Questions_from_Site_Visit.docx

DOCX document 12 KB Posted

Attached to
Bullet Trap Maintenance, Repairs, and Lead Removal
Solicitation number
FA441718Q0180
Issued by

About this file

Questions from site visit.

View the file

Other files

File Type Posted
Attch_5_Addendum_to_52212-2_U0001.pdf PDF
Q_A.pdf PDF
Attch_4_Addendum_to_52212-1_U0001.pdf PDF
FA441718Q0180U0001.pdf PDF
Bullet_Trap_Pictures.pdf PDF
Attch_3_Cover_Sheet.pdf PDF
Attch_4_Addendum_to_52212-1.pdf PDF
Bullet_Trap_RFQ.pdf PDF
Attch_5_Addendum_52212-2.pdf PDF
Attch_1_Bullet_Trap_SOW.pdf PDF
Attch_2_WD_15-4531_Rev-8.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A site visit was held on August 27th at 0800 Central Time. One interested party attended and the following questions were asked.

Q: Based on information gathered at the site, is it possible to exclude the painting portion of the SOW from the contract?

A: The paint requirement will Not be removed from the SOW. The paint portion is minimal, is basic touch up as stated in paragraph 1.1.6 below. Paragraph 4.3 refers to the storage and disposal of the paint and paint removal chemicals.

1.1.6. The contractor shall perform minor corrosion control on the 35 position firing range during monthly inspections. Corrosion control shall be limited to top plate priming and touch-up paint where rust is present and lane number painting if numbering is illegible.

4.3. Corrosion Control/Paint Waste. The contractor shall set up and manage a hazardous waste accumulation point for waste paint, waste solvent and paint stripping residuals unless the waste can be turned in to hazardous waste storage facility on the same day it is generated.
When paint stripping is necessary - all chips, dust and other contaminants must be collected in a manner that prevents a release to the ground, air and water.