AMD0004 - RFI - FY24 MACC Recompete (RESPONSE 3 OCT 23).pdf

PDF 217 KB Posted

Attached to
FY 24 Multiple Award Construction Contract (MACC) Recompete
Solicitation number
FA440723R0002
Issued by

About this file

This document contains 16 questions and answers related to a sample project for the FY 24 Multiple Award Construction Contract (MACC) Recompete solicitation from the Department of the Air Force Air Mobility Command. The sample project involves renovations and repairs to Building 21 of the Red Cross facility, including masonry repairs, foundation work, electrical and plumbing demolition, and structural repairs. Questions from potential offerors seek clarification on the scope of demolition, treatment of exposed foundations, and percentage of masonry tuck-pointing to include in proposals. The government provides concise responses to clarify project requirements and scope.

View the file

Other files

File Type Posted
AMD0005 - RFI - FY24 MACC Recompete (RESPONSE 5 OCT 23).pdf PDF
AMD0005 - Amendment FA440723R00020005 SF 30.pdf PDF
AMD0004 - Solicitation Amendment FA440723R0002.pdf PDF
AMD 0003 - Solicitation Amendment FA440723R00020003 SF 30.pdf PDF
23-Section L(V4) - AMD 0003.pdf PDF
Solicitation Amendment FA440723R00020002 SF 30.pdf PDF
RFI - FY24 MACC Recompete (RESPONSE 5 SEP 23) AMD 0002.xlsx XLSX spreadsheet
23-Section L(V3) AMD0002.pdf PDF
Solicitation Amendment FA440723R00020001 SF 30.pdf PDF
Site Visit Log AMD 0001.pdf PDF
Section L AMD 0001.pdf PDF
11-PPI AMD 0001.pdf PDF
Revised SOW AMD0001 1123710 REPAIR Renovate Red Cross Elevate B21 - REV1.pdf PDF
Preconstruction Conference Slide show.pptx PPTX presentation
18-SOW ATCH 6 - 1123710 REPAIR - Renovate Red Cross - Elevate_ B21 - Seed Mix.pdf PDF
3. Macc Gen Rqmts_04 August 2023.pdf PDF
8. Scott CIP.pdf PDF
3a. Arch Compatibility Guide.pdf PDF
2. MACC Gen Rqmts-EMCS 2023.pdf PDF
07-SAFB Climatic Data.pdf PDF
20-SOW ATCH 8 - 1123710 REPAIR - Renovate Red Cross - Elevate_ B21 - Applicable Comm Standards.pdf PDF
24-Section M.pdf PDF
28 - Maximum Allowable Concentrations.pdf PDF
09-DOD Safe.pdf PDF
23-Section L.pdf PDF
21-Construction_cost_estimate_breakdown.xlsx XLSX spreadsheet
27 - Soil Testing and Disposal Procedure.pdf PDF
05- WD IL230007-Apr 2023.pdf PDF
19-SOW ATCH 7 - 1123710 REPAIR - Renovate Red Cross - Elevate_ B21 - Utilities.pdf PDF
14-SOW ATCH 2 - 1123710 REPAIR - Renovate Red Cross - Elevate_ B21 - Map.pdf PDF
25 - Table 6-1. Fixed Wing Aprons.pdf PDF
04-NAF GP.pdf PDF
11a-FY 24 MACC PPQ.pdf PDF
13-SOW ATCH 1 - 1123710 REPAIR - Renovate Red Cross - Elevate_ B21 - C.Req..pdf PDF
16-SOW ATCH 4 - 1123710 REPAIR - Renovate Red Cross - Elevate_ B21 - Env. Report.pdf PDF
17-SOW ATCH 5 - 1123710 REPAIR - Renovate Red Cross - Elevate_ B21 - Historic Preservation.pdf PDF
06- WD IL230017-Jun 2023.pdf PDF
11-PPI.pdf PDF
10-Real ID.pdf PDF
22-Schedule_material_submittals.xlsx XLSX spreadsheet
26 - Non-Nuclear Configuration Management Database (CMD) Equipment Approval.pdf PDF
12-SOW 1123710 REPAIR- Renovate Red Cross- Elevate- B21.pdf PDF
15-SOW ATCH 3 - 1123710 REPAIR - Renovate Red Cross - Elevate_ B21 - Design Drawings.pdf PDF
01a-TO Procedures.pdf PDF
Solicitation - FA440723R0002.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI

Date Recv'd

Date Sent to CES

RFI Response Date

Answered

1 16-Aug-23 31-Aug-23 Attachment “19-SOW ATCH 7 - 1123710 REPAIR, Renovate Red Cross, Elevate_ B21 – Utilities” shows building 21 and 22 but the specs and other details does not include any details about building 22. Please confirm if sample project includes building 21 only.

Building 21 is the only building part of this project. Building 22 was only shown as it was on the shared site, and to allow for continuation of utilities to be shown.

31-Aug-23

2 16-Aug-23 31-Aug-23 Attachment “19-SOW ATCH 7 - 1123710 REPAIR, Renovate Red Cross, Elevate_ B21 – Utilities” shows building 21 and 22 but the specs and other details does not include any details about building 22. Please confirm if sample project includes building 21 only.

Building 21 is the only building part of this project. Building 22 was only shown as it was on the shared site, and to allow for continuation of utilities to be shown.

