bldg 509 Sewer Lift Station

Joint Base Charleston Air Base

South Carolina 18 February 2026

Statement of Work: The project consists of providing all plant, labor, material parts, and equipment necessary to replace standpipes and bases on the sewer lift station at building 509 on Joint Base Charleston Air Base, South Carolina. The project requirements include, but are not limited to the following major items of work:

Sewer Lift station Contractor Requirements:

• Set-up to perform OSHA Permitted Confined Space Entry (CSE).

• Plug manhole and install bypass pump while old equipment is being removed.

• Pull pump #1 and perform CSE to remove #1 guiderails, standpipe and base.

• Set new base, standpipe and reinstall existing guide rails using new guide rail brackets.

• Repeat process for other three standpipes.

• Once installed, all components will be tested for functionality to ensure normal operations.

Water and Fuel Shop (CE) Requirements:

• Set up a bypass pump to continue normal sewage pumping operations while old equipment is being removed.

• Following OSHA safety standards, disconnect power to pumps and control panel. Lock out and tag out pumps at the panel.

• Using proper heavy equipment, attach to and lift out each of the four existing sewage pumps.

• Power cables must be disconnected from existing pumps. Old pumps are property of the US government and will be retained by the water and fuels shop.

• Using proper heavy equipment, attach to and lower each of the four new sewage pumps.

• After all equipment has been installed and in coordination with contractor for timing, all locks will be removed, and power will be turned back on.

Required Warranty Period:

All products and materials used under this project requirement shall be warranted against defective workmanship and material failure for a period of one year from the completion date.

Products:

All products and materials shall be installed in accordance with the manufacturer’s technical instructions and specifications. All excess material and products shall be turned over to the government.

Applicable Instructions:

Work areas around project site will be occupied by the using activity during the course of work. Caution must be taken to ensure all safety work practices are adhered to while construction work requirements are performed at the facility work site.

Caution must be taken in all work areas of the site to avoid physical or cosmetic damage to existing government property. Any damage to government property resulting from construction procedures shall be the responsibility of the contractor.

Special Instructions:

Project site shall be kept clean and orderly daily.

Work methods and practices shall be accomplished in a safe manner abiding by work safety and base safety standards. Work site is subject to OSHA inspections.

Work site areas shall be returned to existing conditions at completion of work requirements.

D. ENVIRONMENTAL: The contractor shall comply with all applicable requirements stated in the Toxic Substances Control Act of 2016. All materials used in the performance of this contract shall be applied in strict accordance with manufacturer’s printed label instructions and all applicable standards.

The use of Class I ozone depleting substances, asbestos containing materials, and lead paints are strictly prohibited.

E. SAFETY: The contractor shall comply with all OSHA safety regulations during the performance of this delivery order. Install and maintain barricades and barriers as needed. Lay down areas are to be as designated by the Contracting Officer. Work methods and practices shall be accomplished in a safe manner complying with work safety and base safety standards.