This solicitation is for a firm-fixed price construction contract to provide all labor, materials, equipment and supervision necessary to complete an addition to an existing Child Development Center building at Hurlburt Field, Florida. The approximately 3,850 square foot addition will include 3 infant activity rooms, corridors and support spaces, along with an outdoor play area of approximately 1,250 square feet. The contractor will be responsible for minor demolition, site work, utilities, finishes and casework. The period of performance is 330 calendar days from notice to proceed. The solicitation includes plans and specifications for the work dated September and October 2023. Responses are due by close of business on November 3rd, 2023.

View the file

Other files

File Type Posted
SOLICITATION as of AMENDMENT 0004 - FA441723R0009 CONFORMED.pdf PDF
RFIs FINAL_7 NOV 2023 - FA441723R0009 Addition CDC W B90306.pdf PDF
AMENDMENT 4 - FA441723R0009-0004 - Released.pdf PDF
PHOTOS OF THE ELECTRICAL ROOM AT CDC WEST BLDG 90306.docx DOCX document
RFIs_ 2 NOV 2023_FA441723R0009 Addition CDC W B90306.pdf PDF
SITE VISIT CONTRACTOR ATTENDANCE 26 Oct 2023.pdf PDF
AMENDMENT 3 - FA441723R0009-0003.pdf PDF
AMENDMENT 2 - FA441723R0009-0002.pdf PDF
VOIDED Solicit Amendment 1_FA441723R0009-0001 SF 30.pdf PDF
ATCH 3 - WAGE DETERMINATION_ DTD 29 September 2023.pdf PDF
SOLICITATION FA441723R0009 CDC WEST BLDG 90306.pdf PDF
Site Visit Attendees - Solicitation FA441723R0009.pdf PDF
Solicitation Amendment FA441723R0009-0001 SF 30.pdf PDF
ATCH L4 - Contract Progress Schedule_AF Form 3064 - Fillable.xlsx XLSX spreadsheet
ATCH L3 - 50 Div Construction Cost Est Wksht.xlsx XLSX spreadsheet
ATCH L1 - Past Present Performance Questionnaire.pdf PDF
ATCH 2 - DRAWINGS - Addition to CDC West Bldg 90306.pdf PDF
ATCH 3 - WAGE DETERMINATION NO FL20220217 Dtd 12 Jan 2023.pdf PDF
Solicitation - FA441723R0009.pdf PDF
ATCH 1 - SPECIFICATIONS - Addition to CDC West Bldg 90306.pdf PDF
ATCH L2 - Financial Questionnaire.docx DOCX document
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

7. ISSUED BY CODE 8. ADDRESS OFFER TO

9. FOR INFORMATION

CALL:

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See ).

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and copies to perform the work required are due at the place specified in Item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

b. An offer guarantee is, is not required.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

STANDARD FORM 1442 (REV. 8/2014)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

12b. CALENDAR DAYS

YES NO

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED PAGE OF PAGES

AMOUNTS

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA

BY

31c. DATE

STANDARD FORM 1442 (REV. 8/2014) BACK

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

Section A - Solicitation/Contract Form

Addition to CDC West Bldg. 90306

Project Number: CP1024656 Date: 05 Oct 2023

FA441723R00090003

Section B - Supplies or Services & Prices or Costs

Additional Information/Notes

Item Supplies/Service Quantity Unit Unit Price Amount

The contractor shall provide all materials, labor, tools, supervision and equipment to perform all operations necessary to accomplish all work in accordance with the Project CP 1024656, Project Title Construct Addition to Child Development Center (CDC) West, Building 90306 in accordance with the project drawings dated 09/04 /2020 and project specifications dated 4 September 2020.

Pricing Arrangement: Firm Fixed Price

Product Service Code: Z2AZ Claimant Program Code: C2 Pricing Arrangement: Firm Fixed Price

1 Job

000101 FUNDING FOR CLIN 0001

Purchase Request Number: HURLF30033D

Section C - Description/Specifications/Statement of Work

Requirements The contractor shall provide all materials, labor, tools, supervision and equipment to perform all operations necessary to accomplish all work in accordance with Project CP 1024656, Addition to CDC West Building 90306.

This contract will be a firm-fixed price (FFP) contract to include the work of approximately 3850 SF addition to existing Child Development Center. The addition includes 3 infant activity rooms, corridor and facility support spaces. An outdoor play area of approximately 1250 SF is immediately adjacent this addition. Work includes minor demolition at existing facility to tie in the new addition as well as sitework, utilities, finishes and casework. Existing building HVAC, electrical, communications, plumbing and fire protection systems will be modified to support the addition. This is a construction contract that is funded by Non-Appropriated Funds (NAF) and will adhere to NAF guidance, regulations and clauses. FAR, DFARS and AFFARS regulations and clauses are not applicable.

