Appendix A - Cost Breakdown.xlsx

XLSX spreadsheet 11 KB Posted

Attached to
OSI B926 Flooring
Solicitation number
FA302226R0020
Issued by

About this file

This is a cost breakdown template for construction project proposals submitted to Columbus Air Force Base. The form requires vendors to provide comprehensive pricing information organized into standardized categories: bonds and insurance (certificate of insurance, performance bonds, payment bonds, and bid bonds); mobilization costs; architecture and engineering design at multiple phases (35%, 65%, 95%, and 100% design); materials; equipment; labor hours with rates; and miscellaneous charges including Mississippi state tax. Vendors must complete all vendor information fields including name, address, contact details, NAICS code, and cage code, along with solicitation details such as project title, solicitation number, proposed period of performance, and proposal validity period. The template emphasizes that offerors bear sole responsibility for providing adequate supporting data and attachments, and must submit fully supportable pricing that reflects total project costs with documented basis and rationale for all proposed costs to enable government personnel to verify reasonableness, currency, completeness, and accuracy of the information provided.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CAFB

Appendix A - COLUMBUS AIR FORCE BASE
INSTRUCTIONS: Please provide information that properly reflects the total cost of the project. Refer to the Statement of Work and Sections L and M in the solicitation to ensure that your proposal meets the requirementsof this project.
SOLICITATION NUMBER:
CONSTRUCTION PRICE PROPOSAL BREAKDOWN
VENDOR'S INFORMATION
Name:
Address:
Phone Number:
Email:
NAICS Code
Cage Code:
SOLICITATION INFORMATION
Title of Project:
Solicitation Number:
Proposed Period of Performance
Number of Days Proposal and Price are Valid:
BONDS AND INSURANCEQTYUNIT OF ISSUEPRICETOTAL
Certificate of Insurance1
Performance Bonds1
Payment Bonds1
Bid Bonds1
subtotal
MOBILIZATIONQTYUNIT OF ISSUEPRICETOTAL
subtotal
ARCHITECTURE AND ENGINEERING DESIGNQTYUNIT OF ISSUEPRICETOTAL
35% Design
65% Design
95% Design
100% Design (Construction Set)
subtotal
MATERIALQTYUNIT OF ISSUEPRICETOTAL
subtotal
EQUIPMENTQTYUNIT OF ISSUEPRICETOTAL
subtotal
LABORHOURSUNIT OF ISSUERATEAMOUNT
subtotal
MISCELLANEOUS CHARGESQTYUNIT OF ISSUEPRICETOTAL
Misissippi State Tax
subtotal
CONSTRUCTION PROJECTTOTAL PROJECT PRICE
GENERAL INFORMATION
The purpose of the requested information in the attached worksheets is to assist government personnel in the review and evaluation of proposals submitted by offerors. Offerors are reminded that the responsibility for providing adequate supporting data and attachments lies solely with them. Further, the offeror must also bear the burden of proof in establishing reasonableness of proposed pricing; therefore, it is in the offeror’s best interest to submit a fully supportable and well-prepared cost proposal that reflects the total cost of the project. The basis and rationale for all proposed costs should be provided as part of the proposal so that Government personnel can place reliance on the information as current, complete and accurate.