This document is a Questions and Answers (Q&A) response set for a Design-Build contract to repair Multi-Service Facility B2263 located at JBSA-Fort Sam Houston, Texas. The file contains 82 contractor questions and corresponding government responses covering scope clarification, technical specifications, and project requirements.
The facility is a 79,583 gross square feet historic building requiring comprehensive renovation including structural repairs, MEP systems replacement, communications infrastructure upgrades, and fire protection system installation. Key scope elements include: standby generator installation with load calculations to be determined by the contractor; Juliette railing fabrication and historic preservation review per Section 106 consultation; elevator repair or replacement assessment based on flood damage; attic clay tile partition wall infill per code requirements; operations center development with TEMPEST/RED-BLACK Level II separation requirements; communications rooms with open 7-foot data racks and CAT6A cabling; fire pump yard with masonry screening; and removal of non-compliant temporary systems. The contractor must incorporate LiDAR scan data (provided after Notice to Proceed), conduct geotechnical investigations for foundation design, address multiple hazardous materials datasets (2013 Argus, 2018 DSE, 2024 Baer reports) with observations from site walks determining actual abatement quantities, and maintain moisture control during HVAC system installation. The performance period is 786 calendar days with commissioning requirements per Section 01 91 00.15, design review phases at 35%, 65%, 95%, and IFC milestones, and liquidated damages applicable per solicitation terms. Amendment 0005 extended the proposal due date to July 20, 2026. Pricing is firm fixed with no separate line items or unit pricing allowances for discovered conditions.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
No. Contractor Question/RFI or Recommendation Government Response
1 Building Square Footage (Scope & Pricing Driver): Please provide the approximate gross square footage of Building B2263 included in the renovation scope, broken down by floor/level if available.
The gross square footage of the facility in the Government record is 79,583 SF. Breakdown by floor is not available.
Standby Generator – Size, Location & Integration: Please confirm the exact or estimated kW rating, voltage, fuel type, and preferred/required location for the new standby generator, along with any load calculation basis discussed during the site visit.
KTR shall refer to Specification 01 11 00 para 1.4.1.2.4 Geotechnical; 1.4.1.2.12 Electrical & KTR is to determine size needed based on load calculations from end users requirements.
Juliette Railings – Quantity & Fabrication Requirements (Amendment 0004, Item 48): Amendment 0004 states there are 17 long and 19 short railings on site, which is insufficient. Please confirm the exact number of windows on the south façade (1st and 3rd floors) requiring refinishing/reinstallation or new fabrication, and provide dimensions/profiles for matching historic railings per Section 01 11 00 paragraph 1.4.1.2.7.j(12).
KTR shall refer to Specification 01 11 00 Appx B_B2_19880620_As-built for EXTERIOR ELEVATIONS sheet, in combination with the RFI responses provided.
Juliette Railings – Historic Approval & Installation Process: Please clarify the process and timeline for historic preservation review/approval of newly fabricated Juliette railings, including any required Section 106 consultation.
KTR shall refer to Specification 01 11 00 para 1.4.1.2.7.j.(12) & (13) & Appx A_01 32 33.00_ATT-01_Consultation Package Template
Existing Elevator – Flood Damage Extent & Repair vs. Replacement (Amendment 0004, Item 56): Please provide details from the site visit regarding the extent of flooding damage to the elevator machine room and pit to support repair-versus-replacement analysis.
During each site visit, the elevator machine room location was identified. In each instance it was stated that water had flooded this space and likely caused water damage to the existing equipment. With no power distribution in the facility the extent of equipment damage cannot be confirmed. Based on site observations pointed out to contractors in-attendance, the water level in the space likely reached approximately 6 ft in height.
6 LiDAR Scan Data – Delivery Timeline & Accuracy: Please confirm when the Government-provided LiDAR scan data will be available after NTP and any known limitations regarding accuracy or registration.
As stated in specification 01 11 00 section 1.4.1.2.1.a(3)(a), data will provided after NTP. There are no known limitations to their accuracy or registration.
Geotechnical Data for Generator & Fire Pump Foundations: Please provide any available geotechnical reports or boring logs from previous projects at or near B2263 for foundation design of the generator yard and fire pump screen walls.