The period of performance is 330 calendar days. The contractor shall perform all work as specified in the project specifications and drawings.

NOTE: This is a nonappropriated fund purchase and it does not obligate appropriated funds of the United States Government. Nonappropriated funds are generated by the military community through the sale of goods and services and the collection of fees and charges for participation in military community programs. This purchase does not involve federal tax dollars.

Section D - Packaging and Marking

Section E - Inspection and Acceptance

The NAFI inspector, 1 SOCES/CENM provides all Inspection and Acceptance for this construction project.

Overall Contract Inspection/Acceptance Locations

Inspection and Acceptance Location

Both Destination Instructions: See specifications and drawings for the construction contract inspection requirements.

DoDAAC: F2F323 CountryCode: USA

1 SOCES CEOE

AF BPN NO MILSBILLS PROCESSES, 415 INDEPENDENCE RD

HURLBURT FIELD, FL 32544-5267

UNITED STATES

Gary Billow Email: gary.billow.1@us.af.mil Telephone: 850-884-1790

Section F - Deliveries or Performance

The delivery schedule will be provided at the contract award. The total period of performance for this project is 330 calendar days.

Overall Contract Delivery Period

From date of lead time event to beginning of performance 10 Calendar Days Date of Notice to Proceed Receipt

From date of lead time event to completion of performance 330 Calendar Days Date of Notice to Proceed Receipt

Line Item Delivery Schedule Quantity Address and POC

Delivery Schedule From date of lead time event to completion of performance 330 Calendar Days Date of Notice to Proceed Receipt

1 Job Place of Performance DoDAAC: F2F323 CountryCode: USA

1 SOCES CEOE

AF BPN NO MILSBILLS PROCESSES, 415

INDEPENDENCE RD

HURLBURT FIELD, FL 32544-5267

UNITED STATES

Gary Billow Email: gary.billow.1@us.af.mil Telephone: 850-884-1790

Section G - Contract Administration Data

A. Following award, this contract will be administered by the 1 SOCONS/PKB, Contracting Office. The name, address, telephone number, and fax number of the Contracting Officer (CO) and Administrator are as follows:

CO: Tina Kneip

1 SOCONS/PKB

350 Tully Street Building 90339 Hurlburt Field, FL 32544 Phone: 850-884-4941

E-mail: tina.kneip.1@us.af.mil

Contract Admin: Chris Young Phone: 850-884-3298 E-mail: christine.young.1@us.af.mil

B. The Contracting Officer, is the only person authorized to approve changes or modify any of the requirements under this contract and notwithstanding any provisions contained elsewhere in this contract, the said authority remains solely in the CO. In the event the Contractor effects any such change at the direction of any person other than the CO, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in costs incurred as a result thereof.

CONTRACTOR AUTHORIZED INDIVIDUALS

To be completed by the Contractor:

The below individuals are authorized to negotiate or discuss this proposal:

Name of Primary: _____________________________________________________________________________________________________

Address: ______________________________________________________________________________________________________________

Telephone: __________________________________________________________________________________

Alternate Phone: ____________________________________________________________________________

Email: _______________________________________________________________________________________

To be completed by the Contractor:

Name of Alternate:

Address:

Telephone: __________________________________________________________________________________

Alternate Phone: ____________________________________________________________________________

Email: _________________________________________________________________________________________________

Section H - Special Contract Requirements

SUBMISSION OF QUESTIONS: this solicitation must be submitted in writing via email to the two individuals listedQuestions regarding above in Section G .no later than close of business , 6 business days after the date of the site visit3 November 2023 at 4:00 p.m., CST

SUBMISSION OF PROPOSALS: Offeror is responsible for submitting their proposal so as to reach the NAFI Contracting office designated in the solicitation by the date/time specified. Personnel requiring access to Hurlburt Field for the purpose of delivering a proposal or attending the site visit must email a written request containing the company name and the full name (First, Middle, Last) of person(s) requiring access to the Contract Specialist, Christine Young(christine.young.1@us. af.mil), and the Contracting Officer, Tina Kneip (tina.kneip.1@us.af.mil). Hurlburt Field base access requests must be received NLT 72 hours prior to the date and time established for receipt of proposals . All individuals will enter through the Commercial gate, (CVI gate) located on Downs Rd, Hurlburt Field and the CVI gate entrance/exit is located off of Martin Luther King Jr Blvd. Please allow extra time to obtain your temporary base pass at the Commercial gate.

