Repair Military Working Dog Area - Building B649 155580BID
SECTION 07 61 14.00 20
STEEL STANDING SEAM ROOFING
05/11
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN IRON AND STEEL INSTITUTE (AISI)
AISI SG03-3 (2002; Suppl 2001-2004; R 2008) Cold-Formed Steel Design Manual Set
ASTM INTERNATIONAL (ASTM)
ASTM A1008/A1008M (2013) Standard Specification for Steel, Sheet, Cold-Rolled, Carbon, Structural, High-Strength Low-Alloy and High-Strength Low-Alloy with Improved Formability, Solution Hardened, and Bake Hardened
ASTM A1011/A1011M (2014) Standard Specification for Steel, Sheet, and Strip, Hot-Rolled, Carbon, Structural, High-Strength Low-Alloy and High-Strength Low-Alloy with Improved Formability and Ultra-High Strength
ASTM A653/A653M (2013) Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process
ASTM A792/A792M (2010) Standard Specification for Steel Sheet, 55% Aluminum-Zinc Alloy-Coated by the Hot-Dip Process
ASTM B117 (2011) Standard Practice for Operating Salt Spray (Fog) Apparatus
ASTM D1654 (2008) Evaluation of Painted or Coated Specimens Subjected to Corrosive Environments
ASTM D2244 (2014) Calculation of Color Tolerances and Color Differences from Instrumentally Measured Color Coordinates
ASTM D2247 (2011) Testing Water Resistance of Coatings in 100% Relative Humidity
ASTM D4214 (2007) Standard Test Method for Evaluating the Degree of Chalking of Exterior Paint Films
SECTION 07 61 14.00 20 Page 1 16 March 2023
ASTM D522/D522M (2014) Mandrel Bend Test of Attached Organic Coatings
ASTM D523 (2014) Standard Test Method for Specular Gloss
ASTM D714 (2002; R 2009) Evaluating Degree of Blistering of Paints
ASTM D968 (2005; R 2010) Abrasion Resistance of Organic Coatings by Falling Abrasive
ASTM E1592 (2005; R 2012) Structural Performance of Sheet Metal Roof and Siding Systems by Uniform Static Air Pressure Difference
ASTM E84 (2014) Standard Test Method for Surface Burning Characteristics of Building Materials
ASTM G152 (2013) Operating Open Flame Carbon Arc Light Apparatus for Exposure of Nonmetallic Materials
ASTM G153 (2013) Operating Enclosed Carbon Arc Light Apparatus for Exposure of Nonmetallic Materials
NATIONAL ASSOCIATION OF ARCHITECTURAL METAL MANUFACTURERS (NAAMM)
NAAMM AMP 500 (2006) Metal Finishes Manual
SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION
(SMACNA)
SMACNA 1793 (2012) Architectural Sheet Metal Manual, 7th Edition
1.2 DEFINITIONS
1.2.1 Field-Formed Seam
Seams of panels so configured that when adjacent sheets are installed the seam is sealed utilizing mechanical or hand seamers. Crimped (45 degree bend), roll formed (180 degree bend), double roll formed (2 - 180 degree bends), and roll and lock systems are types of field-formed seam systems.
1.2.2 Snap Together Seam
Panels so configured that the male and female portions of the seam interlock through the application of foot pressure or tamping with a mallet. Snap-on cap configurations are a type of snap together system.
1.2.3 Pre-Formed
Formed to the final, less field-formed seam, profile and configuration in the factory.
SECTION 07 61 14.00 20 Page 2
1.2.4 Field-Formed
Formed to the final, less field-formed seam, profile and configuration at the site of work prior to installation.
1.2.5 Roofing System
The roofing system is defined as the assembly of roofing components, including roofing panels, flashing, fasteners, and accessories which, when assembled properly result in a watertight installation.