KTR shall refer to Specification 01 11 00 para 1.4.1.2.4
Prior Contractual Effort – Specific Deficiencies & Scope of Rework: Please provide a more detailed description of the specific deficiencies from the previous contractual effort that must be corrected or reworked under this contract.
KTR shall refer to Specification 01 11 00 para 1.4.1.2.1(1) and all subsequent items.
Attic Clay Tile Partition Walls – Code-Required Infill Locations (Amendment 0004, Item 47): Please identify which openings in the existing clay tile block partition walls in the attic require infill per code versus those that may remain open.
Design shall determine if any infill of attic clay block walls is required. This is the purpose of executing this project as design-build. KTR is to research appropriate codes to determine required infill for proper airflow.
Communications Rooms – Rack/Cabinet Configuration & Sparing (Amendment 0004, Items 26-29): Please clarify whether communications rooms should use full open 7’ data racks or reuse existing cabinets, and confirm sparing requirements per UFC 3-580-01.
KTR shall refer to Specification 01 11 00 para 1.4.1.2.13 and referenced UFC 3-580-01. In UFC 3-580-01 para 2-
3.1.5.3 and 2-3.1.5.4.
Operations Center – Conference Table NIPR/SIPR Drops (Amendment 0004, Item 19): Please confirm the exact number and configuration of NIPR/SIPR drops required in the large conference table within the Operations Center.
Assumed total quantity provided in previous RFI responses (solicitation Amendment 0004). Answer implied an equal split between NIPR and SIPR drops.
White Noise System – Locations & Performance Criteria (Amendment 0004, Items 23-25): Please provide additional detail on white noise system requirements in the Operations Center (locations and performance criteria).
ICD-705, UFC 4-010-05 & DoDM 5200.01, Volume 3
OSP Entrance Facilities – 502nd Coordination Process (Amendment 0004, Item 38): Please clarify the process and timeline for coordination with the 502nd regarding the OSP fiber and copper entrance issues at the Stanley Street side.
802 CES submits all questions to Installation stakeholders for coordination. Coordination may begin after a contract has been awarded and NTP issed by 502 CONS. While there have been multiple insinuations that there are issues with the existing cabling coming into the existing entrance facility, 502 CS has examined the cabling and not identified any concerns with their continued use.
Subsurface Utility Investigation – Quality Level & Government Maps: Please confirm whether additional subsurface utility investigation beyond Quality Level B is anticipated and whether updated Government utility maps beyond ATT-10 are available.
KTR shall refer to Specification 01 11 00 para 1.4.1.2.3(1)
15 HAZMAT Reports – Current Quantities & Locations: Please provide any updates or additional sampling results to the HAZMAT reports since the 2024 report.
The 2024 report is the most recent report conducted by the 802 CES.
16 Performance Period & Liquidated Damages: Please confirm the required performance period and whether liquidated damages apply.
KTR shall refer to Specification 01 11 00 para 3.1 PERFORMANCE PERIOD.
KTR shall refer to the solicitation for liquidated damage details.
17 Section 106 Review Process – Timeline & Expectations: Please provide guidance on the Section 106 review timeline, expected iterations, and how historic character-defining features will be identified.
KTR shall refer to Specification 01 11 00 para 1.4.1.2.1.b.(2)(a)1. & Appx A_01 32 33.00_ATT-01_Consultation Package Template All references to Section 106 review are listed throughout the Statement of Work and the consultation package that will be prepared and submitted by the CRO to SHPO.
18 Existing CAT6 Cable Reuse vs. Replacement: Please clarify whether existing CAT6 cable on the 2nd and 3rd floors may be reused where it supports the new layout, or if full CAT6A replacement is required.
KTR shall refer to Specification 01 11 00 para 1.4.1.2.13.g
19 Communications Room Sparing & Existing Cabinet Modifications: When retaining existing 7’ cabinets, please confirm whether full sparing requirements still apply and if fans or ventilation modifications are required.
KTR shall refer to Specification 01 11 00 para 1.4.1.2.13 and referenced UFC 3-580-01. In UFC 3-580-01 para 2-
3.1.5.3 and 2-3.1.5.4.
Operations Center – Door Hardware Side & Lock Type (Amendment 0004, Items 9-12): Please confirm which side of the separating door should receive the X-10/cipher lock and whether FSH standard cipher locks are acceptable on NIPR comm room doors.