31-Aug-23

3 17-Aug-23 31-Aug-23 Can the PPI past performance period be extended from 3 years to 5 years? COVID created a gap within the 3 plus year timeframe identified.

Addressed in Amendment 0001to extend PPIs recency to 5 years.

5-Sep-23

4 17-Aug-23 31-Aug-23

Please clarify “relevant projects” associated with the PPI’s (Attachment 11, in accordance with Section L).

Is the gov looking for experience that is only directly related to the sample project, or broader experience related to industry and facility construction, renovation, utility installation, utility repairs and site development?

The sample project entails various disciplines within the sphere of constructiont to include specialty work. See the solicitation as to the magnitude, complexity, etc. of the PPIs requested.

5-Sep-23

5 21-Aug-23 31-Aug-23

The SOW title indicates that the Sample Project is a Bid-Build project. However, SOW paragraph 1.3 states in part, “Contractor to prepare documents and submit for SHPO approval as part of the first design review meeting.” This statement seems to indicate that this is a Design-Build project. Please clarify prior to the site visit if this should be considered a Design-Build project or a bid-build/construction only effort.

This statement has been removed per Revision #1 dated 24 Aug 2023.

31-Aug-23

6 22-Aug-23

Sent to Legal

22 AUG

In reference to SSP Attachment 3, Section L-1.4 Joint Venture Offerors: If the joint venture is comprised of 8(a) firms, the SBA must approve the joint venture agreement prior to award. Please advise if this requirement will be changed per the new FAR.

The language in the Section L attachment can be deleted.

31-Aug-23

7 25-Aug-23 31-Aug-23

1. SOW item 3.1.19.7 references the existing wood subfloor and 3.1.19.8 references the existing floor joists about installing sister floor joist next to the existing. Item 3.1.19.7 states there is 2 layers of subfloor, but we are only removing the top layer. There is no good access into the crawl space to stock the new wood joists so in our opinion it would work best to remove both layers of subfloor or we are going to have to sawcut and demo some of the foundation for better access. Can you address how you would like us to bid this work?

SOW has been revised per Revision #1 dated 24 Aug 2023. Ref. 3.1.19.7.

31-Aug-23

8 25-Aug-23 31-Aug-23

The Demolition Floor Plan sheet 1 of 5 describes the scope of demolition for the building based on the floor plan however it doesn’t address the scope of demolition in the crawl space. In our walk thru yesterday there is ductwork, piping, romex cable nailed to the floor joist, etc… what is the intent of the demolition in the crawl space?

Demolition Floor Plan (1 of 5) General Note 9 states: Remove all existing electrical, plumbing, Phone, Data, HVAC, Gyp. Bd.

and Insulation. Interior of building should be reduced to a shell consisting of existing studs. This note does not diferentiate between above and below floor and would apply to all areas of the building.

SOW 3.1.15.1 calls to remove all electrical items from building.

3.1.16.1 calls to remove all HVAC components from building,

3.1.17.1 calls to remove all existing sanitary plunbing from building

3.1.17.2 calls to remove all exisitng supply water lines from the building

31-Aug-23

9 25-Aug-23 31-Aug-23

Demolition Floor Plan sheet 1 of 5 has a General Note #9 which reads “Remove all electrical, plumbing, phone, data, HVAC, Gyp. Bd. and insulation. Interior of building should be reduced to a shell consisting of existing studs.” I assume that means demolish/remove all romex wire or any other wire or other material nailed to studs inside wall cavities?

Correct, SOW 3.1.15.1 also covers the demolition of electrical items.

31-Aug-23

10 25-Aug-23 31-Aug-23 Will the government remove the loose furniture in the building, or will that be left for the contractor to remove and dispose?

Demolition Floor Plan (1 of 5) General Note 15 states: Remove all exisitng furniture, shelving and display cases.

31-Aug-23

11 28-Aug-23 31-Aug-23 Please confirm the statement “Contractor to provide sealed documents prepared by a QFPE (Qualified Fire Protection Engineer)” found in the Revised SOW pertains to future projects rather than the sample project.

Correct, no documents to currently be prepared.

31-Aug-23

12 3-Oct-23 3-Oct-23 What % of tuck-pointing are we to bid? Per SOW 3.1.4, 60% of Masonry 3-Oct-23

13 3-Oct-23 3-Oct-23 Where the anchors get removed from the brick are we just patching the holes with mortar? Mortar is an acceptable patch for brick. 3-Oct-23

14 3-Oct-23 3-Oct-23 I saw a few damaged brick, how many brick should we figure in our price? Damaged brick to remain. 3-Oct-23

15 3-Oct-23 3-Oct-23 On the exposed exterior con foundation wall what %/S.F. of concrete patching are we to figure?

Per SOW 3.1.9 Repair cracks in foundation.

Remove previously applied crack repair if crack has re-developed or repair is missing.

Per SOW 3.1.3 (Porch) Patch and repair any spalling, breakouts, or cracks to slab and porch foundation.

3-Oct-23

16 3-Oct-23 3-Oct-23 Are we to figure applying a cementious slurry coat over the entire exposed exterior foundation wall? No, this was not mentioned in the SOW 3-Oct-23

Requests For Information (RFIs) - FY 24 MACC Recompete, B21 Red Cross sample project