VALID ID: For either the site visit or submission of proposals, all personnel requesting access to Hurlburt Field must possess a valid State or Government picture identification card. Furthermore, individuals presenting identification cards from a state that is non-compliant with the REAL ID Act will require additional documentation to gain base access. Additional documentation includes a valid U.S. or foreign government issued passport, an employment authorization document that contains a photograph, or identification cards issued by federal state or local government agencies that include a photo and biographic information. A full list of REAL ID Act compliant and non-complaint states can be found at https://www.dhs.gov/real-

id. Personnel requesting vehicle access to Hurlburt Field must provide a valid driver's license, current vehicle registration, and valid vehicle insurance.

SITE PROTECTION DURING HURRICANE SEASON

Normally, the period from 1 June through 30 November is the premier season for Hurricanes, Tropical Storms and Tropical Depressions for Hurlburt Field, FL and surrounding areas. In the event of a hurricane and at the direction of the Contracting Officer, the Contractor shall be responsible for:

a) Securing all equipment, materials and cleaning up the work area;

b) Continuing normal operations until directed otherwise by the Contracting Officer;

c) Evacuating the base as directed by the Contracting Officer;

d) Provide a POC to the Contracting Officer to recall the contractor after the danger is over;

e) Be prepared to resume normal operations when notified by the Contracting Officer. The work site should be free of objects capable of becoming airborne and causing a hazard. For service contracts, damages occurring as a result of contractor debris are the responsibility of the contractor and will be handled in accordance with FAR 52.237-2, this clause and other requirements of this contract. For construction contracts, per FAR clauses 52.236- 9 and 52.236-12, you are required to maintain your work area free of debris and in a safe and secure condition at the completion of each workday with particular care during the hurricane season.

SPECIAL CLAUSES FOR CONSTRUCTION

NFC-203-14 - DISPLAY OF HOTLINE POSTER(S) (JUN 2020)

(a) Definition.

"United States," as used in this clause, means the 50 States, the District of Columbia, and outlying areas.

(b) . Except as provided in paragraph (c)Display of fraud hotline poster(s)

(1) During contract performance in the United States, the Contractor shall prominently display in common work areas within business segments performing work under this contract and at contract work sites.

(i) Any agency fraud hotline poster or Department of Homeland Security (DHS) fraud hotline poster identified in paragraph (b)(3) of this clause; and

(ii) Any DHS fraud hotline poster subsequently identified by the Contracting Officer.

(2) Additionally, if the Contractor maintains a company website as a method of providing information to employees, the Contractor shall display an electronic version of the poster(s) at the website.

(3) Any required posters may be obtained as follows:

Poster(s) Obtain from

Defense Hotline Posters http://www.dodhotline.dodig.mil/Hotline/posters.cfm

(c) If the Contractor has implemented a business ethics and conduct awareness program, including a reporting mechanism, such as a hotline poster, then the Contractor need not display any agency fraud hotline posters as required in paragraph (b) of this clause, other than any required DHS posters.

(d) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph(d), in all subcontracts that exceed $5.5 million, except when the subcontract

(1) Is for the acquisition of a commercial item; or

(2) Is performed entirely outside the United States.

(End of clause)

NFC-222-36 - EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020)

the requirements of the equal opportunity clause at 41 CFR 60-(a) Equal opportunity clause. The Contractor shall abide by

741.5(a),as of March 24, 2014. This clause prohibits discrimination against qualified individuals on the basis of disability, and requires affirmative action by the Contractor to employ and advance in employment qualified individuals with disabilities.

(c) Subcontracts. The Contractor shall include the terms of this clause in every subcontract or purchase order in excess of the threshold specified in Federal Acquisition Regulation (FAR) 22.1408(a) on the date of subcontract award, unless exempted by rules, regulations, or orders of the Secretary, so that such provisions will be binding upon each subcontractor or vendor. The Contractor shall act as specified by the Director, Office of Federal Contract Compliance Programs of the U.S. Department of Labor, to enforce the terms, including action for noncompliance. Such necessary changes in language may be made as shall be appropriate to identify properly the parties and their undertakings.

(End of clause)

NFC-225-9 - BUY AMERICAN-CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. As used in this clause--"Commercially available off-the-shelf (COTS)item"

(1) Means any item of supply (including construction material) that is

(i) A commercial item;

(ii) Sold insubstantial quantities in the commercial marketplace; and

(ii) Offered to the NAFI, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Component" means an article, material, or supply incorporated directly into a construction material.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting ,fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the NAFI are supplies, not construction material.

"Cost of components" means

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty(whether or not a duty-free entry certificate is issued); or

For components manufactured by the Contractor, all costs associated with the manufacture of the component, including(2) transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

"Domestic construction material" means

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which non availability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.

"Foreign construction material" means a construction material other than a domestic construction material.

"United States" means the 50States, the District of Columbia, and outlying areas.

(a) Domestic preference.

