Questions and Answers Clarification (Question 20 and 62) (VNVP 181605 – Repair Chiller, Cooling Tower, & Controls, B1080)

Question: "What is the size of the existing breakers that feed MCC and G, and are we replacing the existing OCP devices or reusing them?

Answer: The intent is to reuse the existing OCPDs in both MDPs. Refer to the two attached drawings for more info.

Attachments:

1 - Switchboard Elevation Drawing

2 – Electrical Drawing