See detail in Appx A_01 11 00_ATT-07_MEDCOM Requirements. Page 10 showing access control icons.
21 MEDCOM Functional Requirements & Space Usage (ATT-6 & ATT-7): Please provide additional clarification on intended functions and any special MEP or security requirements for rooms whose usage is not clearly labeled.
Specification 01 11 00 para 1.4.1.2.1a.(1) includes rework to the design that does not meet Appx A_01 11 00_ATT- 07_MEDCOM Requirements
22 Qualified Fire Protection Engineer (QFPE) – Scope of Review & Involvement: Please clarify the expected involvement of the QFPE during design phases and construction for Divisions 21 and 28.
KTR shall refer to Specification 01 11 00 para 1.4.1.2.1.b.(1)
23 Commissioning Requirements – Scope & Level (Section 01 91 00.15): Please confirm the required level of commissioning and the roles of the Contractor, DOR, and any Commissioning Authority.
Specification 01 91 00.15 explains entire commissioning requirements for the project.
24 Design Submittal Requirements – Detail Level at Each Phase: Please provide guidance on the expected level of detail and specific deliverables at the 35%, 65%, 95%, and IFC phases.
KTR shall refer to Specification 01 33 16.00 30 para 1.3.13 through 1.3.16. A similar question was asked and responded to in the first round of RFIs (i.e. question #42).
Site Access, Badging, Staging & Laydown Constraints at JBSA: Please provide details on access requirements, badging/escort procedures, and any staging or laydown limitations due to the historic building or base operations.
KTR shall refer to Specification 01 14 00 para 1.4.1.2 for Installation access requirements. Refer to specification 01 50 00 para 3.5 and 3.7 for general guidance and restrictions for contractor temporary facilities. Refer to specification 01 50 00 para 3.3 for guidance on traffic provisions on the Installation.
26 Moisture Control & Mold Prevention During Construction: Please provide specific standards or monitoring requirements for moisture control while the HVAC system is not fully operational.
KTR shall refer to specification 01 32 33.00 referenced NPS TPS Brief 39, specification 01 33 29 para 1.6.12, & specification 01 35 26 para 1.16.
27 Fire Pump Yard – Location, Screening & AT/FP Requirements: Please confirm the location and provide additional detail on screening and AT/FP requirements for the fire pump yard.
KTR shall refer to Specification 01 11 00 para 1.4.1.2.6.b
Project Title: DB - Repair Multi-Service Facility B2263 Project Location: JBSA-Fort Sam Houston, Texas
28 Existing Conditions Verification Responsibility – Historic Elements: Please clarify the Contractor’s responsibility for field verification of existing dimensions, particularly for historic elements and new-to-existing interfaces.
The required Historical Architect should understand the scope and its historical fabric and context related to the requirements for dimensions and details. All previously supplied information is strictly for reference only.
KTR shall refer to Specification 01 11 00 para 1.4.1.2.1.b.(2) and all subsequent sub paragraphs & Appendix B for appropriate historical dimensions as they relate to the areas identified throughout Specification 01 11 00 as requiring Section 106 review.
KTR shall refer to Specification 02 41 00 para 1.10.
29 Request for extension of the proposal due date: Request to extend the proposal due date no fewer than 21 calendar days?
Extension for an additional 7 calendar is included in this Amendment 0005: New Proposal Due Date is 20 July 2026 at 1000 Central Time.
Hazardous materials — the package contains three non-reconciling datasets (2013 Argus, 2018dse, and 2024 Baer with Nov 2024 lead sampling) with no single controlling survey identified, leavingabatement and disposal quantities indeterminate:
The 2024 report is the most recent report conducted by the Government.
1.Controlling survey. The solicitation includes three hazardous-materials datasets (2013 Argus,2018 dse from 2017 inspections, and the 2024 Baer report with November 2024 additionalsampling). Which single dataset is contractually controlling for pricing abatement, and will theGovernment reconcile them into one governing survey?
Basis: 2018 dse identified asbestos VCT/mastic and chrysotile window glazing plus PCBs and mercury; 2024Baer addresses only basement moisture barrier and pipe insulation.
Each report targeted a separate area of focus. There will be no single compiled report. Contractors shall use their observations from the multiple site walks to determine if any previously identified hazardous material is still present. Refer to specification 01 11 00 para 1.4.1.2.2 for hazardous materials still left to address.
