FA330024R0033 Q and A.pdf
PDF 73 KB Posted
- Solicitation number
- FA330024R0033
About this file
This document is a Question and Answer (Q&A) document related to the Solicitation for Deck and Dock Repairs at the Lake Martin Recreation Area (LMRA), Solicitation No. FA330024R0033.
The Q&A addresses several details of the project, including the type of decking material to be used (5/4 pressure treated decking boards), confirmation that structural components are not part of the contract, information on the utility survey and wire installation, and the requirement for the contractor to provide a load of crushed stone for the replacement of steps. The Q&A also clarifies that providing on-site lodging for the contractor's crew is not a requirement, but will be discussed during the pre-construction conference.
The related federal contract opportunity is a Total Service-Disabled Veteran Owned Small Business (SDVOSB) Set-Aside for repairs to dock decking, stairs, and railings, as well as repairs to a lift station and replacement of railroad tie stairs at the LMRA. The estimated magnitude of the construction project is between $100,000 to $200,000, and the contracting agency is the Department of the Air Force Air Education and Training Command.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FA330024R0033 QA rev01.pdf | ||
| Atch 0004 Decking Power Map.pdf | ||
| Atch 0001 Decking Power SOW v5.pdf | ||
| Solicitation Amendment FA330024R00330001 SF 30.pdf | ||
| Atch 0003 Decking Power AF3052 Blank v2.xlsx | XLSX spreadsheet | |
| Atch 0002 WGD Al 20240115.pdf | ||
| Atch 0003 Decking Power AF3052 Blank.xlsx | XLSX spreadsheet | |
| Atch 0001 Decking Power SOW.pdf | ||
| Solicitation - FA330024R0033.pdf | ||
| Atch 0004 Decking Power Maps.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA3300-24-P-0033, Deck and Dock Repairs, Lake Martin Recreation Area (LMRA) Solicitation Questions and Answers
Per the Site Visit conducted on Tuesday, 04 June 2024, All questions were due by COB on Friday, 07June 2024.
Q1: If the statement of work is revised to encompass doing 100% decking on many of the docks/decks (which I think is reasonably anticipated), does the facility wish to deck them in 5/4 decking boards or 2x6 dimensional lumber? Dimensional lumber is much more expensive but superior in quality/durability. The same question applies to the docks/decks that currently require 100% replacement of the decking boards, are these to be replaced with 2x6 dimensional lumber or decking boards?
A1: Use 5/4 decking boards (pressure treated).; The dimensional lumber is cost prohibitive.
Q2: I wish to clarify that no structural stringers/joist are a part of this contract, and that no post are a part of this contract. We understand that from the site visit this appears to be the case, just want an official answer as many of these docks/decks do have structural issues.
A2: Structural stringers or joists are NOT a part of this contract.
Q3: Can a utility survey be provided in reference to the trenching and wire installation that is going to be required between sites 25 and 27. We only need one for this location. Is it expected that the old wire is to be dug up and disposed of or is it to be left in place and a new wire put alongside of it?
A3: A utility survey will be provided to the successful offeror. The old wire is to be abandoned in place.
Q4: Are we to procure a load of gravel to put in where the steps are to be replaced or will the gravel be provided by or installed by the facility? When the steps are pulled up it is going to make a mess. Either the contractor or the facility needs to provide a load of gravel and put it down or it is going to render the new steps a muddy mess.
A4: Offerors should account for supplying a load of crushed stone to use in re-installation of the steps within their proposal (AF3052).
Q5: Is the facility willing to provide a few campsites to facilitate lodging for our crew? This will make it simpler logistically as well as more secure for our tools and equipment storage.
A5: Staying on site will be discussed with the awardee during the Pre-Construction Conference and shall not be a part or contingent part of the anticipated contract.
(End of Questions and Answers)