Attach_12-SEED_Project,_Working_Time_Analysis,_Replace_Roofs_on_Bldg_90705_(Revised)_30_Oct_18.pdf

PDF 102 KB Posted

Attached to
Roofing IDIQ Federal contract opportunity
Solicitation number
FA441718R0012
Issued by
Department of the Air Force Special Operations Command

About this file

Attach 12-SEED Project, Working Time Analysis, Replace Roofs on Bldg 90705 (Revised) 30 Oct 18

View the file

Other files for this federal contract opportunity

Other files attached to Roofing IDIQ, newest first.
File Type Posted
Additional_Questions_and_Answers_-_FA441718R0012.pdf PDF
FA441718R00120005.pdf PDF
FA441718R00120005.pdf PDF
Questions_and_Answers_-_FA441718R0012.pdf PDF
FA441718R00120004.pdf PDF
Attach_11-SEED_Project,_Statement_of_Work,_Replace_Roofs_30_Oct_18.pdf PDF
FA441718F00120003.pdf PDF
MFR-FA441718R0012-Site_Visit_Brief_and_Sign_In.pdf PDF
FA441718R0012-0002.pdf PDF
FA441718R00120001.pdf PDF
Attach_3-Wage_Determination_FL180262.pdf PDF
Attach_6_Financial_Institution_Reference_Sheet.pdf PDF
Attach_11_Seed_Project_SOW_Replace_Roofs_on_Bldg_90705_-_17_Jun_18.pdf PDF
Attach_14_Seed_Project_Material_Submittal_Form.xls XLS spreadsheet
Attach_10_Material_Submittal_Form.xls XLS spreadsheet
Attach_1_Contract_Line_Item_Listing_-_Bid_Schedule.xlsx XLSX spreadsheet
Attach_7_Sample_Project_SOW.pdf PDF
Attach_13_Seed_Project_Drawing.pdf PDF
Attach_5_Past_Performance_Questionnaire.pdf PDF
FA441718R0012.pdf PDF
Attach_3_Wage_Determination_Decision_No_FL20170262.pdf PDF
Attach_2-Roofing_IDIQ_Specs_12_July_2018.pdf PDF
Attach_8_Sample_Project_Drawing.pdf PDF
Attach_9_Sample_Project_WTA.pdf PDF
Attach_12_Seed_project_WTA__Bldg_90705.pdf PDF
Attach_4_Additional_Contractor_Information.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WORKING TIME ANALYSIS

PROJECT: CP# Bldg. 90705

ITEM NO: DESCRIPTION ALLOWABLE CALENDAR DAYS

1. Mobilization 1

2. Make Req'd Submittals 10

3. Secure AF 103 Permit Material/Equipment 10

4. Perform All Work 11

5. Correct Punch List item’s 3

6. Obtain Other Permits 0

TOTAL ALLOWABLE CONTRACT TIME 35