(1) This clause implements the 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the NAFI as follows:

NONE ______________________________________[Contracting Officer to list applicable excepted materials or indicate "none"]

(2) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the NAFI determines that

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(b) Request for determination of inapplicability of the Buy American statute.

(1)

Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for NAFI evaluation of the request, including

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) the market and A request based on unreasonable cost shall include a reasonable survey of a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction issued).site and any applicable duty (whether or not a duty-free certificate may be

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the NAFI determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the NAFI determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(a) Data. To permit evaluation of requests under paragraph (c)of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

Foreign and Domestic Construction Materials Price Comparison

Construction material description Unit of measure Quantity Price (dollars) *

Item 1

Foreign construction material

Domestic construction material

Item 2

Foreign construction material

Domestic construction material

[List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.]

[ ]Include other applicable supporting information.

[*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]

NFC-252-2 - CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Full text is available online at: https://www.afnafpo.afsv.net/pages/Construction-Support/Construction-Support.aspx (NAF Contracting).

CLAUSES INCORPORATED BY REFERENCE

NFC-202-1 Definitions

NFC-203-2 Certificate of Independent Price Determination

NFC-203-3 Gratuities

NFC-203-5 Covenant Against Contingent Fees

NFC-203-7 Anti-Kickback Procedures

NFC-203-8 Cancellation, Recession, and Recovery of Funds for Illegal or Improper Activity

NFC-203-

Price or Fee Adjustment for Illegal or Improper Activity

NFC-203-

Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions

NFC-203-

Limitation on Payments to Influence Certain Federal Transactions

NFC-203-

Contractor Code of Business Ethics and Conduct

NFC-203-

Contractor Employee Whistleblower Rights and Requirement to Inform appraisals

NFC-204-3 Taxpayer Identification

NFC-204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper

NFC-204-9 Personal Identity Verification of Contractor Personnel

NFC-204-

Data Universal Numbering System Number Maintenance

NFC-204-

Incorporation by Reference of Representations and Certifications

NFC-209-2 Prohibition on Contracting with Inverted Domestic Corporations - Representation.

NFC-209-5 Certification Regarding Responsibility Matters

NFC-209-6

Protecting the NAFI's Interest When Subcontracting with Contractor's Debarred, Suspended, or Proposed for Debarment

NFC-209-9 Updates of Publicly Available Information Regarding Responsibility Matters

NFC-210-1 Market Research

NFC-211-

Commencement, Prosecution, and Completion of Work

NFC-211-

Time Extensions

NFC-215-2 Audit and Records--Negotiations

NFC-215-6 Place of Performance

NFC-215-8 Order of Precedence--Uniform Contract Format

NFC-222-1 Notice to the NAFI of Labor Disputes

NFC-222-4 Contract Work Hours and Safety Standards-Overtime Compensation

NFC-222-5 Employment Eligibility Verification.

NFC-222-6 Construction Wage Rate Requirements.

NFC-222-7 Withholding of Funds.

NFC-222-8 Payrolls and Basic Records

NFC-222-9 Apprentices and Trainees.

NFC-222-

Compliance with Copeland Act Requirements.

NFC-222-

Subcontracts (Labor Standards)

NFC-222-

Contract Termination- Debarment.

NFC-222-

Compliance with Construction Wage Rate Requirements and Related Regulations

NFC-222-

Disputes Concerning Labor Standards.

NFC-222-

Certification Regarding Knowledge of Child Labor for Listed End Products

NFC-222-

Previous Contracts and Compliance Reports

NFC-222-

Affirmative Action Compliance

NFC-222-

Affirmative Action Compliance Requirements for Construction.

NFC-222-

Employment Reports on Veterans.

NFC-222-

Compliance with Veterans' Employment Reporting Requirements

NFC-222-

Notification of Employee Rights Under the National Labor Relations Act.

NFC-223-1 Biobased Product Certification

Affirmative Procurement of Biobased Products Under Service and Construction

NFC-223-2

Contracts.

NFC-223-3 Hazardous Material Identification and Material Safety Data.

NFC-223-4 Recovered Material Certification

NFC-223-6 Drug-Free Workplace.

NFC-223-9 Estimate of Percentage of Recovered Material Content for EPA - Designated Items.

NFC-223-

Waste Reduction Program.

NFC-223-

Energy Efficiency in Energy-Consuming Products.

NFC-223-

Affirmative Procurement of EPA-designated Items in Service and Construction

Contracts.

NFC-223-

Encouraging Contractor Policies to Ban Text Messaging While Driving

NFC-224-1 Privacy Act Notification.

NFC-224-2 Privacy Act.