2.Asbestos materials status. Were the VCT floor tile, black mastic, and wood-window glazingcompound identified in 2018 abated since 2017, or simply not re-sampled in 2024? If abated,please provide abatement close-out documentation.
Abatement documentation not available despite work having taken place.
Each report targeted a separate area of focus. There will be no single compiled report. Contractors shall use their observations from the multiple site walks to determine if any previously identified hazardous material is still present. Refer to specification 01 11 00 para 1.4.1.2.2 for hazardous materials still left to address.
3.PCBs and mercury. The 2018 report addressed PCBs (ballasts, caulk, paint) and mercurydevices; the 2024 report did not. Please confirm whether these have been re-surveyed andprovide the data needed to price disposal.
The 2024 report only includes items not previously sampled. All reports must be taken together.
4.Lead-based paint quantities. The November 2024 sampling identified a basement beam at1.37 mg/cm² as LBP.
Please confirm the full count and locations of LBP-positive surfaces andlead-containing components requiring OSHA 29 CFR 1926.62 controls.
Per direction from the referenced report, "The results apply to all surfaces that share the same component, color, and/or substrate". Quantitiy shall be determined from observations made during the full facility walkthrough performed during the site visits.
5.Abatement pricing structure / allowance. Is asbestos/lead abatement to be priced within thelump-sum design-build or as a separate line item, and will the Government provide anallowance or unit-price mechanism for quantities discovered beyond the controlling survey,consistent with the express ‘limited / inaccessible area’ caveats in each survey and theDiffering Site Conditions clause (FAR 52.236-2) already incorporated?
Refer to Section B of the solicitation. No separate breakout is required. No unit-pricing or allowances for work.
Per solicition requirements pricing must be firm fixed pricing. Specification 01 11 00 para 1.4.1.2.2 and contractor observations from the full facility walk through during site visits will allow contractors to build their proposals. Given the state of the facility, existing conditions are clearly visible.
Other remediation allowed per OSHA need to be detailed to ensure adherance to the Environmental and Historical specifications.
Secured Operations Center — thecontrolling TEMPEST / RED-BLACK criteria are classified or not provided, preventing pricing ofshielding and filtered power absent a cleared briefing:
There is no classified information briefing required or that will be provided. Per referenced UFC 3-580-02, which references CNSSAM 1-13 for application of RED/BLACK separation. Level II separation is the requirement for the Operations Center.
1. Accreditation path. The Operations Center is specified as Open Storage (to Top Secret) withTEMPEST, IDS (two systems), access control, and vault doors. Confirm whether the space must be accredited as an ICD 705 SCIF, and identify the Accrediting Official / Cognizant Security Authority and the required Construction Security Plan.
Basis: SOW references Open Storage and UFC 4-010-05 but does not identify the AO/CSA or CSP.
This space does not require accreditation, a site security manager, or a construction security plan0.
KTR shall refer to Specification 01 11 00 para 1.4.1.2.7.b; Appx A_01 11 00_ATT-07_MEDCOM Requirements; & Appx A_01 11 00_ATT-04_AR380-5
2. Security construction responsibility. Will a Site Security Manager and/or Construction Surveillance Technicians be required, and is the contractor responsible for personnel clearances and the Construction Security Plan?
Please provide the controlling security-construction criteria document (e.g., ICD 705 Technical Specification).
A site security manager is not required for this project.
3. TEMPEST / RED-BLACK criteria. The controlling TEMPEST and RED/BLACK criteria appear to be classified or are not provided. How are offerors to design and price TEMPEST shielding, filtered power, and RF separation without the criteria, and will the Government provide a cleared briefing during the proposal period?
There is no classified information briefing required or that will be provided. Per referenced UFC 3-580-02, which references CNSSAM 1-13 for application of RED/BLACK separation. Level II separation is the requirement for the Operations Center.
4. Operations Center generator. Confirm fuel type, runtime/fuel storage, emissions permitting (TCEQ), and location for the dedicated backup generator, and whether the Generator Authorization Request (ATT-11) must be approved before award. Note: the provided ATT-11 appears to be a blank, non-rendering form.