1.3 SYSTEM DESCRIPTION
1.3.1 Design Requirements
a. Panels shall be continuous lengths up to manufacturer's standard longest lengths, with no joints or seams, except where indicated or specified. Ribs of adjoining sheets shall be in continuous contact from eave to ridge. Individual panels of snap together type systems shall be removable for replacement of damaged material.
b. There shall be no exposed or penetrating fasteners except where shown on approved shop drawings. Fasteners into steel shall be stainless steel, zinc cast head, or cadmium plated steel screws inserted into predrilled holes. There shall be a minimum of two fasteners per clip. Single fasteners will be allowed when supporting structural members are prepunched or predrilled.
c. Snap together type systems shall have a capillary break and a positive side lap locking device. Field-formed seam type systems shall be mechanically locked closed by the manufacturer's locking tool. The seam shall include a continuous factory applied sealant when required by the manufacturer to withstand the wind loads specified.
d. Roof panel anchor clips shall be concealed and designed to allow for longitudinal thermal movement of the panels, except where specific fixed points are indicated. Provide for lateral thermal movement in panel configuration or with clips designed for lateral and longitudinal movement.
1.3.2 Design Conditions
The system shall be designed to resist positive and negative loads specified herein in accordance with the AISI SG03-3 . Panels shall support walking loads without permanent distortion or telegraphing of the structural supports.
1.3.2.1 Wind Uplift
The design uplift pressures for the roof system shall be computed and applied using basic wind speed indicated on structural drawings .
The design uplift force for each connection assembly shall be that pressure given for the area under consideration, multiplied by the tributary load area of the connection assembly, and multiplied by the appropriate factor of safety, as follows:
a. Single fastener in a connection: 3.0
SECTION 07 61 14.00 20 Page 3
b. Two or more fasteners in each connection: 2.25
1.3.2.2 Roof Live Loads
Loads shall be applied on the horizontal projection of the roof structure. The minimum roof design live load shall be 20 psf .
1.3.2.3 Thermal Movement
System shall be capable of withstanding thermal movement based on a temperature range of 10 degrees F below and 140 degrees F .
1.3.2.4 Deflection
Panels shall be capable of supporting design loads between unsupported spans with deflection of not greater than L/180 of the span.
1.3.3 Structural Performance
The structural performance test methods and requirements of the Standing Seam Roofing Systems (SSRS) shall be in accordance with ASTM E1592.
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for DOR and Contractor Quality Control approval and are for information only to Government When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Roofing ; G
Submit roofing drawings to supplement the instructions and diagrams. Drawings shall include design and erection drawings containing an isometric view of the roof showing the design uplift pressures and dimensions of edge, ridge and corner zones; and show typical and special conditions including flashings, materials and thickness, dimensions, fixing lines, anchoring methods, sealant locations, sealant tape locations, fastener layout, sizes, and spacing, terminations, penetrations, attachments, and provisions for thermal movement. Details of installation shall be in accordance with the manufacturer's Standard Instructions and details or the SMACNA 1793. Prior to submitting shop drawings, have drawings reviewed and approved by the manufacturer's technical engineering department.
Where roof is being installed over existing structure, shop drawings shall indicate attachment and spacing of new system to existing structure
SD-03 Product Data
Roofing panels ; G
Attachment clips
SECTION 07 61 14.00 20 Page 4
Closures
Accessories
Fasteners
Factory color finish
Sealants
Insulation , including joint sealing measures for vapor barrier facing
Sample warranty certificate; G
Submit for materials to be provided. Submit data sufficient to indicate conformance to specified requirements.
SD-04 Samples
Roofing panel
Submit a 12 inch long by full width section of typical panel.
For color selection, submit 2 by 4 inch metal samples in color, finish and texture.
SD-05 Design Data
Design calculations
SD-06 Test Reports
Field Inspection ; G
Submit manufacturer's technical representative's field inspection reports as specified in paragraph entitled "Manufacturer's Field Inspection."
Structural performance tests
Finish tests
Water penetration
SD-07 Certificates
Manufacturer's Technical Representative 's Qualifications
Statement of Installer's Qualifications
Submit documentation from roofing manufacturer proving the manufacturer's technical representative meets below specified requirements. Include name, address, telephone number, and experience record.
Submit documentation proving the installer is factory-trained, SECTION 07 61 14.00 20 Page 5 has the specified experience, and authorized by the manufacturer to install the products specified.
SD-08 Manufacturer's Instructions
Installation manual; G Submit manufacturers printed installation manual, instructions, and standard details.
SD-11 Closeout Submittals
Information card
For each roofing installation, submit a typewritten card or photoengraved aluminum card containing the information listed on Form 1 located at the end of this section.
1.5 DESIGN CALCULATIONS
Provide design calculations prepared by a professional engineer registered in the state of North Carolina, specializing in structural engineering verifying that system supplied and any additional framing meets design load criteria indicated. Coordinate calculations with manufacturer's test results. Include calculations for:
Wind load uplift design pressure at roof locations specified in paragraph entitled "Wind Uplift."
Clip spacing and allowable load per clip.
Fastening of clips to structure or intermediate supports.
Intermediate support spacing and framing and fastening to structure when required.
Allowable panel span at anchorage spacing indicated.
Safety factor used in design loading.
Governing code requirements or criteria.
Edge and termination details.
1.6 QUALITY ASSURANCE
1.6.1 Preroofing Conference
After submittals are received and approved but before roofing work, including associated work, is preformed, the Contractor shall hold a preroofing conference to review the following :
a. The drawings and specifications
b. Procedure for on site inspection and acceptance of the roofing substrate and pertinent structural details relating to the roofing system
SECTION 07 61 14.00 20 Page 6
c. Contractor's plan for coordination of the work of the various trades involved in providing the roofing system and other components secured to the roofing
d. Safety requirements
The preroofing conference shall be attended by the Contractor and personnel directly responsible for the roofing installation, mechanical and electrical work, and the roofing manufacturer's technical representative. Conflicts among those attending the preroofing conference shall be resolved and confirmed in writing before roofing work, including associated work, is begun .
1.6.2 Manufacturer
The SSMRS shall be the product of a metal roofing industry - recognized manufacturer who has been in the practice of manufacturing SSMRS for a period of not less than 5 years and who has been involved in at least 5 projects similar in size and complexity to this project.
1.6.3 Manufacturer's Technical Representative
The representative shall have authorization from manufacturer to approve field changes and be thoroughly familiar with the products and with installations in the geographical area where construction will take place. The manufacturer's representative shall be an employee of the manufacturer with at least 5 years experience in installing the roof system. The representative shall be available to perform field inspections and attend meetings as required herein, and as requested by the Contracting Officer.
1.6.4 Installer's Qualifications
The roofing system installer shall be factory-trained, approved by the metal roofing system manufacturer to install the system, and shall have a minimum of three years experience as an approved applicator with that manufacturer. The applicator shall have applied five installations of similar size and scope as this project within the previous 3 years.
1.6.5 Single Source
Roofing panels, clips, closures, and other accessories shall be standard products of the same manufacturer; shall be the latest design by the manufacturer; and shall have been designed by the manufacturer to operate as a complete system for the intended use.
1.6.6 Laboratory Tests For Panel Finish
The term "appearance of base metal" refers to the metal coating on steel.
Panels shall meet the following test requirements:
a. Formability Test: When subjected to a 180 degree bend over a 1/8 inch diameter mandrel in accordance with ASTM D522/D522M, exterior coating film shall show only slight microchecking and no loss of adhesion.
b. Accelerated Weathering Test: Withstand a weathering test for a minimum of 2000 hours in accordance with ASTM G152 and ASTM G153, Method 1 without cracking, peeling, blistering, loss of adhesion of the protective coating, or corrosion of the base metal. Protective
SECTION 07 61 14.00 20 Page 7 coating that can be readily removed from the base metal with a penknife blade or similar instrument shall be considered to indicate loss of adhesion.
c. Chalking Resistance: After the 2000-hour weatherometer test, exterior coating shall not chalk greater than No. 8 rating when measured in accordance with ASTM D4214 test procedures.
d. Color Change Test:
After the 2000-hour weatherometer test, exterior coating color change shall not exceed 2 NBS units when measured in accordance with ASTM D2244 test procedure.
e. Salt Spray Test: Withstand a salt spray test for a minimum of 1000 hours in accordance with ASTM B117, including the scribe requirement in the test. Immediately upon removal of the panel from the test, the coating shall receive a rating of 10, no blisters in field as determined by ASTM D714; and an average rating of 7, 1/16 inch failure at scribe, as determined by ASTM D1654. Rating Schedule No. 1.
f. Abrasion Resistance Test for Color Coating: When subjected to the falling sand test in accordance with ASTM D968, coating system shall withstand a minimum of 100 liters of sand per mil thickness before appearance of base metal.
g. Humidity Test: When subjected to a humidity cabinet test in accordance with ASTM D2247 for 1000 hours, a scored panel shall show no signs of blistering, cracking, creepage, or corrosion.
i. Glare Resistance Test:
Surfaces of panels that will be exposed to the exterior shall have a specular reflectance of not more than 10 when measured in accordance with ASTM D523 at an angle of 85 degrees. Specular reflectance may be obtained with striations or embossing. Requirements specified under "Formability Test" will be waived if necessary to conform to this requirement.
1.7 WARRANTY
Furnish manufacturer's no-dollar-limit materials and workmanship warranty for the roofing system. The warranty period shall be not less than 20 years from the date of Government acceptance of the work. The warranty shall be issued directly to the Government. The warranty shall provide that if within the warranty period the metal roofing system becomes non-watertight or shows evidence of corrosion, perforation, rupture or excess weathering due to deterioration of the roofing system resulting from defective materials or installed workmanship the repair or replacement of the defective materials and correction of the defective workmanship shall be the responsibility of the roofing system manufacturer. Repairs that become necessary because of defective materials and workmanship while roofing is under warranty shall be performed within 7 days after notification, unless additional time is approved by the Contracting Officer. Failure to perform repairs within the specified period of time will constitute grounds for having the repairs performed by others and the cost billed to the manufacturer. The Contractor shall also provide a 5 year no penal sum contractor
SECTION 07 61 14.00 20 Page 8 installation warranty.
1.8 DELIVERY, STORAGE AND HANDLING
Deliver, store, and handle preformed panels, bulk roofing products and other manufactured items in a manner to prevent damage or deformation.
1.8.1 Delivery
Provide adequate packaging to protect materials during shipment. Crated materials shall not be uncrated until ready for use, except for inspection. Immediately upon arrival of materials at the jobsite, inspect materials for damage, dampness, and staining. Damaged or permanently stained materials that cannot be restored to like-new condition shall be replaced with satisfactory material. If materials are wet, remove the moisture and re-stack and protect the panels until used.
1.8.2 Storage
Stack materials on platforms or pallets and cover with tarpaulins or other suitable weathertight covering which prevents water trapping or condensation. Store materials so that water which might have accumulated during transit or storage will drain off. Do not store the panels in contact with materials that might cause staining, such as mud, lime, cement, fresh concrete or chemicals. Protect stored panels from wind damage.
1.8.3 Handling
Handle material carefully to avoid damage to surfaces, edges and ends.
PART 2 PRODUCTS
2.1 ROOFING PANELS
Panel s shall have interlocking ribs for securing adjacent sheets. System for securing the roof covering to structural framing members shall be concealed clip fastening system with no fasteners penetrating the panels except at the ridge or eave, rakes, penetrations, and end laps. Backing plates and ends of panels at end laps shall be predrilled or prepunched;
factory prepare ends of panels to be lapped by trimming part of seam, die-setting or swaging ends of panels. Length of sheets shall be sufficient to cover the entire length of any unbroken roof slope when such slope is 30 feet or less. When length of run exceeds 30 feet , each sheet in the run shall extend over two or more spans. Sheets longer than 30 feet may be furnished if approved by the Contracting Officer. Width of sheets shall provide not less than 12 inches of coverage in place. Height of corrugations of adjacent roof sheets shall be not less than 2.25 inches (nominal). Make provisions for expansion and contraction at either ridge or eave, consistent with the type of system to be used. Panels from coil stock shall be formed without warping, waviness or ripples not part of the panel profile and shall be free of damage to the finish coating system.
Available Products/Basis of Design: Metal Sales Manufacturing Corporation, "Vertical Seam - 16 inch panel" or approved equal.
2.1.1 Material
Zinc-coated steel conforming to ASTM A653/A653M , G90 coating designation or aluminum-zinc alloy coated steel conforming to ASTM A792/A792M , AZ 55
SECTION 07 61 14.00 20 Page 9 coating. Minimum thickness to be 0.023 inch thick (24 gage) minimum except when mid field of roof is subject to design wind uplift pressures of 60 psf or greater, entire roof system shall have a minimum thickness of
0.030 inch (22 gage) .
2.1.2 Texture
Smooth with raised intermediate ribs for added stiffness.
2.1.3 Finish
Factory color "Dark Bronze" finish.
2.2 Factory Color Finish
Comply with NAAMM AMP 500 for recommendations for applying and designating finishes. Noticeable variations in same piece are not acceptable.
Variations in appearance of adjoining components are acceptable if they are within the range of approved samples and are assembled or installed to minimize contrast.
All panels are to receive a factory-applied Kynar 500/Hylar 5000 finish consisting of a baked-on top-coat with a manufacturer's recommended prime coat conforming to the following:
2.2.1 Metal Preparation
Carefully prepare all metal surface for painting on a continuous process coil coating line by alkali cleaning, hot water rinsing, application of chemical conversion coating, cold water rinsing, sealing with acid rinse, and thorough drying.
2.2.2 Prime Coating
Apply a base coat of epoxy paint, specifically formulated to interact with the top-coat, to the prepared surfaces by roll coating to a dry film thickness of 0.20 plus 0.05 mils. Prime coat must be oven cured prior to application of finish coat.
2.2.3 Exterior Finish Coating
Roll coat the finish coating over the primer by roll coating to dry film thickness of 0.80 plus 5 mils (3.80 plus 0.50 mils for Vinyl Plastisol) for a total dry film thickness of 1.00 plus 0.10 mils (4.00 plus 0.10 mils for Vinyl Plastisol). Oven-cure finish coat.
2.2.4 Interior Finish Coating
Apply a wash-coat on the reverse side over the primer by roll coating to a dry film thickness of 0.30 plus 0.05 mils for a total dry film thickness of 0.50 plus 0.10 mils. Oven-cured the wash coat.
2.3 ATTACHMENT CLIPS
Fabricate clips from ASTM A1011/A1011M , or ASTM A1008/A1008M steel hot-dip galvanized in accordance with ASTM A653/A653M , G 90 , or Series 300 stainless steel. Size, shape, thickness and capacity as required to meet the load, insulation thickness and deflection criteria specified.
SECTION 07 61 14.00 20 Page 10
2.4 ACCESSORIES
Sheet metal flashings, gutters, downspouts, trim, moldings, closure strips, pre-formed crickets, caps, equipment curbs, and other similar sheet metal accessories used in conjunction with preformed metal panels shall be of the same material as used for the panels. Provide metal accessories with a factory color finish to match the roofing panels, except that such items which will be concealed after installation may be provided without the finish if they are stainless steel. Metal shall be of a thickness not less than that used for the panels. Thermal spacer blocks and other thermal barriers at concealed clip fasteners shall be as recommended by the manufacturer except that wood spacer blocks are not allowed.
2.4.1 Intake Vent
Provide aluminum continuous soffit vents where indicated. Available products/manufacturers: "Continuous Soffit Vent - Model SV201" by Air Vent Inc. Finish: To match metal roof panels.
2.4.2 Ridge Vent
Provide stucco embossed aluminum flash filter vents where indicated.
Available products/manufacturers: "Flash FilterVent - Model FFV162BL" by Air Vent Inc. Finish: To match metal roof panels.
2.4.3 Closures
2.4.3.1 Rib Closures
Corrosion resisting steel, closed-cell or solid-cell synthetic rubber, neoprene or polyvinyl chloride pre-molded to match configuration of rib opening. Material for closures shall not absorb water.
2.4.3.2 Ridge Closures
Metal-clad foam or metal closure with foam secondary closure matching panel configuration for installation on surface of roof panel between panel ribs at ridge and headwall roof panel flashing conditions and terminations. Foam material shall not absorb water.
2.4.4 Fasteners
Zinc-coated steel, corrosion resisting steel, zinc cast head, or nylon capped steel, type and size specified below or as otherwise approved for the applicable requirements. Design the fastening system to withstand the design loads specified. Exposed fasteners shall be gasketed or have gasketed washers on the exterior side of the covering to waterproof the penetration. Washer material shall be compatible with the covering; have a minimum diameter of 3/8 inch for structural connections; and gasketed portion of fasteners or washers shall be neoprene or other equally durable elastomeric material approximately 1/8 inch thick.
2.4.4.1 Screws
Not smaller than No. 14 diameter if self-tapping type and not smaller than No. 12 diameter if self-drilling and self-tapping.
SECTION 07 61 14.00 20 Page 11
2.4.4.2 Bolts
Not smaller than 1/4 inch diameter, shouldered or plain shank as required, with proper nuts.
2.4.4.3 Automatic End-Welded Studs
Automatic end-welded studs shall be shouldered type with a shank diameter of not smaller than 3/16 inch and cap or nut for holding covering against the shoulder.
2.4.4.4 Explosive Driven Fasteners
Fasteners for use with explosive actuated tools shall have a shank diameter of not smaller than 0.145 inch with a shank length of not smaller than 1/2 inch for fastening to steel and not smaller than one inch for fastening to concrete.
2.4.4.5 Rivets
Blind rivets shall be stainless steel with 1/8 inch nominal diameter shank. Rivets shall be threaded stem type if used for other than the fastening of trim. Rivets with hollow stems shall have closed ends.
2.4.5 Sealants
Elastomeric type containing no oil or asphalt. Exposed sealant shall cure to a rubberlike consistency. Concealed sealant shall be the non-hardening type. Seam sealant shall be factory-applied, non-skinning, non-drying, and shall conform to the roofing manufacturer's recommendations.
Silicone-based sealants shall not be used in contact with finished metal panels and components unless approved otherwise by the Contracting Officer.
2.4.6 GASKETS AND INSULATING COMPOUNDS
Nonabsorptive and suitable for insulating contact points of incompatible materials. Insulating compounds shall be nonrunning after drying.
2.5 THERMAL INSULATION
Rigid faced with a flexible vapor retarder. Insulation and facing shall have a flame-spread rating of 50 or less in accordance with ASTM E84.
Vapor retarder facing shall have a permeance rating of 0.05 perm or less.
Facings shall be factory-applied.
2.6 UNDERLAYMENT MATERIALS
Provide self-adhering, cold-applied, sheet underlayment, a minimum of 30 mils thick, consisting of slip-resistant, polyethylene-film top surface laminated to a layer of butyl or SBS-modified asphalt adhesive, with release-paper backing. Provide primer when recommended by underlayment manufacturer .
Manufacturers:Suggested manufacturers include, but are not limited, to the following:
a. Carlisle WIP Products; a brand of Carlisle Construction Materials
b. GCP Applied Technologies Inc.
c. Henry Company.
SECTION 07 61 14.00 20 Page 12
d. Metal-Fab Manufacturing, a Drexel Metals Company.
e. Owens Corning.
Slip Sheet: Manufacturer's recommended slip sheet, of type required for application.
PART 3 EXECUTION
3.1 EXAMINATION
Examine surfaces to receive standing seam metal roofing and flashing.
Ensure that surfaces are plumb and true, clean, even, smooth, as dry and free from defects and projections which might affect the installation.
3.2 INSTALLATION
Install products in accordance with the approved manufacturer's erection instructions, shop drawings, and diagrams. Panels shall be in full and firm contact with attachment clips. Where prefinished panels are cut in the field, or where any of the factory applied coverings or coatings are abraded or damaged in handling or installation, they shall, after necessary repairs have been made with material of the same color as the weather coating, be approved before being installed. Seal completely openings through panels. Correct defects or errors in the materials.
Replace materials which cannot be corrected in an approved manner with nondefective materials. Provide molded closure strips where indicated and where necessary to provide weathertight construction. Use shims as required to ensure attachment clip line is true. Use a spacing gage at each row of panels to ensure that panel width is not stretched or shortened.
3.2.1 Roof Panels
Apply roofing panels with the standing seams parallel to the slope of the roof. Provide roofing panels in longest practical lengths from ridge to eaves (top to eaves on shed roofs), with no transverse joints except at the junction of ventilators, curbs, skylights, chimneys, and similar openings. Install flashing to assure positive water drainage away from roof penetrations. Locate panel end laps such that fasteners do not engage supports or otherwise restrain the longitudinal thermal movement of panels. Form field-formed seam type system seams in the field with an automatic mechanical seamer approved by the manufacturer. Attach panels to the structure with concealed clips incorporated into panel seams. Clip attachment shall allow roof to move independently of the structure, except at fixed points as indicated.
3.2.2 Flashing Fasteners
Fastener spacings shall be in accordance with the panel manufacturer's recommendations and as necessary to withstand the design loads indicated.
Install fasteners in roof valleys as recommended by the manufacturer of the panels. Install fasteners in straight lines within a tolerance of 1/2 inch in the length of a bay. Drive exposed penetrating type fasteners normal to the surface and to a uniform depth to seat gasketed washers properly and drive so as not to damage factory applied coating. Exercise extreme care in drilling pilot holes for fastenings to keep drills perpendicular and centered. Do not drill through sealant tape. After drilling, remove metal filings and burrs from holes prior to installing
SECTION 07 61 14.00 20 Page 13 fasteners and washers. Torque used in applying fasteners shall not exceed that recommended by the manufacturer. Remove panels deformed or otherwise damaged by over-torqued fastenings, and provide new panels.
3.2.3 Rib and Ridge Closure/Closure Strips
Set closure/closure strips in joint sealant material and apply sealant to mating surfaces prior to adding panel.
3.3 PROTECTION OF APPLIED ROOFING
Do not permit storing, walking, wheeling, and trucking directly on applied roofing materials. Provide temporary walkways, runways, and platforms of smooth clean boards or planks as necessary to avoid damage to applied roofing materials, and to distribute weight to conform to indicated live load limits of roof construction.
3.4 CLEANING
Clean exposed sheet metal work at completion of installation. Remove metal shavings, filings, nails, bolts, and wires from roofs. Remove grease and oil films, excess sealants, handling marks, contamination from steel wool, fittings and drilling debris and scrub the work clean.
Exposed metal surfaces shall be free of dents, creases, waves, scratch marks, solder or weld marks and damage to the finish coating.
3.5 MANUFACTURER'S FIELD INSPECTION
Manufacturer's technical representative shall visit the site as necessary during the installation process to assure panels, flashings, and other components are being installed in a satisfactory manner. Manufacturer's technical representative shall perform a field inspection during the first 20 squares of roof panel installation and at substantial completion prior to issuance of warranty, as a minimum, and as otherwise requested by the Contracting Officer. Additional inspections shall not exceed one for 100 squares of total roof area with the exception that follow-up inspections of previously noted deficiencies or application errors shall be performed as requested by the Contracting Officer. Each inspection visit shall include a review of the entire installation to date. After each inspection, a report, signed by the manufacturer's technical representative, shall be submitted to the Contracting Officer noting the overall quality of work, deficiencies and any other concerns, and recommended corrective actions in detail. Notify Contracting Officer a minimum of 2 working days prior to site visit by manufacturer's technical representative.
3.6 COMPLETED WORK
Completed work shall be plumb and true without oil canning, dents, ripples, abrasion, rust, staining, or other damage detrimental to the performance or aesthetics of the completed roof assembly.
3.7 INFORMATION CARD
For each roof, provide a typewritten card, laminated in plastic and framed for interior display or a photoengraved 0.032 inch thick aluminum card for exterior display. Card to be 8 1/2 by 11 inches minimum and contain the information listed on Form 1 at end of this section. Install card near point of access to roof, or where indicated.
SECTION 07 61 14.00 20 Page 14
3.8 FORM ONE
SECTION 07 61 14.00 20 Page 15
FORM 1 - PREFORMED STEEL STANDING SEAM ROOFING SYSTEM COMPONENTS
1. Contract Number:
2. Building Number & Location:
3. NAVFAC Specification Number:
4. Deck/Substrate Type:
5. Slopes of Deck/Roof Structure:
6. Insulation Type & Thickness:
7. Insulation Manufacturer:
8. Vapor Retarder: ( )Yes ( )No
9. Vapor Retarder Type:
10. Preformed Steel Standing Seam Roofing Description:
a. Manufacturer (Name, Address, & Phone No.):
b. Product Name: c. Width: d. Gage:
e. Base Metal: f. Method of Attachment:
11. Repair of Color Coating:
a. Coating Manufacturer (Name, Address & Phone No.):
b. Product Name:
c. Surface Preparation:
d. Recoating Formula:
e. Application Method:
12. Statement of Compliance or Exception:_________________________________
13. Date Roof Completed:
14. Warranty Period: From_______________ To_______________
15. Roofing Contractor (Name & Address):
16. Prime Contractor (Name & Address):
Contractor's Signature _________________________ Date:
Inspector's Signature _________________________ Date:
-- End of Section --
SECTION 07 61 14.00 20 Page 16
| 07 61 14.00 20 - STEEL STANDING SEAM ROOFING |
| PART 1 GENERAL |
| 1.1 REFERENCES |
| 1.2 DEFINITIONS |
| 1.2.1 Field-Formed Seam |
| 1.2.2 Snap Together Seam |
| 1.2.3 Pre-Formed |
| 1.2.4 Field-Formed |
| 1.2.5 Roofing System |
| 1.3 SYSTEM DESCRIPTION |
| 1.3.1 Design Requirements |
| 1.3.2 Design Conditions |
| 1.3.2.1 Wind Uplift |
| 1.3.2.2 Roof Live Loads |
| 1.3.2.3 Thermal Movement |
| 1.3.2.4 Deflection |
1.3.3 Structural Performance
| 1.4 SUBMITTALS |
| 1.5 DESIGN CALCULATIONS |
| 1.6 QUALITY ASSURANCE |
| 1.6.1 Preroofing Conference |
| 1.6.2 Manufacturer |
| 1.6.3 Manufacturer's Technical Representative |
| 1.6.4 Installer's Qualifications |
| 1.6.5 Single Source |
| 1.6.6 Laboratory Tests For Panel Finish |
| 1.7 WARRANTY |
| 1.8 DELIVERY, STORAGE AND HANDLING |
| 1.8.1 Delivery |
| 1.8.2 Storage |
| 1.8.3 Handling |
| PART 2 PRODUCTS |
| 2.1 ROOFING PANELS |
| 2.1.1 Material |
| 2.1.2 Texture |
| 2.1.3 Finish |
| 2.2 Factory Color Finish |
| 2.2.1 Metal Preparation |
| 2.2.2 Prime Coating |
| 2.2.3 Exterior Finish Coating |
| 2.2.4 Interior Finish Coating |
| 2.3 ATTACHMENT CLIPS |
| 2.4 ACCESSORIES |
| 2.4.1 Intake Vent |
| 2.4.2 Ridge Vent |
| 2.4.3 Closures |
| 2.4.3.1 Rib Closures |
| 2.4.3.2 Ridge Closures |
| 2.4.4 Fasteners |
| 2.4.4.1 Screws |
| 2.4.4.2 Bolts |
| 2.4.4.3 Automatic End-Welded Studs |
| 2.4.4.4 Explosive Driven Fasteners |
| 2.4.4.5 Rivets |
| 2.4.5 Sealants |
| 2.4.6 GASKETS AND INSULATING COMPOUNDS |
| 2.5 THERMAL INSULATION |
| 2.6 UNDERLAYMENT MATERIALS |
| PART 3 EXECUTION |
| 3.1 EXAMINATION |
| 3.2 INSTALLATION |
| 3.2.1 Roof Panels |
| 3.2.2 Flashing Fasteners |
| 3.2.3 Rib and Ridge Closure/Closure Strips |
| 3.3 PROTECTION OF APPLIED ROOFING |
| 3.4 CLEANING |
| 3.5 MANUFACTURER'S FIELD INSPECTION |
| 3.6 COMPLETED WORK |