NFC-225-2 Buy American Act Certificate

NFC-225-4 Buy American Act--Free Trade Agreements--Israeli Trade Act Certificate

NFC-225-6 Trade Agreements Certificate

NFC-225-

Restrictions on Certain Foreign Purchases

NFC-227-1 Authorization and Consent.

NFC-227-2 Notice and Assistance Regarding Patent and Copyright Infringement.

NFC-227-4 Patent Indemnity- Construction Contracts.

NFC-227-6 Royalty Information

NFC-227-

Representation of Limited Rights Data and Restricted Computer Software

NFC-228-2 Additional Bond Security.

NFC-228-

Pledges of Assets

NFC-228-

Prospective Subcontractor Requests for Bonds.

NFC-228-

Irrevocable Letter of Credit.

NFC-228-

Performance and Payment Bonds- Construction.

NFC-229-3 Federal, State, and Local Taxes.

NFC-232-5 Payments under Fixed-Price Construction Contracts.

NFC-232-

Interest.

NFC-232-

Prompt Payment for Construction Contracts.

NFC-232-

Payment by Electronic Funds Transfer - Other than System for Award Management

NFC-232-

Unenforceability of Unauthorized Obligations.

NFC-233-3 Protest after Award.

NFC-233-4 Applicable Law for Breach of Contract Claim

NFC-236-2 Differing Site Conditions

NFC-236-3 Site Investigation and Conditions Affecting the Work.

NFC-236-5 Material and Workmanship.

NFC-236-6 Superintendence by the Contractor

NFC-236-7 Permits and Responsibilities.

NFC-236-8 Other Contracts.

NFC-236-9

Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements.

NFC-236-

Operations and Storage Areas.

NFC-236-

Use & Possession Prior to Completion.

NFC-236-

Cleaning Up.

NFC-236-

Accident Prevention.

NFC-236-

Availability and Use of Utility Services.

NFC-236-

Schedules for Construction Contracts.

NFC-236-

Layout of Work.

NFC-236-

Specifications and Drawings for Construction.

NFC-236-

Preconstruction Conference.

NFC-242-

Bankruptcy

NFC-242-

Suspension of Work

NFC-244-6 Subcontracts for Commercial Items

NFC-245-1 NAFI Property

NFC-246-

Warranty of Construction

NFC-248-1 Value Engineering--Construction

NFC-249-

Default (Fixed-Price Construction)

Section I - Contract Clauses

NONAPPROPRIATED FUND STANDARD CLAUSES

l. DEFINITIONS

As used throughout this contract, the following terms and abbreviations have the meanings set forth below:

a. Contract. An agreement that creates a legal obligation. The elements of a contract are a mutual agreement; between competent parties; for a legal purpose; involving the exchange of legal consideration; and that creates a mutuality of obligation to perform between the parties. The term contract, as used herein, includes without limitation, formal bilateral contracts, purchase orders, consignment sales agreements, amendments and modifications thereto, as well as other agreements entered into by an authorized Contracting Officer acting within his or her authority.

b. Contracting Officer. An individual delegated the authority to legally bind the NAFI by entering into, modifying, administering, and terminating contracts.

c. Contractor. Any legal entity that is awarded a contract. The Contractor is the party responsible for and agrees to furnish supplies and/or services at specified prices/rates and/or to pay the NAFI mutually agreed to commissions and/or fees in conjunction with providing services to NAFI customers under this contract. Contractor may include, but is not limited to the following terms "vendor," "seller," "supplier," "manufacturer," "distributor," "concessionaire" and/or "licensee."

d. Contracting Officer's Representative (COR). An individual authorized in writing by a Contracting Officer to monitor Contractor performance and /or help administer a contract, but does not have authority to legally bind the NAFI into any contractual or legal obligations. Definition applies to Contracting Officer's Technical Representative (COTR) and Alternate COR (ACOR).

e. Day. A day means, unless otherwise provided, a 24 hour period of time denoted as midnight to midnight of a calendar day, unless the last day of a specified number of days within which the contractor must file a claim or notice with the Contracting Officer falls on Saturday, Sunday or a federal holiday, in which case the last day shall be the next business day denoted as Monday through Friday.

f. Nonappropriated Fund Instrumentality (NAFI). A DoD organizational and fiscal entity supported in whole or in part by Nonappropriated Funds. A NAFI, as an instrumentality of the U.S. Government, enjoys the same immunities and privileges as the U.S. Government in the absence of specific Federal statute. It is not incorporated under the law of any State, but has the legal status of an instrumentality of the United States. References to United States, the Government, and other related references will generally be implied to mean the NAFI throughout this contract.

2. LEGAL STATUS

The Nonappropriated Fund Instrumentality (NAFI), which is party to this contract, is an integral part of the Department of Defense and is an instrumentality of the United States Government. No appropriated funds of the United States shall become due or be paid the Contractor by reason of this contract.

