This document is a set of Questions and Answers related to a federal contract opportunity for Flooring Installation and Painting services at Hurlburt Field. The key details are:
The government intends to award up to two Blanket Purchase Agreements (BPAs) for painting in dormitories and flooring installation throughout the base. Contractors must comply with the mandatory Air Force Carpet II program, purchasing products from Tier I suppliers. Painting requirements include semi-gloss finishes for walls, metal doors, and moisture-resistant "green-board" in bathrooms. The BPAs will have a $25,000 call limit and a $4 million ceiling, with a 4-year period of performance. Questions cover topics such as site visits, working hours, hazardous materials, disposal, pricing, and security requirements for contractor personnel. Contractors should carefully review the Statement of Work and BPA documents for complete details on the requirements and proposal submission.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. Are there any additional color/material preferences for paint and flooring beyond the SOW?
Answer: Paint finish for walls will be semi-gloss. Exterior doors are metal with metal frame, paint must be compatible. Interior doors are wood, paint must be compatible. Bathroom walls are moisture-resistant gypsum “green-board” or similar; paint will be semi-gloss in bathroom areas.
2. Any specific restrictions on working hours, especially for noisy tasks?
Answer: See paragraph 3.2 of SOW for updated details.
3. What dates and times are available for a site visit?
Answer: As stated in SAM.gov posting, a site visit for this requirement will NOT be held. All site visits will be conducted after the signing of the Blanket Purchase Agreement and once a requirement (project) has been identified and funded.
4. Will access include all relevant dormitories and common areas?
Answer: Contractor will have access to specific work areas as requirements (projects) are identified and funded. Hours and days will be coordinated prior to beginning work.
5. Who will be our point of contact during the visit, and any security protocols?
Answer: After BPA is established, project specific site visits will be conducted with either the Dorm Management or CE Inspector. These site visits will be for measurement purposes.
6. Any certifications or forms required with the proposal?
Answer: Contractors are encouraged to carefully read SOW AND Combo Dorm Paint- Flooring BPA document; specifically, 52.212-1 Instructions to Offerors
7. Are there additional steps or documents needed for handling hazardous materials?
Answer: Provided in SOW
8. Is there an on-site disposal area for non-hazardous waste?
Answer: Instructions for recycle material is identified in the SOW. Contractor responsible for removal and disposal of all other materials.
9. What’s the required response time after a BPA call is issued? Also should contractor submit a BPA for the entire duration of the contract term or just the estimate for work as needed.
Answer: Period of performance for each “Call” or Task Order will be negotiated prior to award of the project.
10. Any critical deadlines for specific phases?
Answer: All period of performance dates are established around mission requirements and access to the work area. Consideration for time will be given prior to award or as modified by the Contracting Officer.
11. Will background checks or clearance be needed for contractor personnel?
Answer: Security Forces will conduct a review of all personnel prior to being granted access to the installation. The following will result in an individual being denied access:
The individual is known to be or reasonably suspected of being a terrorist or belongs to an organization with known terrorism links/support.
■ The installation is unable to verify the individual's claimed identity.
■ The individual has previously been barred from access to a federal installation or stand-alone facility.
■ The individual is wanted by Federal, State, Local, or other civil law enforcement authorities, regardless of offense or violation.
■ The individual has any conviction for espionage, sabotage, treason, terrorism, or murder.
■ The individual's name appears on any Federal or State agency's watch list or hit list for criminal behavior or terrorist activity.
■ The individual has been convicted of a firearms or explosive violation.
■ The individual has been convicted of sexual assault, armed robbery, rape, child molestation, child pornography, trafficking in humans, drug possession with intent to sell, or drug distribution.
■ The individual has knowingly and willfully engaged in acts or activities designed to overthrow the U.S.
Government by force.
■ prohibited items include weapons, drugs, alcoholic beverages, and photographic equipment
■ Foreign Nationals must have a valid Passport, work visa, and social security card with them.
12. Are special access badges required, and what’s the processing time?
Answer: Processing time can vary depending on day, time and number of vehicles at the gate. Contractor personnel should plan ahead.
13. Is there flexibility on pricing for materials outside Tier I suppliers if cost-effective?
Answer: No, all carpet products are required to use the “MANDATORY” Air Force Carpet II contract and Tier I suppliers.
