Repair Military Working Dog Area
Building 649 at
Joint Base Charleston – Air Base North Charleston, South Carolina
Charleston County
Specifications Part I
September 20, 2018 Final Design
Project Manager: Patrick Buhler, P.E.
patrickb@adcengineering.com JBC Project No. DKFX 13-1010 ADC Project No. 15307
DEPARTMENT OF THE AIR FORCE
HEADQUARTERS 628TH AIR BASE WING (AMC)
JOINT BASE CHARLESTON SC
04 Nov 2022
MEMORANDUM FOR Record
FROM: 628 CES/CENMP
210 W. Stewart Avenue Joint Base Charleston SC 29404
SUBJECT: Notice of Document Edits
1. This document has been edited after original production and stamp, with permission of the Designer of Record (DOR), Greg Jones, PE.
2. The following specification sections were included in the original specifications produced by ADC Engineering but have been replaced by the Joint Base Charleston Project Manager to reflect current installation standards at the time of solicitation:
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 00 PROJECT SCHEDULE Previously numbered 01 32 16.00 20
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 45 00 QUALITY CONTROL
01 78 00 CLOSEOUT REQUIREMENTS’
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
3. Please direct any questions to the Alex Smith, at (843) 963-1477 or alexander.smith.47@us.af.mil.
Alex Smith, RA Architect / Project Manager 628th Civil Engineer Squadron
Repai r Mi l i t ar y Wor ki ng Dog Ar ea, Bl dg. 649 Fi nal Desi gn JBC Pr oj ect No. DKFX 13- 1010 Sept ember 20, 2018
PROJECT TABLE OF CONTENTS
DI VI SI ON 00 - PROCUREMENT AND CONTRACTI NG REQUI REMENTS
00 01 15 LI ST OF DRAWI NGS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRI CTI ONS
01 30 00 ADMI NI STRATI VE REQUI REMENTS
01 32 16. 00 20 PROJECT SCHEDULE AND PROGRESS DOCUMENTATI ON
01 33 00 SUBMI TTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUI REMENTS
01 42 00 SOURCES FOR REFERENCE PUBLI CATI ONS
01 45 00 QUALI TY CONTROL FOR MI NOR CONSTRUCTI ON
01 45 35 SPECI AL I NSPECTI ONS
01 50 00 TEMPORARY CONSTRUCTI ON FACI LI TI ES AND CONTROLS
01 54 00. 00 31 GREEN PROCUREMENT
01 57 19. 00 31 TEMPORARY ENVI RONMENTAL CONTROLS ( JB CHS- 7/ 2014)
01 57 20. 00 31 ENVI RONMENTAL PROTECTI ON
01 73 29 CUTTI NG AND PATCHI NG
01 74 19. 00 31 CONSTRUCTI ON AND DEMOLI TI ON WASTE MANAGEMENT ( JB CHS)
01 78 00 CLOSEOUT SUBMI TTALS
01 78 23 OPERATI ON AND MAI NTENANCE DATA
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 01 00. 00 GEOTECHNI CAL DATA
02 01 00. 00 10 ENVI RONMENTAL ASSESSMENT
02 41 00 DEMOLITION
DI VI SI ON 03 - CONCRETE
03 30 00 CAST- I N- PLACE CONCRETE
03 39 00. 00 10 CONCRETE CURI NG
DI VI SI ON 04 - MASONRY
04 20 00 MASONRY
DI VI SI ON 05 - METALS
05 12 00 STRUCTURAL STEEL
05 50 13 MI SCELLANEOUS METAL FABRI CATI ONS
DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES
06 10 00 ROUGH CARPENTRY
06 20 00 FI NI SH CARPENTRY
06 41 16. 00 10 LAMI NATE CLAD ARCHI TECTURAL CASEWORK
06 61 16 SOLI D POLYMER ( SOLI D SURFACI NG) FABRI CATI ONS
DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON
07 21 16 MI NERAL FI BER BLANKET I NSULATI ON
07 24 00 EXTERI OR I NSULATI ON AND FI NI SH SYSTEMS
07 60 00 FLASHI NG AND SHEET METAL
07 61 14. 00 20 STEEL STANDI NG SEAM ROOFI NG
PROJECT TABLE OF CONTENTS Page 1 jenniferp Typewritten Text
PART I
07 84 00 FIRESTOPPING
07 92 00 JOI NT SEALANTS
DI VI SI ON 08 - OPENI NGS
08 11 13 STEEL DOORS AND FRAMES
08 14 00 WOOD DOORS
08 51 13 ALUMI NUM WI NDOWS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL LOUVERS
DI VI SI ON 09 - FI NI SHES
09 22 00 SUPPORTS FOR GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 13 CERAMI C TI LI NG
09 51 00 ACOUSTI CAL CEI LI NGS
09 65 00 RESI LI ENT FLOORI NG
09 67 23. 13 RESI NOUS FLOORI NG
09 77 30 SANI TARY WALL FI NI SHES
09 84 30 SOUND- ABSORBI NG UNI TS
09 90 00 PAI NTS AND COATI NGS
DI VI SI ON 10 - SPECI ALTI ES
10 10 00 VI SUAL COMMUNI CATI ONS SPECI ALTI ES
10 14 00. 20 I NTERI OR SI GNAGE
10 26 13 WALL AND CORNER GUARDS
10 28 13 TOI LET ACCESSORI ES
10 44 16 FI RE EXTI NGUI SHERS
DI VI SI ON 12 - FURNI SHI NGS
12 48 13 ENTRANCE FLOOR MATS AND FRAMES ( BI D OPTI ON 2)
DI VI SI ON 13 - SPECI AL CONSTRUCTI ON
13 19 13 KENNEL ENCLOSURES AND GATES
DI VI SI ON 21 - FI RE SUPPRESSI ON
21 13 13. 00 20 WET PI PE SPRI NKLER SYSTEM, FI RE PROTECTI ON
DI VI SI ON 22 - PLUMBI NG
22 00 00 PLUMBI NG, GENERAL PURPOSE
DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)
23 00 00 AI R SUPPLY, DI STRI BUTI ON, VENTI LATI ON, AND EXHAUST SYSTEMS
23 03 00. 00 20 BASI C MECHANI CAL MATERI ALS AND METHODS
23 05 48. 00 40 VI BRATI ON AND SEI SMI C CONTROLS FOR HVAC PI PI NG AND
EQUIPMENT
23 05 93 TESTI NG, ADJUSTI NG, AND BALANCI NG FOR HVAC
23 07 00 THERMAL I NSULATI ON FOR MECHANI CAL SYSTEMS
23 09 23. 02 BACNET DI RECT DI GI TAL CONTROL FOR HVAC AND OTHER BUI LDI NG
CONTROL SYSTEMS
23 81 00. 00 20 UNI TARY AI R CONDI TI ONI NG EQUI PMENT
PROJECT TABLE OF CONTENTS Page 2 jenniferp Typewritten Text
PART II
DI VI SI ON 26 - ELECTRI CAL
26 00 00. 00 20 BASI C ELECTRI CAL MATERI ALS AND METHODS
26 05 48. 00 10 SEI SMI C PROTECTI ON FOR ELECTRI CAL EQUI PMENT
26 08 00 APPARATUS I NSPECTI ON AND TESTI NG
26 09 23. 00 40 LI GHTI NG CONTROL DEVI CES
26 20 00 I NTERI OR DI STRI BUTI ON SYSTEM
26 24 16. 00 40 PANELBOARDS
26 41 00 LI GHTNI NG PROTECTI ON SYSTEM
26 51 00 I NTERI OR LI GHTI NG
26 56 00 EXTERI OR LI GHTI NG
DI VI SI ON 27 - COMMUNI CATI ONS
27 10 00 BUI LDI NG TELECOMMUNI CATI ONS CABLI NG SYSTEM
DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY
28 31 76 FI RE DETECTI ON AND ALARM SYSTEM, ADDRESSABLE
DI VI SI ON 31 - EARTHWORK
31 00 00 EARTHWORK
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 05 33 LANDSCAPE ESTABLI SHMENT
32 11 24 GRADED CRUSHED AGGREGATE BASE COURSE FOR FLEXI BLE PAVEMENT
32 12 10 BI TUMI NOUS TACK AND PRI ME COATS
32 12 16 HOT- MI X ASPHALT ( HMA) FOR ROADS
32 16 13 CONCRETE SI DEWALKS AND CURBS AND GUTTERS
32 31 13 CHAI N LI NK FENCES AND GATES
32 84 24 I RRI GATI ON SPRI NKLER SYSTEMS
32 92 23 SODDING
DI VI SI ON 33 - UTI LI TI ES
33 11 00 WATER UTI LI TY DI STRI BUTI ON PI PI NG
33 30 00 SANI TARY SEWERS
33 40 00 STORM DRAI NAGE UTI LI TI ES
- - End of Pr oj ect Tabl e of Cont ent s - -
PROJECT TABLE OF CONTENTS Page 3
DOCUMENT 00 01 15
LI ST OF DRAWI NGS
02/11
PART 1 GENERAL
1. 1 SUMMARY
Thi s sect i on l i s t s t he dr awi ngs f or t he pr oj ect pur suant t o cont r act c l ause " DFARS 252. 236- 7001, Cont r act Dr awi ngs, Maps and Speci f i cat i ons. "
1. 2 CONTRACT DRAWI NGS
Cont r act dr awi ngs ar e as f ol l ows:
SHEET TI TLE I SSUED
T00 TI TLE SHEET 9/ 20/ 2018
C001 CI VI L ABBREVI ATI ONS & NOTES 9/ 20/ 2018
C002 BORI NG LOGS 9/ 20/ 2018
C003 BORI NG LOGS 9/ 20/ 2018
C004 CSPP - OVERALL 9/ 20/ 2018
C101 EXI STI NG SI TE & DEMOLI TI ON PLAN 9/ 20/ 2018
C102 EXI STI NG SI TE & DEMOLI TI ON PLAN 9/ 20/ 2018
C201 SI TE PLAN 9/ 20/ 2018
C202 SI TE PLAN 9/ 20/ 2018
C301 GRADI NG & STORM DRAI NAGE PLAN 9/ 20/ 2018
C302 GRADI NG & STORM DRAI NAGE PLAN 9/ 20/ 2018
C401 UTI LI TY PLAN 9/ 20/ 2018
C402 UTI LI TY PLAN 9/ 20/ 2018
C620 CI VI L DETAI LS - SI TE 9/ 20/ 2018
C630 CI VI L DETAI LS - STORM DRAI NAGE 9/ 20/ 2018
C640 CI VI L DETAI LS - WATER 9/ 20/ 2018
C641 CI VI L DETAI LS - WATER & SEWER 9/ 20/ 2018
C701 EROSI ON CONTROL PLAN 9/ 20/ 2018
C702 EROSI ON CONTROL PLAN 9/ 20/ 2018
C710 EROSI ON CONTROL DETAI LS 9/ 20/ 2018
C711 EROSI ON CONTROL DETAI LS 9/ 20/ 2018
C712 EROSI ON CONTROL NOTES 9/ 20/ 2018
L201 LANDSCAPE PLAN - AREA 1 9/ 20/ 2018
L202 LANDSCAPE PLAN - AREA 2 9/ 20/ 2018
L301 PLANT SCHEDULE AND DETAI LS 9/ 20/ 2018
G101 LI FE SAFETY PLAN 9/ 20/ 2018
AD101 DEMOLI TON FLOOR PLAN 9/ 20/ 2018
A000 PROJECT I NFORMATI ON & CODE ANALYSI S 9/ 20/ 2018
A001 CONSTRUCTI ON SUBSYSTEMS 9/ 20/ 2018
A002 PARTI TI ON TYPES 9/ 20/ 2018
A100 ARCHI TECTURAL SI TE PLAN 9/ 20/ 2018
A101 RENOVATI ON FLOOR PLAN 9/ 20/ 2018
A102 NEW KENNEL FLOOR PLAN 9/ 20/ 2018
A121 RENOVATI ON RCP 9/ 20/ 2018
A122 NEW KENNEL RCP 9/ 20/ 2018
A151 NEW KENNEL ROOF PLAN 9/ 20/ 2018
A201 RENOVATI ONS ELEVATI ONS 9/ 20/ 2018
A202 NEW KENNEL ELEVATI ONS 9/ 20/ 2018
A301 RENOVATI ON BUI LDI NG SECTI ONS 9/ 20/ 2018
A302 NEW KENNEL BUI LDI NG SECTI ONS 9/ 20/ 2018
A310 WALL SECTI ONS 9/ 20/ 2018
DOCUMENT 00 01 15 Page 1
A320 WALL DETAI LS 9/ 20/ 2018
A321 WALL DETAI LS 9/ 20/ 2018
A401 ENLARGED PLANS AND I NTERI OR ELEVATI ONS 9/ 20/ 2018
A402 ENLARGED PLANS AND I NTERI OR ELEVATI ONS 9/ 20/ 2018
A403 ENLARGED PLANS AND I NTERI OR ELEVATI ONS 9/ 20/ 2018
A403 ENLARGED PLANS AND I NTERI OR ELEVATI ONS 9/ 20/ 2018
A520 CEI LI NG & ROOF DETAI LS 9/ 20/ 2018
A521 CASEWORK DETAI LS 9/ 20/ 2018
A522 CASEWORK DETAI LS 9/ 20/ 2018
A523 MI SC. DETAI LS 9/ 20/ 2018
A603 DOOR & WI NDOW SCHEDULES 9/ 20/ 2018
A604 DOOR DETAI LS 9/ 20/ 2018
A605 WI NDOW DETAI LS 9/ 20/ 2018
A700 FI NI SH LEGEND 9/ 20/ 2018
A701 RENOVATI ON FI NI SH PLAN 9/ 20/ 2018
A702 NEW KENNEL FI NI SH PLAN 9/ 20/ 2018
A730 FURNI TURE PLANS 9/ 20/ 2018
S001 GENERAL NOTES 9/ 20/ 2018
S100 FOUNDATI ON PLAN 9/ 20/ 2018
S102 SLAB PLAN 9/ 20/ 2018
S103 WALL PLAN 9/ 20/ 2018
S104 LOW ROOF FRAMI NG PLAN 9/ 20/ 2018
S105 HI GH ROOF FRAMI NG PLAN 9/ 20/ 2018
S201 SCHEDULES 9/ 20/ 2018
S211 TYPI CAL DETAI LS 9/ 20/ 2018
S212 TYPI CAL DETAI LS 9/ 20/ 2018
S221 TYPI CAL DETAI LS 9/ 20/ 2018
S222 TYPI CAL DETAI LS 9/ 20/ 2018
S223 TYPI CAL DETAI LS 9/ 20/ 2018
S231 TYPI CAL DETAI LS 9/ 20/ 2018
S232 TYPI CAL DETAI LS 9/ 20/ 2018
S301 GABEL TRUSS ELEVATI ON 9/ 20/ 2018
S501 FOUNDATI ON SECTI ONS 9/ 20/ 2018
S502 WALL SECTI ONS 9/ 20/ 2018
S503 ROOF FRAMI NG SECTI ONS 9/ 20/ 2018
S504 ROOF FRAMI NG SECTI ONS 9/ 20/ 2018
M001 HVAC - NOTES & LEGENDS 9/ 20/ 2018
M002 HAVC SEI SMI C & SCHEDULES 9/ 20/ 2018
M003 HVAC DETAI LS 9/ 20/ 2018
M004 HVAC DETAI LS 9/ 20/ 2018
M005 HVAC DETAI LS 9/ 20/ 2018
M006 HVAC DETAI LS 9/ 20/ 2018
M050 HVAC DEMOLI TI ON PLAN 9/ 20/ 2018
M101 RENOVATI ON HVAC PLAN 9/ 20/ 2018
M201 NEW KENNEL HVAC PLAN 9/ 20/ 2018
E001 ELECTRI CAL NOTES 9/ 20/ 2018
E002 ELECTRI CAL LEGENDS 9/ 20/ 2018
E003 ELECTRI CAL SCHEDULES & DETAI LS 9/ 20/ 2018
E004 ELECTRI CAL DETAI LS 9/ 20/ 2018
E005 LI GHTNI NG PROETECI ON DETAI LS 9/ 20/ 2018
E010 ELECTRI CAL ONE- LI NE DI AGRAM 9/ 20/ 2018
E011 ELECTRI CAL PANEL SCHEDULES 9/ 20/ 2018
E050 RENOVATI ON ELECTRI CAL DEMOLI TI ON PLAN 9/ 20/ 2018
E051 RENOVATI ON SYSTEMS DEMOLI TI ON PLAN 9/ 20/ 2018
E052 RENOVATI ON POWER &TELECOM DEMOLI TI ON PLAN 9/ 20/ 2018
E100 ELECTRI CAL SI TE PLAN 9/ 20/ 2018
E101 RENOVATI ON POWER &TELECOM PLAN 9/ 20/ 2018
E102 RENOVATI ON LI GHTI NG PLAN 9/ 20/ 2018
E103 RENOVATI ON SYSTEMS PLAN 9/ 20/ 2018
DOCUMENT 00 01 15 Page 2
E201 NEW KENNEL POWER & TELECOM PLAN 9/ 20/ 2018
E202 NEW KENNEL LI GHTI NG PLAN 9/ 20/ 2018
E203 NEW KENNEL SYSTEMS PLAN 9/ 20/ 2018
E204 NEW KENNEL ROOF PLAN 9/ 20/ 2018
FP001 FI RE PROTECTI ON NOTES, LEGENDS & DETAI LS 9/ 20/ 2018
FP101 RENOVATI ON FI RE PROTECTI ON PLAN 9/ 20/ 2018
FP102 NEW KENNEL FI RE PROTECTI ON PLAN 9/ 20/ 2018
P001 PLUMBI NG NOTES & LEGENDS 9/ 20/ 2018
P002 PLUMBI NG SCHEDULES 9/ 20/ 2018
P003 PLUMBI NG DETAI LS 9/ 20/ 2018
P050 PLUMBI NG DEMOLI TI ON PLAN 9/ 20/ 2018
P101 RENOVATI ON DOMESTI C WATER PLAN 9/ 20/ 2018
P102 RENOVATI ON SANI TARY PLAN 9/ 20/ 2018
P201 NEW KENNEL DOMESTI C WATER PLAN 9/ 20/ 2018
P202 NEW KENNEL SANI TARY PLAN 9/ 20/ 2018
- - End of Document - -
DOCUMENT 00 01 15 Page 3
Repair Military Working Dog Area, Bldg. 649 Revised JBC Project No. DKFX 13-1010 September 16, 2022
Section 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
JB Charleston (Dec 2021)
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The work includes reconfiguring site plan to accommodate a new kennel facility and incidental related work. The new Kennel Facility contains 10 pens and outdoor runs, a food prep, and bath area. Site areas to be provided include a relocated obedience course and a break area for the military working dogs. Existing obedience course equipment will be reused. New water, firewater, electrical, and sewer service utilities will be provided to the new kennel building.
1.1.2 Location
The work shall be located on Joint Base Charleston (JBC) Air Base (AB), approximately as indicated. The exact location will be shown by the Contracting Officer.
1.2 OCCUPANCY OF PREMISES
Building(s)will be occupied during performance of work under this Contract.
Before work is started, the Contractor shall arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.3 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer or Contracting Officer’s Representative. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.4 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located on Joint Base Charleston.
Section 01 11 00 Page 2
Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
Section 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
PART 1 GENERAL
1.1 SUBMITTALS
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Air Force – Base Civil Engineering – Dig Permit Request; FIO
Approved Utility Outage Request; FIO
Approved Road Closure Requests; FIO
List of Contact Personnel; FIO
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. Obedience Course must be ready for operation as approved by Contracting Officer before work is started on the New Kennel Facility which would interfere with normal operation.
b. The existing military working dog facility (B649) will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Requirements for security and base access varies between various locations within Joint Base Charleston. It is incumbent on the Contractor to ascertain the current security and base access requirements appropriate to the project location and incorporate the cost, if any, for compliance to said requirements into Contractor's proposal. Lack of knowledge of current requirements does not constitute a basis for an adjustment to the contract.
Should requirements change during the construction timeframe, Contractor may be eligible, subject to documentation acceptable to the Government, for an adjustment to the contract.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.3.1.2 Additional Personnel Requirements
Section 01 14 00 Page 2
1.3.1.3 Identification Badges/Passes
Identification badges/passes are required for unescorted access beyond 1 day per 12 month period. Contractor shall confirm the most current security requirements with the Contracting Officer or Base Sponsor. Application for and use of badges shall be as directed based on current access requirements. Contractor shall furnish a completed Joint Base Charleston (JB CHS) Worksheet for Base Access form for all personnel requesting badges/passes for Base Sponsor digital signature no later than 7 calendar days in advance of needing a badge/pass. The most current version of this form can be obtained from the Base Sponsor. The Prime Contractor shall be responsible for filling out the form accurately and delivering a signed copy of the form with required supporting documentation (including photo identification in accordance with Real ID Act) to the Air Base or Weapons Station Visitor Control Center (VCC) after obtaining sponsor signature.
The Prime Contractor is responsible for the accuracy of worksheet information and proper use of all badges/passes issued for purposes related to their contract. Badges/passes shall only be used to access the locations specified, for the purposes specified, during the dates and times specified. When Applicants no longer requires access, it is the Prime Contractor’s responsibility to ensure all access badges/passes are promptly returned to the issuing VCC. Contractor shall immediately report instances of lost or stolen badges/passes to the Base Sponsor. Any noncompliance with Joint Base Charleston, USAF, DOD, and Federal policies and directives could result in adverse contract action, legal action, and/or being barred from the installation.
1.3.1.4 Tobacco Use Policy
Tobacco use is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation.
Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.3.2 Working Hours
Regular working hours will consist of an 8 1/2 hour period established by the Contracting Officer, between 7 a.m. and 3:30 p.m., Monday through Friday, excluding Government holidays.
1.3.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.
Section 01 14 00 Page 3
1.3.4 Occupied and Existing Building[s]
The Contractor shall be working around existing buildings which are occupied. Do not enter the buildings without prior approval of the
1.3.6 Road Closure and Utility Outage Requests
a. Make road closures and utility outages after normal working hours or on Saturdays, Sundays, and Government holidays when practical. Road closure and utility outage requests shall be transmitted to the Contracting Officer or the Contracting Officer’s Representative for coordination and Government approval at least 21 calendar days prior to the desired outage or closure date. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS. Road closure and utility outage requests shall be identified on the Contractor’s Three (3)-Week Look Ahead Schedule.
b. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
1.3.7 ON-SITE PERMITS
1.3.7.1 Dig Permit Request
1.3.7.1.1 South Carolina 811
a. Prior to submitting a dig permit request, the Contractor shall contact
South Carolina Palmetto Utility Protection Services (PUPS) and obtain a PUPS tracking number.
b. Locators use the APWA Uniform color code to mark underground facilities. Each color represents a different type of utility:
Red – Electric Power Lines, Cables, Conduit or Lightning Cables Yellow – Gas, Oil, Steam, Petroleum or Gaseous Material Orange – Communication, Cable TV, Signal Cables, or Telephone Blue – Potable Water Green – Sewer or Drain Lines Pink – Temporary Survey Markings Purple – Reclaimed Water, Irrigation, or Slurry Lines White – Proposed Excavation
1.3.7.1.2 Air Force – Base Civil Engineering – Dig Permit Request
a. Complete the Air Force – Base Civil Engineering – Dig Permit Request and transmit to the Contracting Officer or the Contracting Officer Representative for routing and approval 14 calendar days prior to the desired outage or closure date.
b. The Contractor is responsible for verifying all utilities prior to excavation. The Contractor is responsible for maintaining all markings
Section 01 14 00 Page 4 on the project site throughout excavation. The markings shall be kept current throughout the contract period of performance – transmit to the Contracting Officer or the Contracting Officer Representative for routing and re-approval every 21 Calendar Days after initial approval to avoid an expired permit.
c. The Contractor is responsible to verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated to be specified or removed but indicated or discovered in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
d. Notify the Contracting Officer or the Contracting Officer Representative at least 48 hours prior to starting excavation work.
Not Used
Section 01 30 00 Page 1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
Resume for the proposed Superintendent; G
Preconstruction Survey; FIO
SD-07 Certificates
Progress and Completion Pictures; FIO
1.2 PRECONSTRUCTION SURVEY AND PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Submit these photographs with a narrative report indicating the existing conditions of the project site prior to mobilization.
Provide monthly, and within one month of the completion of work, digital photographs, 1600 x 1200 x 24 bit true color 5-megapixel minimum resolution in jpeg file format showing the sequence and progress of work.
Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views from points located by the Contracting Officer’s Representative. Submit a view location sketch indicating points of view upon request.
Photographs for each month shall be in a separate monthly directory and each file name shall include a date designator. Cross-reference submittals in the appropriate daily report. Photographs shall be provided for unrestricted use by the Government.
1.3 MINIMUM INSURANCE REQUIREMENTS
Procure and maintain during the entire period of performance under this contract the following minimum insurance coverage:
a. Comprehensive general liability: $500,000 per occurrence
b. Automobile liability: $200,000 per person, $500,000 per occurrence for bodily injury, $20,000 per occurrence for property damage
Section 01 30 00 Page 2
c. Workmen's compensation as required by Federal and State workers' compensation and occupational disease laws.
d. Employer's liability coverage of $100,000, except in States where workers compensation may not be written by private carriers.
e. Others as required by State law.
1.4 CONTRACTOR SPECIAL REQUIREMENTS
1.4.1 Space Temperature Control, HVAC TAB, and Apparatus Inspection
All contract requirements of Section 23 05 93 TESTING, ADJUSTING AND BALANCING FOR HVAC, Section 23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING CONTROL SYSTEMS, and Section 26 08 00 APPARATUS INSPECTION AND TESTING shall be accomplished directly by a first tier subcontractor, including the Commissioning Agent. No work required by Section 23 05 93, 23 09 23.02, or 26 08 00 shall be accomplished by a second tier subcontractor.
1.5 SUPERVISION
1.5.1 Minimum Communication Requirements
Have at least one qualified superintendent capable of reading, writing, and conversing fluently in the English language, on the job-site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.
1.5.2 Superintendent Qualifications
Superintendent must have a minimum of 5 years experience as a project manager, project engineer, superintendent, or quality control manager on projects similar in size, scope and complexity to this project as identified in Section 01 11 00. The project superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.
Furthermore, the Contracting Officer may issue an order stopping work on all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop work orders shall be made the subject of a claim for extension of time for excess costs or damages by the contractor.
Approval of the project superintendent is required prior to the start of construction. Provide a resume for the proposed superintendent describing their experience with references and qualifications to the contracting officer for approval. The contracting officer reserves the right to interview the proposed project superintendent at any time in order to verify the submitted qualifications.
1.6 PRECONSTRUCTION CONFERENCE
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the contract and safety program, preparation of the schedule of prices, shop drawings, and other
Section 01 30 00 Page 3 submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.
1.7 AVAILABILITY OF CADD DRAWING FILES
After award and upon request, the electronic "Computer-Aided Drafting and Design (CADD)" drawing files will only be made available to the Contractor for use in preparation of construction drawings and data related to the referenced contract subject to the following terms and conditions.
Data contained on these electronic files shall not be used for any purpose other than as a convenience in the preparation of construction drawings and data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic CADD drawing files are not construction documents.
Differences may exist between the CADD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CADD files, nor does it make representation to the compatibility of these files with the Contractors hardware or software. In the event that a conflict arises between signed and sealed construction documents prepared by the Government and the furnished CADD files, the signed and sealed construction documents shall govern. The Contractor is responsible for determining if any conflict exists. Use of these CADD files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.
If the Contractor uses, duplicates and/or modifies these electronic CADD files for use in producing construction drawings and data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.
1.8 ELECTRONIC MAIL (E-MAIL) ADDRESS
The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats. Within 10 days after contract award, the Contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats, etc.. Multiple email addresses will not allowed.
Section 01 30 00 Page 4
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to this email address.
SECTION 01 32 00
PROJECT SCHEDULE
1.1 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
Project Scheduler Qualifications; G
Baseline Cost Loaded Critical Path Method (CPM) Project Schedule; G
Schedule and Pay Request Calendar; G
SD-07 Certificates
Monthly Cost Loaded CPM Project Schedule Updates; G
SD-11 Closeout Submittals
As-Built Schedule; G
1.2 PROJECT SCHEDULER QUALIFICATIONS
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 5-years’ experience scheduling construction projects similar in size and nature, as identified in Section 01 11 00, to this project with scheduling software that meets the requirements of this specification.
Representative must have a comprehensive knowledge of CPM scheduling principles and application. A resume outlining the individual’s qualifications shall be submitted for acceptance by the Contracting Officer.
2.1 SOFTWARE
The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this specification.
2.1.1 Contractor Software
Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available.
2.1.1.1 Primavera
If Primavera P6 is selected for use, provide the P6 "xer" export file.
Additionally, provide an exported .pdf files for submittal review IAW the “Schedule Reports” paragraph.
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel shall actively participate in the development of the schedule and coordinate closely with the Contracting Officer, Contracting Officer's Representative, and Facility Manager(s) in its maintenance. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.
Prepare each Project Schedule using the Precedence Diagram Method (PDM) to control, budget, and invoice project activities. For consistency, when scheduling software terminology is used in this specification, the terms in Primavera’s scheduling programs are used.
3.2 BASIS FOR PAYMENT AND COST LOADING
The Baseline Cost Loaded CPM Project Schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.
Lack of an approved updated Cost Loaded CPM Project Schedule may result in an inability of the Contracting Officer to evaluate the Contractor's progress for the purposes of payment. The Baseline Cost Loaded CPM Project Schedule shall be submitted for approval within 30 calendar days after the Notice of Award has been acknowledged.
The Contractor is responsible for scheduling, sequencing, budgeting, and executing work to comply with the requirements of the Contract Documents.
Government acceptance extends only to the activities of the Contractor’s schedule that the Government has been assigned responsibility and agrees it is responsible. Comments offered on other parts of the schedule, to which the Contractor is assigned responsibility, are offered as a courtesy and are not conditions of Government acceptance; but are for the general conformance with established industry scheduling concepts.
The Contractor shall submit a Schedule and Pay Request Calendar with the Baseline Cost Loaded CPM Project Schedule within 30 calendar days after the Notice of Award has been acknowledged. Reference Attachment A as an example. The Schedule and Pay Request Calendar shall forecast dates for the following:
a. Contractor Provides Draft Monthly Cost Loaded CPM Schedule Update and Narrative to JB Charleston.
b. Contractor Conducts Monthly Periodic Schedule Meeting with JB Charleston.
c. Contractor Submits Final Monthly Cost Loaded CPM Schedule Update and all Reports.
d. Contractor Provides Approved Monthly Cost Loaded CPM Schedule Update and Submits Pay Application (AIA Style) to JB Charleston.
e. Contractor Submits Approved Invoice for Payment in Wide Area Work Flow (WAWF).
Reference Attachment A – Schedule and Pay Request Calendar as an example submittal requirement. An excel spreadsheet version of this calendar can be provided upon request.
All pay applications may be submitted using the AIA Document G702-1992, Application and Certificate for Payment, and G703-1992, Continuation Sheet.
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.
The Contractor is advised to refer to the contract’s payments clause for more detail relative to payment for stored material or equipment. Material and Equipment Costs for which payment will be requested in advance of installation shall be assigned to their respective procurement activity (i.e., the material/equipment on-site activity). All other construction costs shall be assigned to their respective Construction Activities. The value of inspection/testing activities will not be less than 10 percent of the total costs for Procurement and Construction Activities. Evenly disperse overhead and profit to each activity over the duration of the project.
Each cost-loaded activity shall have a detailed quantity breakdown and unit of measure.
3.2.2 Withholdings / Payment Rejection
Failure to meet the requirements of this specification may result in the disapproval of the baseline or periodic schedule updates and subsequent rejection of payment requests until compliance is met.
In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, review and approval of pay applications may be delayed.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods. Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 28 calendar days.
3.3.3 Procurement Activities
Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.4 Mandatory Tasks
Include the following activities/tasks in the baseline project schedule and all updates.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals
(individual activity for each).
b. Submission, review and acceptance of features require design completion.
c. Submission of mechanical/electrical/information systems layout drawings.
d. Long procurement activities
e. Submission and approval of O & M manuals.
f. Submission and approval of as-built drawings.
g. Submission and approval of DD1354 data and installed equipment lists.
h. Submission and approval of testing and air balance (TAB).
i. Submission and approval of fire protection specialist.
j. Building commissioning - Functional Performance Testing.
k. Controls testing.
l. Performance Verification testing.
m. Pre-Warranty Conference.
n. Other systems testing, if required.
o. Contractor's pre-final inspection.
p. Correction of punch list from Contractor's pre-final inspection.
q. Government's pre-final inspection.
r. Correction of punch list from Government's pre-final inspection.
s. Final inspection.
3.3.5 At a minimum, each activity shall include the following information:
a. Activity ID
b. Activity Description
c. Calendar
d. Original Duration in Calendar Days
e. Early Start Date
f. Early Finish Date
g. Late Start Date
h. Late Finish Date
i. Total Float
j. Contract Line Item Number (CLIN)(i.e.: CLIN 0001, CLIN 0002, etc.)
3.3.6 Government Activities
Show Government and other agency activities that could impact progress.
These activities include, but are not limited to: approvals permit approvals by State regulators, inspections, utility tie-in/outages, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.
3.3.7 Contract Milestones and Constraints
Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.
Mandatory constraints that ignore or affect network logic are prohibited.
No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.
3.3.7.1 Contract Award Date Milestone:
The Contractor shall include as the first activity on the schedule a start milestone titled "Contract Award", which shall have a Mandatory Start constraint equal to the Contract Award Date.
3.3.7.2 Project Start Date Milestone and Constraint:
The Contractor shall include as an activity after award on the schedule a start milestone titled "Notice to Proceed (NTP)", which shall have a Mandatory Start constraint equal to the date the Notice to Proceed is acknowledged.
3.3.7.3 Projected Completion Milestone:
The Contractor shall include an unconstrained finish milestone on the schedule titled "Projected Completion", indicating the point in time at which the project is complete and ready for its intended use. This milestone shall have the Contract Completion Date (CCD) as its only successor.
3.3.7.4 Contract Completion Date (CCD) Milestone:
The Contractor shall include as the last activity on the schedule a finish milestone titled "Contract Completion (CCD)", which shall have a Finish on or Before constraint equal to the Contract Completion Date.
The only predecessor to the Contract Completion Date Milestone shall be the Projected Completion Milestone. The CCD Shall be equal to the Period of Performance (in Calendar Days) added to the NTP date.
Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "Contract Completion Date" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "Contract Completion Date" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.
3.3.7.5 Interim Completion Dates and Constraints
Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.
3.3.7.6 Start Phase
Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.
3.3.7.7 End Phase
Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.
3.3.8 Calendars
Schedule activities on a Calendar to which the activity logically belongs.
Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc.
Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop Seasonal Calendar(s) and assign to seasonally affected activities as applicable.
All activity durations and float values shall be shown in calendar days.
Default activity type shall be set to “Task” and the project “Must Finish By” date shall be left blank.
3.3.8.1 Monthly Anticipated Adverse Weather Delays - in Calendar Days
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 6 5 5 5 5 8 9 9 7 5 4 6
If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated adverse weather delay days. The above chart in paragraph 3.3.8.1 indicates the amount of weather days to be accounted for in the Critical Path Method Schedule for those activities that are weather sensitive. A lost workday due to weather conditions is defined as a day in which the Contractor cannot reasonably work at least 50 percent of the day on the impacted activity.
Use the National Oceanic and Atmospheric Administration's (NOAA) Summary of Monthly Normals report to obtain the historical average number of days each month with precipitation, using a nominal 30-year, greater than 0.10 inch precipitation amount parameter, as indicated on the Station Report for the NOAA location closest to the project site as the basis for establishing a "Weather Calendar" showing the number of anticipated Non-workdays for each month due to adverse weather, in addition to Saturdays, Sundays and all Federal Holidays as non-work days. Table 3.3.8.1 indicates this anticipated schedule for Joint Base Charleston.
3.3.8.2 Government Holidays
The following holidays shall be incorporated into the Project Schedule as non-work days. Follow the procedures identified in Specification 01 14 00 to request work on the following days. Reference the Office of Personnel Management Website (https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/#url=Overview) for the most current information regarding Government Holidays and the specific days for observance:
New Year’s Day
Birthday of Martin Luther King, Jr.
Washington’s Birthday
Memorial Day
Juneteenth National Independence Day
Independence Day
Labor Day
Columbus Day
Veterans Day
Thanksgiving Day
Christmas Day
3.3.9 Open Ended Logic
Only two open ended activities are allowed: the first activity "Contract Award Date" may have no predecessor logic, and the last activity, "Contract Completion Date" may have no successor logic.
Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.
3.3.10 Default Progress Data Disallowed
Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule.
3.3.11 Out-of-Sequence Progress
Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer. Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.
3.3.12 Added and Deleted Activities
Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer. Activity ID and description changes are considered new activities and cannot be changed without Contracting Officer approval.
3.3.13 Original Durations
Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.
3.3.14 Leads, Lags, and Start to Finish Relationships
Lags, Leads (negative lags), and Start-to-Finish (SF) relationships are prohibited.
3.3.15 Retained Logic
Schedule calculations must retain the logic between predecessors and successors ("retained logic" mode) even when the successor activity(s) starts and the predecessor activity(s) has not finished (out-of-sequence progress). Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") are not be allowed.
3.3.16 Percent Complete
Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete to allow for proper schedule management.
3.3.17 Remaining Duration
Update the remaining duration for each activity based on the number of estimated calendar days it will take to complete the activity.
Remaining duration may not mathematically correlate with percentage found under paragraph entitled Percent Complete.
3.3.18 Cost Loading of Closeout Activities
Cost load the "Correction of punch list from Government pre-final inspection" activity(ies) not less than 1 percent of the present contract value. Activity(ies) may be declared 100 percent complete upon the Government's verification of completion and correction of all punch list work identified during Government pre-final inspection(s).
3.3.18.1 As-Built Drawings
If there is no separate contract line item (CLIN) for as-built drawings, cost load the "Submission and approval of as-built drawings" activity not less than 1 percent of the present contract value. Activity will be declared 100 percent complete upon the Government's approval.
3.3.18.2 O & M Manuals
Cost load the "Submission and approval of O & M manuals" activity not less than 1 percent of the overall contract value. Activity will be declared 100 percent complete upon the Government's approval of all O & M manuals.
3.3.19 Early Completion Schedule and the Right to Finish Early
An Early Completion Schedule is a Baseline Project Schedule that indicates all scope of the required contract work will be completed before the contractually required completion date.
a. No Baseline Project Schedule indicating an Early Completion will be accepted without being fully resource-loaded (including crew sizes and man-hours) and the Government agreeing that the schedule is reasonable and achievable.
b. The Government is under no obligation to accelerate work items it is responsible for to ensure that the early completion is met nor is it responsible to modify incremental funding (if applicable) for the project to meet the contractor's accelerated work.
c. If an Early Completion Schedule is proposed by the Contractor and accepted by the Government, the difference between the Early Completion CCD and the…