3. CLAIMS, PROTESTS & APPEALS

a. This contract is not subject to the Contract Disputes Act of 1978 (41 U.S.C. 7101-7109), and therefore, not subject to the jurisdiction of the Government Accountability Office (GAO). All disputes arising under or relating to this contract shall be resolved under this clause IAW DoDI

4105.67 and AFMAN 64-302.

b. Protests and/or protest appeals shall be filed with the Contracting Officer that issued the contract, or other designated authority, in strict accordance with the procedures and timelines in AFMAN 64-302.

c. "Claims," as used in this clause, means the inability of a Contractor and the Contracting Officer to reach a mutual agreement related to contractual issues in controversy resulting in the filing of a written demand or assertion seeking payment of money, adjustment or interpretation of contract, or other relief, and issuance of a Contracting Officer's final decision. A voucher, invoice, or other routine request for payment that is not in dispute when submitted is not a claim under this clause. The submission may be converted to a claim under this clause, by complying with the submission requirements of this clause. If it is disputed either as to liability or amount or is not acted upon in a reasonable time.

(1) A claim by the Contractor shall be made in writing and submitted to the Contracting Officer for a written decision. A claim by the NAFI against the Contractor shall be subject to a written decision by the Contracting Officer.

(2) For Contractor claims exceeding $100,000, the Contractor shall submit with the claim a certification that contains the following statement:

"Subject to the False Claims Act, 31 USC 3729, I certify the claim is made in good faith; that the supporting data is accurate and complete to the best of my knowledge and belief; that the amount requested accurately reflects the contract adjustment for which the Contractor believes the NAFI is liable; and that I am duly authorized to certify on behalf of the Contractor."

(3) For contract claims of less than $100,000, the Contracting Officer must, if requested in writing by the Contractor, render a decision within 60 days of the request. For Contractor-certified claims over $100,000, the Contracting Officer must, within 60 days, decide the claim or notify the Contractor of the date by which the decision will be made.

d. The Contracting Officer's decision shall be final unless the contractor appeals as provided in paragraph (d) of this clause.

e. The Contracting Officer's final decision on claims may be appealed by submitting a written appeal to Armed Services Board of Contract Appeals with a copy to the Contracting Officer, within 90 days of receipt of the Contracting Officer's final decision. Decisions of the Armed Services Board of Contract Appeals are final and are not subject to further appeal.

f. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any request for relief, claim, appeal, or action arising under the contract, and comply with any decision of the Contracting Officer.

4. REPRESENTATIONS

a. This written contract, including identified attachments, enclosures and documents incorporated by reference, is the entire agreement between the parties. The NAFI will not be bound by any oral or written representation not included or incorporated in the written contract or a written modification thereto. The NAFI will not be bound by any terms on Contractor forms or letters unless such terms are specifically agreed to and incorporated in the contract and signed by the Contracting Officer. Except as otherwise specifically provided in this contract, all additions, changes or deletions to this contract must be prepared in writing as a modification and signed either unilaterally by the Contracting Officer or bilaterally by both parties in accordance with applicable regulations.

b. The Contractor shall not represent itself to be an agent or representative of the NAFI or any other agency or instrumentality of the United States.

5. ADVERTISEMENTS

The Contractor shall not represent in any manner, expressly or by implication, that items or services purchased or sold under this contract are approved or endorsed by any element of the U.S. Government, including the NAFI. All Contractor advertisements that refer to the NAFI or a NAFI activity will contain a statement that the advertisement was neither paid for nor sponsored, in whole or in part, by the U.S. Government or the NAFI.

6. EXAMINATION OF RECORDS

a. The Contractor agrees that the Contracting Officer or a duly authorized representative(s) shall have the right to examine and audit the books and records of the Contractor directly pertaining to the contract during the period of the contract and until expiration of three (3) years after the final payment under the contract.

b. The Contractor shall include this clause in all subcontracts.

7. HOLD AND SAVE HARMLESS

The Contractor agrees to indemnify and hold harmless the NAFI and any other agency or instrumentality of the United States, and their officers, agents, and employees, from any loss, expense, damage, injury, claim, suit or judgment (including administrative actions taken against the NAFI by other federal, state or local agencies) arising from the Contractor's (employees, agents or subcontractors) acts or omissions or the items/services provided pursuant to the contract (including any patent, copyright, or trademark infringement claimed by a third party in connection with the items /services provided by the contractor). Nothing contained herein, however, shall relieve or be construed as relieving the NAFI or any other agency or instrumentality of the United States from any liability resulting from its negligence.