14. What was the previous award amount for this contract, if any?
Answer: There were two (2) BPA’s previously awarded; FA441723A0009 and FA441723A0010, both with a Not to Exceed (NTE) amount of $1M each.
15. How do I properly complete my application for this BPA?
Answer: See answer to Question #6 above.
16. Regarding the painting requirements for dorms: What type of paint finish is needed (flat, satin, semi-gloss, gloss, or epoxy)? What type for window/door frames? How many of the bathrooms have wallcoverings for sanding and Kilz?
Answer: See Answer 1 above.
17. Will photo’s or floor plans be available for contractors to view?
Answer: No, Paragraph 1.6 of Attachment 001 (SOW) provides approximate square footage and measurements for painting, carpet and cove base for each of the dormitory buildings.
Additional buildings on base, for flooring requirements, will vary.
18. Under the Furniture heading on the price list, does “replace” mean place back and/or reassemble?
Answer: Replace means put furniture back in position. If disassembly was used to remove the furniture, it must be reassembled when put back in position. In some cases, furniture may be “lifted” to accommodate removal and installation of new flooring product. This would be considered contractors “means and methods” depending on how work is accomplished.
19. Does the freight line item mean storage for a different location for furniture while work is being done?
Answer: No, the freight line item is for shipping charges associated with carpet and/or flooring materials (if required).
20. Is the objective to award two (2) BPA’s for painting and flooring or award one (1) for painting and another for flooring?
Answer: The government intends to award (up to) 2 BPA’s, both to include flooring installation throughout the base and painting in the dormitories only.
21. Does the government purchase the carpet under the BPA, or, is the contractor required to purchase the carpet and invoice for reimbursement?
Answer: You are encouraged to carefully read the USAF Carpet II Program Ordering Guide at Attachment 003.
22. Will the government update the pricing list with different materials as needed in the future for each service call? Currently, the price list only reflects Engineered Floors (J&J) Passages and Wellversed modular carpet tiles.
Answer: Yes, in the future, the Government may select a carpet product other than what is currently on the price list as long as its provided by one of the seven (7) Tier I suppliers. The facility manager (end-user) for each project will determine the specific manufacturer and style. Contractors selected for a BPA award will be responsible for obtaining prices for alternate products as requirements are identified and Request for Proposals are issued. For the purpose of establishing a BPA(s), contractors shall price only those identified on the price list.
23. Will there be a recycling facility or trailer on base?
Answer: Yes, paragraph 1.2 of the SOW has been updated to include the address for the recycling center on base.
24. Will the government provide dumpsters or will the contractor be responsible for staging dumpsters?
Answer: NO, the contractor is responsible. See paragraph 1.2 of the SOW.
25. What is the scope of work for the Theater?
Answer: There is not an existing requirement for the base theater. SOW paragraph 1.8.1 states that in the event that a facility has theater style seats that are bolted to the floor, the contractor will be responsible for removing and reinstalling the seats for the purpose of installing new flooring materials.
26. What is the next step in bidding this project? Where is the BPA Agreement Form?
What/where is the “Vendor Information” located in the set of attachments?
Answer(s): 1) See 52.212-1- Instructions to Offerors located on the Combo Dorm Paint Flooring BPA document. 2) After the government evaluates offers and selects a successful contractor or contractors, the government will draft the agreement on a SF 1449. This form will include terms and conditions as well as the attached referenced within the combination synopsis-solicitation. This agreement will require signature by both parties. 3) Do not understand the question.
27. How should we price carpet selections? Price list (attachment 004) only identifies two (2) carpet selections with a quantity of one (1) and unit of EACH.
Answer: The two products identified on the price list are the most common product used on Hurlburt but are NOT the only product that may be used under this BPA. Customers may select any product included under the Air Force Carpet II program. If the customer selects a product other than the two (2) currently on the price list, the contractor will submit a proposal for that requirement using the Not to Exceed (NTE) price established under the AF Carpet II program. Contractors shall propose using UNIT detailed in the AF Carpet II program. IF CARPET IS PRICED BY SQUARE YARD (SY), CONTRACTOR SHALL PROPOSE BY
SQUARE YARD. IF CARPET TILE IS PRICED BY EACH (EA), CONTRACTOR SHALL PROPOSE
BY EACH TILE. Contractors shall not adjust the unit of measure on Attachment 004.