About this file
This document appears to be a set of power maps that are part of a federal contract opportunity. The maps indicate that the contractor will be required to replace underground power cables in two locations, with the new cables having similar capacity to the existing cables and being buried at least 24 inches underground. Termination at two pedestals is also required, with the contractor responsible for verifying the details in the field and ensuring both pedestals are made operational.
The related federal contract opportunity is for a solicitation titled "Repairs at Lake Martin (Decks & Docks) PNQS 23-4097". This is a Total Service-Disabled Veteran Owned Small Business (SDVOSB) Set-Aside project with a construction magnitude estimated between $100,000 to $200,000. The project involves furnishing all necessary equipment, labor, supervision, and materials to perform various repairs to dock decking, stairs, railings, a lift station, and railroad tie stairs at the Lake Martin Recreational Area, in accordance with the Statement of Work (SOW).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FA330024R0033 QA rev01.pdf | ||
| Atch 0004 Decking Power Map.pdf | ||
| Atch 0001 Decking Power SOW v5.pdf | ||
| Solicitation Amendment FA330024R00330001 SF 30.pdf | ||
| FA330024R0033 Q and A.pdf | ||
| Atch 0003 Decking Power AF3052 Blank v2.xlsx | XLSX spreadsheet | |
| Atch 0002 WGD Al 20240115.pdf | ||
| Atch 0003 Decking Power AF3052 Blank.xlsx | XLSX spreadsheet | |
| Atch 0001 Decking Power SOW.pdf | ||
| Solicitation - FA330024R0033.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Map 1
Contractor will Replace underground power in the location indicated.
New cable will have similar capacity to existing and will be buried at least 24 inches underground.
Termination at two pedestals is required. Both pedestals will be made operational (Contractor to verify details in the field)
Map 2
Contractor will Replace underground power in the location indicated.
New cable will have similar capacity to existing and will be buried at least 24 inches underground.
Termination at two pedestals is required. Both pedestals will be made operational (Contractor to verify details in the field)