8. INSURANCE

a. The Contractor shall, at its own expense, provide and maintain during the entire performance period of this contract at least the insurance coverage as stated in this contract. In no event shall the coverage be less than the minimum requirements established by applicable state and local regulations and laws for the risk associated with the services to be provided by the contract. The Contractor shall be fully responsible to the NAFI for errors and omissions of its associates and subcontractors under this contract.

b. The Contractor shall furnish to the Contracting Officer a current certificate of insurance prior to the commencement of performance under the contract. The "INSURED" block of the Certificate of Insurance must list both the Contractor's name (or Contractor's d.b.a. name) / and the contract number. The Certificates of Insurance shall evidence that all lines of insurance coverage required by the contract are in effect, and that not less than thirty (30) days prior written notice shall be provided to the Contracting Officer in the event of modification, cancellation, or non-renewal of any portion of the insurance coverage(s). All certificates of insurance must list the NAFI as the certificate holder, name the NAFI and the United States as additional insureds, and carry an endorsement waiving the Contractor's rights to subrogation against the NAFI and the United States.

9. PROCUREMENT INTEGRITY

By submission of an offer or performance of this contract, the offeror or Contractor certifies with respect to this NAFI contract action:

a. That no discussion, offer, or promise of future employment or business opportunity has nor will be made to NAFI civilian or military personnel who personally and substantially participated in the contract action.

(1) That no offer, promise, or gift of any gratuity, entertainment, money, or other thing of value has nor will be made to any NAFI civilian or military personnel or any other employee of the NAFI or member of their family or household.

(2) That no information proprietary to other offerors or other contracting information (offeror list, prices offered, technical evaluations, rankings, etc.)

is sought or obtained until it is available to the public under NAFI procedures.

(3) That no person or selling agency has been employed or retained to secure this contract for a commission, percentage, brokerage, or contingent fee except bona fide employees or bona fide established commercial selling agencies retained by the Contractor for the purpose of securing business.

b. The Contractor certifies that no gratuities (entertainment, gifts, money, kickbacks, or other things of value) were nor will be solicited or accepted by the Contractor or Contractor representative, nor from any Subcontractor or Subcontractor representative, for the purpose of obtaining or rewarding favorable treatment in connection with this contract or any subcontract under it.

c. The Contractor will report in writing to the Contracting Officer any possible violation of this clause when there are reasonable grounds to believe a violation may have occurred. The Contractor will cooperate fully with any federal agency investigation of a possible violation of this clause.

d. For breach of any of these certifications, the NAFI may terminate this contract for default, and/or deduct from amounts due under this or other contracts, or charge the Contractor for the total value of any contingent fee, gratuity, kickback or other loss to the NAFI arising out of the breach.

10. ASSIGNMENT OF CLAIMS

The Contractor cannot assign any right or delegate any obligations under this contract without the prior written permission of the Contracting Officer.

11. TERMINATION FOR CONVENIENCE

The Contracting Officer, by written notice, may terminate this contract, in whole or in part, when it is in the best interest of the NAFI. If this contract is for supplies and is so terminated, the Contractor shall be compensated in accordance with FAR, Sub Parts 49.1 and 49.2 in effect on this contract's date. To the extent that this contract is for services and is so terminated, the NAFI shall be liable only for payment in accordance with the payment clauses of this contract for services rendered prior to the effective date of termination, providing there are no Contractor claims covering nonrecurring costs for capital investment. If there are any such Contractor claims, they shall be settled in accordance with FAR, Sub Parts 49.1 and 49.2.

12. CANCELLATION BY MUTUAL AGREEMENT

Should the situation warrant, the parties upon mutual agreement and no costs, may cancel this contract without further recourse to the other and mutual release of any further obligations.

13. TERMINATION FOR CAUSE

a. The NAFI may, subject to paragraphs c. and d. below, by written notice of cause to the Contractor, terminate this contract in whole or in part if the Contractor fails to-

(1) Deliver the supplies or perform the service within the time specified within this contract or any extension;

(2) Make progress, so as to endanger performance of this contract (however, see paragraph b. below); or

(3) Perform any of the other clauses of this contract (however see paragraph b. below).

b. The NAFI's right to terminate this contract under paragraph a.2., and a.3. above, may be exercised if the Contractor does not cure such failure within 10 days (or more if authorized in writing by the Contracting Officer) after receipt of notice from the Contracting Officer specifying the failure.

c. If the NAFI terminates this contract in whole or in part, it may acquire, under the terms and in the manner the Contracting Officer considers appropriate, supplies or services similar to those terminated, and the Contractor will remain liable to the NAFI for any excess costs for those supplies or services. However the Contractor must continue the work not terminated.

d. Defaults by subcontractors at any tier for any reason do not constitute causes beyond the control and without the fault or negligence of the Contractor. The Contractor shall not be liable for any excess costs if the failure to perform the contract arises from causes beyond the control and without the fault or negligence of the Contractor. Examples of such causes include:

(1) Acts of God or of the public enemy

(2) Act of the NAFI in either its sovereign or contractual capacity

(3) Fires

(4) Floods

(5) Epidemics

(6) Quarantine restrictions

(7) Strikes

(8) Freight embargoes

(9) Unusually severe weather

e. If this contract is terminated for cause, the NAFI may require the Contractor to transfer title and deliver to the NAFI as directed by the Contracting Officer, any

(1) completed supplies, and

(2) partially completed supplies and materials, parts, tool dies, jigs, fixtures, plans, drawings, information, and contract rights (collectively referred to as manufacturing materials in the clause) that the Contractor has specifically produced or acquired for the terminated portion of this contract. Upon direction of the Contracting Officer, the Contractor shall also protect and preserve property in its possession in which the NAFI has an interest.

f. The NAFI shall pay the contract price for completed supplies delivered and accepted. The Contractor and Contracting Officer shall agree on the amount of payment for manufacturing materials delivered and accepted and for the protection and preservation of the property. Failure to agree will be a dispute under the Claims Clause. The NAFI may withhold from these amounts any sum the Contracting Officer determines to be necessary to protect the NAFI against loss because of outstanding liens or claims of former lien holders.

g. If, after termination, it is determined that the cause by the Contractor was excusable, the rights and obligations of the parties shall be the same as if the termination had been issued for convenience of the NAFI.

h. The rights and remedies of the NAFI in this clause are in addition to any other rights and remedies provided by law or under this contract.

i. This contract is automatically terminated for the convenience of the NAFI in the event the NAFI is dissolved.

14. CHANGES

a. The Contracting Officer may at any time, by written order, and without notice to the sureties, if any, make changes within the general scope of this contract in any one or more of the following:

(1) If the requirement is for supplies and/or services: Drawings, designs, or specifications; method of shipment or packing; description of services to be performed; time of performance (i.e., hours of the day, days of the week, etc.); place of delivery or place of performance of services.

(2) If the requirement is for concession services (including public private ventures): Specifications (including drawings and designs); method or manner of performance of work; NAFI-furnished facilities, equipment, materials, services, or site; and/or directing acceleration in the performance of work.

(3) If the requirement is for transportation services: Specifications; work or services; place of origin; place of delivery; tonnage to be shipped; and/or amount of NAFI-furnished property.

b. If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of the work under this contract, whether or not changed by the order, the Contracting Officer will make an equitable adjustment in the contract price, the delivery schedule, or both, and modify the contract.

c. The Contractor must assert its right to an adjustment under this clause within 30 days from the date of receipt of the written order; however, if the Contracting Officer decides that the facts justify it, the Contracting Officer may receive and act upon a proposal submitted before final payment of the contract.

d. If the Contractor's proposal includes the cost of property made obsolete or excess by the change, the Contracting Officer shall have the right to prescribe the manner of the disposition of the property.

e. If the requirement is for architect-engineer or other professional services, no services for which an additional cost or fee will be charged by the Contractor shall be furnished without the prior written authorization of the Contracting Officer.

f. If the requirement is for concession services (including public private ventures), the Contractor shall notify the Contracting Officer in writing within seven (7) days of the occurrence of any event that the Contractor considers a change to the contract that has not been authorized in writing signed by the Contracting Officer. The Contractor will be deemed to have waived any right to an adjustment if timely notice is not provided to the Contracting Officer as required herein. For purposes of this clause, "event" shall include, but not be limited to, an order or direction by a NAFI or other NAFI official, a contested contract interpretation, interference with or interruption of the contract work, or any other event that increases the cost or time to perform the contract as compared to the cost or time that would be required if the Contractor performed the contract in accordance with its terms.

g. Failure to agree to any adjustment shall be a "claim" under the "Claims" clause of this Contract; however, nothing in this clause shall excuse the Contractor from proceeding with the Contract as changed.

15. SOCIAL RESPONSIBILITY AND LABOR STANDARDS NONRESALE

By performance of this contract, the Contractor and any subcontractors shall comply with the Social Responsibility requirements addressed herein:

a. Combating Trafficking in Persons (CTIP). Applicable to all contracts, regardless of location performed.

(1) Definitions. The meanings of the terms coercion, commercial sex act, debt bondage, forced labor, involuntary servitude, severe forms of trafficking in persons, and sex trafficking are as is defined in the Trafficking Victims Protection Act of 2000, Public Law 106-386, October 28, 2000 < http://www.state.gov/documents/organization/10492.pdf >.

(2) Policy. DoD NAFIs have adopted the U.S. Government's zero tolerance policy regarding trafficking in persons.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .