AF 3052 FRONT
| CONSTRUCTION COST ESTIMATE BREAKDOWN | OMB No. 0704-0193 | |||||||||
| Expires 31 October 1989 | ||||||||||
| CONTRACTOR | ADDRESS | |||||||||
| CONTRACT FOR (Work to be preformed) | PROPOSED TOTAL CONTRACT PRICE | |||||||||
| PURCHASE REQUEST NUMBER | PROJECT NUMBER | WORK LOCATION | ||||||||
| MATERIAL COST | LABOR COSTS | |||||||||
| LINE | UNIT | OTHER | ||||||||
| NO. | ITEM | OF | MANHOUR | AVERAGE | DIRECT | LINE | ||||
| MEASURE | QUANTITY | UNIT | TOTAL | MANDAYS | RATE | TOTAL | COSTS | TOTAL | ||
| (1) | (2) | (3) | (4) | (5) | (6) | (7) | (8) | (9) | (10) | |
| 1 | ||||||||||
| 2 | ||||||||||
| 3 | ||||||||||
| 4 | ||||||||||
| 5 | ||||||||||
| 6 | ||||||||||
| 7 | ||||||||||
| 8 | ||||||||||
| 9 | ||||||||||
| 10 | ||||||||||
| 11 | ||||||||||
| 12 | ||||||||||
| 13 | ||||||||||
| 14 | ||||||||||
| 15 | ||||||||||
| 16 | ||||||||||
| 17 | ||||||||||
| 18 | ||||||||||
| AF FORM 3052 Jan 88 | PREVIOUS EDITION IS OBSOLETE |
&CFA3047-10-B-0006&RAttachment 3 &RAtch 8
AF 3052 BACK - SAMPLE
| INSTRUCTIONS FOR COMPLETING AF FORM 3052 | ||||
| Col 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient detail to permit itemizing of | ||||
| all direct costs. | ||||
| Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples - square yards - SY, cubic yards - CY, square feet - SF, linear | ||||
| feet - LF, board feet- BF, each - EA, pound - LB). | ||||
| Col 3 Quantity. Contractor's estimate of quantity required in terms of unit of measure (column 2). Items and units of measure will be furnished by the | ||||
| Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price contract will be issed. Otherwise, the | ||||
| contractor is responsible for determining quantity estimates. | ||||
| Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total cost (col 5) for item listed in column 1. | ||||
| Col 6, 7 and 8 Labor Costs. Enter in col 6 the estimated number of manhours or mandays needed to perform the work listed in column 1. Enter in col 7 | ||||
| the average rate per manhour (manday) and in col 8 the total labor cost. | ||||
| Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1) which are special to the contract and of significant | ||||
| dollar value. | ||||
| Col 10 Line Total. Self-explanatory. | ||||
| NOTE: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on | ||||
| the last page as follows: | ||||
| TOTAL MATERIAL COSTS | $ | |||
| TOTAL LABOR COSTS | $ | |||
| TOTAL OTHER DIRECT COSTS | $ | |||
| TOTAL DIRECT COSTS | $ | |||
| OVERHEAD | % | $ | ||
| SUBTOTAL | $ | |||
| PROFIT | % | $ | ||
| TOTAL PRICE | $ | |||
| DATE ______________________________ | FIRM NAME _______________________________________________ | |||
| TITLE ______________________________ | BY ________________________________________________________ | |||
| (Signature) | ||||
| ____________________________________________________________________________________________________________ | ||||
| INSTRUCTIONS TO OFFERORS | ||||
| 1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of incurred and | ||||
| estimated costs (and attached supporting information) suitable for detailed review and analysis. Prior to the award of a contract resulting from | ||||
| this proposal the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a certificate of current cost or pricing data | ||||
| (see ASPR 3-807.3(e) and 3.807.4). | ||||
| 2. In addition to the specific information required by this form, the offeror is expected, in good faith, to incorporate in and submit with this form any | ||||
| additional data, supporting schedules, or substantiation which are reasonably required for the conduct of an appropriate review and | ||||
| analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that there be a clear understanding of | ||||
| a. The existing, verifiable data. | ||||
| b. The judgmental factors applied in projecting from known data to the estimate, and | ||||
| c. The contingencies used by the offeror in his proposed price. | ||||
| In short, the offeror's estimating process itself needs to be disclosed. | ||||
| 3. When attachment of supporting cost or pricing data to this form is impracticable, the data will be described (with schedules as appropriate), and made | ||||
| available to the contracting officer or his authorized representative upon request. | ||||
| 4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, for the purpose of verifying | ||||
| the cost or pricing data submitted, those books, records, documents and other supporting data which will permit adequate evaluation | ||||
| of such cost or pricing data, along with the computations and projections used therein. This right may be exercised in connection with any | ||||
| negotiations prior to contract award. | ||||
| (Reverse of AF Form 3052, Jan 88) |