Repair Overruns on Center Runway Q A.pdf

PDF 493 KB Posted

Attached to
Repair Overruns on Center Runway
Solicitation number
FA309921R0002
Issued by

View the file

Other files

File Type Posted
Q A Amendment 4 MFR.pdf PDF
Solicitation Amendment FA309921R00020004 SF 30.pdf PDF
Solicitation Amendment FA309921R00020003 SF 30.pdf PDF
Solicitation Amendment FA309921R00020002 SF 30.pdf PDF
Solicitation Amendment FA309921R00020001 SF 30.pdf PDF
1E - Progress Schedule and Progress Report.xlsx XLSX spreadsheet
8. AF IMT Form 103_Work Clearance Request.pdf PDF
1Ci - EQ Contractor Tech Specs May 2019 final.pdf PDF
5. Financial Institution Reference Sheet.pdf PDF
4. AETC 47 - Recovered Materials Determination.pdf PDF
1Cvi LAFB Asbestos Management and Operation Plan (2019).pdf PDF
Solicitation - FA309921R0002.pdf PDF
1Cviii LAFB SWPPP (FOUO).pdf PDF
1Cii AF Form 3952 Chemical Hazardous Material Request Authorization Form.pdf PDF
1Cix Hazmat Usage Log.pdf PDF
9. AF IMT 3000_Material Approval Submittal.pdf PDF
7. Past Performance Questionnaire.pdf PDF
1B - 100 percent Design Specifications.pdf PDF
1A - 100 percent Design Drawings.pdf PDF
1D - AETC Installation Excellence Guide.pdf PDF
1Cvii TCEQ Multi Sector General Permit (TXR050000).pdf PDF
2. Wage Determination TX20210008, dated 01 Jan 21.pdf PDF
1Ciii Uniform Hazardous Waste Manifest.pdf PDF
3. Notification of Compliance with Contract Insurance Requirements.pdf PDF
6. Schedule of Material Submittals.xls XLS spreadsheet
1Cv TCEQ Construction General Permit (TXR150000).pdf PDF
1Civ AF Form 103 Base Civil Engineering Work Clearance Request.pdf PDF
1F - DD 1354.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE AIR FORCE

47TH FLYING TRAINING WING (AETC)

16 Jun 21

MEMORANDUM FOR RECORD

SUBJECT: FA3099-21-R-0002, Repair Overruns on Center Runway, Amendment 01; Questions and

Answers (Q&As)

Question 1: The proposal requirements call for 10 pages total for Part II - Technical Proposal.

The requirements for this proposal include resumes and certifications for qualified personnel.

Are these resumes and certifications to be counted towards the 10 page limit?

Yes for resumes; however, the certificates, including certification numbers, identification numbers, etc., can be listed in the resumes, no copies needed.

Question 2: Sub-factor 3 of Part II proposal calls for an execution schedule. Is there a page size limitation for Part II - Technical Proposal? Would the government accept an 11x17 schedule for this section of the proposal?

Yes, it would be easier to read the proposed schedule.

Question 3: Part III - Past Performance proposal calls for up to 2 pages per provided project. We are to utilize attachment 7 for these projects, this attachment is 3 pages by itself. We respectfully request that the 10 page limit for this Part of the Proposal response be removed.

No, the 10 page limit will still be in effect for the Past Performance Information. To provide further clarification, the Past Performance Questionnaires (Attachment 7), are not considered a part of the 10 page Past Performance Information (as indicated in Section M-

1 (C)). The Past Performance Questionnaires are not required but can be completed and emailed to one of the individuals as stated in Section C of the questionnaire.

Question 4: Part III - Past Performance. Will the government accept CPARS in lieu of the PPQ

Attachment 7 document? If the previous contact does not wish to fill out the attachment 7 document, will the government accept previously filled out PPQ request forms?

No, the contractor can choose whether or not to send the PPQ form. As stated in

Section M-1(C), the Government will evaluate past performance on an offeror based on (i) the references provided by the offeror and any past performance information obtained from survey/questionnaires (Attachment 7), and (ii) any other sources available to the

Government, to include, but not limited to, the Past Performance Information Retrieval

System (PPIRS), Federal Awardee Performance and Integrity Information System

(FAPIIS), Electronic Subcontract Reporting System (eSRS), or other databases; the

Defense Contract Management Agency; and interviews with Program Managers, Contracting Officers, and Fee Determining Officials.

Question 5: Section L2.D.1.f of the solicitation calls for the contractor to sign and date the RFP and return it in its entirety along with any/all amendments. Section L2.D.1(a-e) are the items required for this proposal. Would item f need to be signed?

By completing blocks 19 and 20 of the RFP, Section L-2.D.1.f of the Solicitation will be fulfilled.

Question 6: The SF1442 stipulates that 1 original and 1 copy are to be submitted as sealed offers for this contract solicitation. Section L-10 of the solicitation states that proposals are to be emailed. Please confirm which method of delivery of the proposal documents are correct.

Follow Section L-10 of the Solicitation for submitting the proposal.

JOSHUA CENTILLI

Contract Specialist

2021-06-16T10:31:58-0500