Refer to specification 01 11 00 para 1.4.1.2.12(a). Default fuel storage requirement of 24 hours is defined in UFC 3-540-01. Final location is to be determined during design, as the location shown during site walks is only a Government suggestion. All project environmental requirements are outlined in specification 01 57 19. ATT-11 is to be filled by the KTR after award once load calculations for the required generator size have been performed by the respective DOR.
5. RMF / ATO. ATT-02 (Master FRCS RMF Controls) is included. Please confirm whether the contractor must achieve an Authority to Operate (ATO) for the facility-related control systems and identify the Authorizing Official.
An ATO exists for EMCS, FMCS, and IDS. Any other control system is the responsibility of the end user to authorize. All systems shall meet cybersecurity requirements.
Program documentation — theMEDCOM space-summary attachment needed to size the program is referenced but not included:
It is provided in specification 01 11 00 attachment 7, located in Appendix A.
1. Missing MEDCOM attachment. The MEDCOM Requirements reference Attachments 1–4 (space-summary document, Operations Center draft schematic, access-control requirements, additional door requirements).
These do not appear in the package. Please provide them — the program cannot be sized without the space-summary attachment.
Basis: ATT-07 conceptual layout/end-user narrative is provided, but the referenced sub-attachments are not.
They are included in ATT-7, the narrative is only the first 4 pages as a typed word document. Scroll down to the see the rest. ATTACHMENT 1 starts on PDF page 5 and is listed as ATTACHMENT 1 at the top of the page.
41 2. Requirements baseline. Please confirm that the MEDCOM Requirements (217 total personnel) are final and frozen as the design basis for this proposal.
Confirmed
3. FF&E boundary. FF&E for the auditorium (and possibly other spaces) is excluded from initial award but ‘accounted for as part of the CID.’ Please confirm the power, data, and structural provisions the contractor must design to accommodate the future FF&E installer.
KTR shall also refer to Specification 01 11 00 para 1.4.1.2.8.c & Appx A_01 11 00_ATT-07_MEDCOM Requirements for Auditorium details.
Criteria, codes & precedence:
1. Governing criteria editions. Please identify the controlling UFC and code editions (IBC/NEC/NFPA) and confirm the antiterrorism/force-protection (UFC 4-010-01) standoff and progressive-collapse applicability for this occupancy, including whether existing blast-resistant and progressive-collapse features must be maintained or extended.
KTR shall refer to REFERENCES section in PART 1 GENERAL of each Specification.
KTR shall refer to UFC 4-010-01 STANDARD 6.
2. Existing-building code triggers. Confirm the seismic design category and wind criteria for the site, and whether the existing structure must be brought into current code compliance as part of the repair (triggering structural-upgrade scope).
KTR shall refer to REFERENCES section in PART 1 GENERAL of each Specification.
KTR shall refer to UFC 4-010-01 STANDARD 6.
3. Sustainability target. Please state the required sustainability/energy outcome — e.g., Guiding Principles compliance vs. a LEED level — and the governing energy standard edition (UFC 1-200-02 / ASHRAE 90.1), given the HPSB checklist and AF Sustainability Scoresheet in the package.
LEED not required. KTR shall refer to Specification 01 33 29 para 1.4
46 4. Fire protection basis. Confirm the governing NFPA 13 edition and whether flexible sprinkler drops are permitted (JBSA Flexible Sprinkler Request Form, ATT-08).
See Response to Item # 43 & 01 11 00 para 1.4.1.2.9.d.
5. Design-document precedence. Please confirm the order of precedence among the SOW, specifications, drawings, MEDCOM Requirements, and design criteria for resolving conflicts — in particular, how the conflicting hazardous-materials surveys are to be resolved under FAR 52.215-8 and 52.236-21.
Specification 01 11 00 para 1.4.1.2.1a.(1) includes rework to the design that does not meet Appx A_01 11 00_ATT- 07_MEDCOM Requirements.
All previously supplied drawings are strictly for reference only.
Each report targeted a separate area of focus. There will be no single compiled report. Contractors shall use their observations from the multiple site walks to determine if any previously identified hazardous material is still present. Refer to specification 01 11 00 para 1.4.1.2.2 for hazardous materials still left to address.
Existing conditions & schedule:
1. Existing MEP / structural data. No existing MEP or structural drawings are provided, and the Observed Site Conditions sheet places verification on the contractor. Will the Government provide existing MEP/structural documentation, or permit destructive/above-ceiling investigation during the proposal period?
Refer to Appendix B (solicitation attachment 5) for available drawings. Refer to specification 01 11 00 para 1.4.1.2.a for general scope overview, para 1.4.1.2.10 for plumbing scope, para 1.4.1.2.11 for mechanical scope, para 1.4.1.2.12 for electrical scope. Given the current state of the facility, it is non-sensical for this question to ask for destructive/above-ceiling investigation since all conditions are exposed.
KTR shall refer to Specification 01 11 00 para 1.4.1.2.11.e and all subsequent paragraphs.
All previously supplied drawings are strictly for reference only.
2. Phasing & occupancy. The Period of Performance is stated as 786 calendar days. Please confirm whether B2263 will be fully vacated, partially occupied, or swing-space phased during construction, and identify any occupancy constraints.
This building is in a deconstructed state and is not capable of normal occupancy during construction. It is currently only fit for occupation for typical construction activities.
50 3. Design-review cycle. Please confirm the number and duration of Government design-review stages (e.g., 35/65/95/100%) and over-the-shoulder reviews, and confirm these are reflected in the Period of Performance.
Yes, KTR shall refer to Specification 01 11 00 Part 3 and 01 33 16.00 30 para 1.3.13 - 1.3.16
4. Critical-path close-out items. Confirm whether commissioning (01 91 00.15), the Facility Data Workbook (01 78 24), and DD Form 1354 close-out (01 78 00) are on the critical path for substantial completion, and confirm liquidated-damages and beneficial-occupancy milestones.
Critical path must be determined from all Spec requirements including those developed during Design as well as the KTR's sequencing of work activites. This includes Beneficial Occupany.
KTR shall refer to the solicitation for liquidated damage details.
52 5. Badging lead times. Please confirm base access/badging lead times for cleared and uncleared workers, escort requirements in classified areas, and the Unescorted Access Request (ATT-01) processing timeline.
No areas are classified. KTR shall refer to Specification 01 14 00 para 1.4.1.2
53 6. Utility outage windows. Please confirm the utility-outage request procedure and the maximum allowable outage windows (ATT-03) for the occupied building, which affect sequencing and price.
No areas are classified. KTR shall refer to Specification 01 14 00 para 1.4.6.2
01 11 00 Summary of Work
Exterior Infill at Patios:
There are a number of locations where there will be infills at the patio areas. Is it acceptable to user metal framing and exterior grade gypsum board with an exterior plaster to match the existing exterior surface that is acceptable to CRO?
The breezeways have been enclosed.
Furred out walls in Basement:
During the site walk it was observed that there is approximately 400 lineal feet of exterior wall in the basement that was not furred out. Is it the intent of this project to have the exterior basement walls furred out?
KTR is to provide a design that meets all Government requirements. KTR shall refer to REFERENCES in Specification 01 32 33.00 that do not allow surface mounting to existing historical fabric.
KTR shall refer to Specification 01 11 00 para 1.4.1.2.12g.(1) & 1.4.1.2.13.f.(3) as examples where this is called out.
Ceiling Framing at Windows:
Given the existing floor to underside of overhead slab dimensions and the existing windows, it may be necessary to lower the ceilings below the tops of the windows to accommodate all of the MEP and Comm utility system that will need to be installed above the ceilings. Is it the intent of the project to provide an additional furr out of the existing exterior walls to accommodate the ceilings being lower than the tops of the windows, or is there some other method that the Government entertain at the windows.
KTR shall refer to Specification 01 11 00 para 1.4.1.2.7.j.(11)
Window Caulking/Sealing:
The SOW for the project indicates that there is no work required for the existing windows, with the exception of the oval window over the main entrance. Is the contractor to understand that the existing windows have had backer rod and caulking/sealant applied to them on both the interior and exterior of the building and no further treatment is necessary.
KTR shall refer to Specification 01 11 00 para 1.4.1.2.7.d.(2 & 3)
Fire Protection System:
We understand that the temporary fire sprinkler system is out of legal compliance. Please confirm the temporary system is to be removed in its entirety and a new code compliant system is to be installed.
Please confirm the temporary system is to be removed in its entirety and a new code compliant system is to be installed.
KTR shall refer to Specification 01 11 00 para 1.4.1.2.9.c
Fire Pump Power:
Please confirm, the fire pump will NOT be required to be supported by the backup generator.
No, KTR shall refer to Specification 01 11 00 para 1.4.1.2.12.a.(3)
Oval Window Historical Pictures:
Specification 01 11 00, Summary of Work, paragraph 1.4.1.2.7.d(1) states that the Oval window facing Stanley Rd, above the center building entrance, shall be fully detailed to correct its current improper style, size and installation. Please provide any historical pictures of the oval window to be replaced at the Stanely Rd. side of the building.
Please provide any historical pictures of the oval window to be replaced at the Stanely Rd. side of the building.
Not Available. KTR shall refer to Appx B B3 As Built drawings.
Skim Coat of Floors:
Are all floors to be skim coated to hide the fiberglass reinforcement currently in place? Refer to specification 01 11 00 para 1.4.1.2.7.j(2) & (3)
Entry Way Floors:
Please confirm that we will need to float floors at entry ways to maintain the correct rise and run from the stairs to the floor transition.
Refer to specification 01 11 00 para 1.4.1.2.7.j(2) & (3)
Ceiling Heights:
Please confirm that we are expected to get the ceilings in the low-lying areas as high as possible where mechanical, plumbing and electrical items are prohibiting the standard height.
Ceiling heights shall be installed in accordance with IBC requirements. Where ceilings will not be installed equipment must meet the same requirements.
Sealing of Windows and Doors:
Please confirm that we are not responsible for the sealing of windows and doors already installed by others.
Refer to specification 01 11 00 para 1.4.1.2.7.d. Text also applies to exterior doors not called for replacement.
Stair Well Walls:
Please confirm that the current fur out of stair walls is to be brought back to the structural block and properly abated.
Refer to specification 01 11 00 para 1.4.1.2.7.j(7)
Existing Materials:
Please confirm that we are not to anticipate utilizing any of the existing items in the 3 Connex boxes in the parking lot
Refer to specification 01 11 00 para 1.4.1.2.1.a(2)
Conex Boxes:
Please confirm that we are responsible to remove the Conex boxes, all contents, and any debris around this area off site.
Refer to specification 01 11 00 para 1.4.1.2.1.a(2)
Fire Pump Screen Wall:
Please confirm that the Fire Pump House will also receive the masonry screen wall as does the new generator.
Refer to specification 01 11 00 para 1.4.1.2.6, para 1.4.1.2.7.h, and para 1.4.1.2.7.i
Lift Stations:
Please confirm that we are responsible to repair and/or replace the two lift stations at the rear of the building and only coordinate this effort with American Water.
Refer to specification 01 11 00 para 1.4.1.2.1.10.f
Construction Site Fence:
Please provide a detailed map of the allowable fenced construction site for the duration of the construction project.
KTR shall refer to Specification 01 14 00 para 1.4.1.2 for Installation access requirements. Refer to specification 01 50 00 para 3.5 and 3.7 for general guidance and restrictions for contractor temporary facilities. Refer to specification 01 50 00 para 3.3 for guidance on traffic provisions on the Installation.
CAT 6 vs CAT 6A Wiring:
Reference is made to the attachment to Amendment 0004, Amendment_0004_RFP_RFIs_Combined_6_5_2026, Item No. 3. The question asked was "There is existing CAT6 cable that has already been placed on this project in some locations on the 2nd and 3rd floors. If the location of these existing CAT6 cables will support the new floor plan, may the existing CAT6 cables be left in place and re-used? Or does the Government want the contractor to remove all CAT6 (drop wire) and replace it with CAT6A?" The response provided was "KTR shall refer to 01 11 00 para 1.4.1.2.1.a(1) and 1.4.1.2.13.g" 1.4.1.2.1.a(1)”, which says “Provide full design to complete the renovation and construction of the facility and its supporting facilities.
(1) Includes redesign and rework of the previous contractual effort that is found to be deficient or in violation of current UFC requirements and its referenced codes and standards. PER the UFC, 2-3.3.2.1 Copper UTP.
a. Category 6A is the standard. Do not use Category 3, 5, 5e, or 6 rated cabling in new construction or rehabilitation projects for ICT.
Please confirm that all existing CAT 6 wiring is to be removed and all new CAT 6A wiring is to be installed.
Answered in the previous round of RFIs. Please refer to those responses.
Redacted Copies:
Section 8.3 advises the Offeror to redact company names (Prime, Subcontractors, and Teaming Partner(s)) as well as logos, emblems, CAGE Codes, and UEI Identifiers.
Section 11.5.4 states, " The Offeror shall provide a statement on their company letterhead acknowledging the requirements of key personnel for this contract and the personnel selected for this project will meet the minimum qualifications listed above."
Section 12.5 advises the Offeror to complete a Past Performance Information Form (PPIF) for at least three (3) separate contracts.
Please clarify if the redaction of company identifiers include key personnel names (Section 11.5.4) as well any or all portions of the PPIF (Section 12.5) for past performance.
Personnel names are not required to be redacted.
The PPIFs will be returned directly to the POCs for this project and do not require redaction.
The documents submitted by the KTR must have an un-redacted and redacted copy.
NIPR Wiring in Ops Center:
Reference is made to the attachment to Amendment 0004, Amendment_0004_RFP_RFIs_Combined_6_5_2026, Item No. 15. This asked the question “Does the government want NIPR to be CAT6A, or fiber in the Operations Senter?? The government response was “ KTR shall refer to 01 11 00 para 1.4.1.2.13.g, the answer is no to fiber to workstations”. Amend 4 does not have a “1.4.1.2.13.g” The UFC says: 2-3.3.2.1 Copper UTP.
a. Category 6A (CAT6A). Provide one CAT6A UTP cable to each standard 8-pin modular jack...
Note: When specifically required by other criteria or needed for the application, such as high bandwidth uncompressed video, designers may use screened or shielded twisted pair (ScTP or STP) cabling (as in Europe or secure areas). The key word being “may” as in it is not required.
Does the government want (require) the NIPR to be CAT6A, or CAT6A shielded in the Operations Center?
That answer is partly addressed by the previous Government responses and the response provided to item #37:
There is no classified information briefing required or that will be provided. Per referenced UFC 3-580-02, which references CNSSAM 1-13 for application of RED/BLACK separation. Level II separation is the requirement for the Operations Center.
Equipment Racks:
Per the RFI’s and specs, open 7’ data racks are to be used in the Comm Rooms. During the walk we noticed that there are 7’ data cabinets in at least 2 of the existing Comm rooms. Question 26 – 29 asked the government about these existing cabinets.
The government’s response was to refer to the UFC. Per the UFC 2-3.1.5.3 Equipment Racks. Provide 19-inch (475-millimeter) floor-mounted equipment racks. A minimum of 36 inches’ (900 millimeters’) space, both in front and behind the rack measured from the equipment, and a minimum side clearance of 36 inches on at least one end of the rack or row of adjacent racks is required. Allow a front-to rear-space of 42 inches (1067 millimeters) to accommodate equipment. Coordinate with the Information Communications Technology Manager to determine the space and weight requirements for the USG-provided active equipment. A four-post rack may be required to support equipment due to weight or mounting requirements. Provide 25% spare rack unit capacity within each rack used. Provide one spare rack for every four used racks, with a minimum of one spare rack per telecommunication space.
In existing facilities with narrow or crowded telecommunication spaces, equipment racks may be wall-mounted with the approval of the Information Communications Technology Manager. Workspace around the cabinet/rack is still required even if the cabinet is mounted 6.5 feet (2 meters) off the floor. Refer to Figure 2-3.
2-3.1.5.4 Equipment Cabinets.
Provide equipment cabinets in lieu of racks where:
-identified by Service-specific chapters in this UFC.
-required by the Information Communications Technology Manager.
-physical security is required, such as to mount secure or mission critical equipment.
-separately controlled access is desired (when multiple systems are collocated within the room).
The UFC states the contractor can use data racks in the NIPR comm rooms. Cabinets would be an acceptable upgrade, but, these existing cabinets eat up all of the floor space and will not allow for the” sparing” required in the UFC.
Does the government want the contractor to remove these cabinets and replace them with 2 Open Data Racks due to floor space since only one cabinet will fit in the existing comm rooms that currently have them in place?
KTR shall refer to Specification 01 11 00 para 1.4.1.2.13 and referenced UFC 3-580-01. In UFC 3-580-01 para 2-
3.1.5.3 and 2-3.1.5.4.
Comm Room Door Locks:
Reference is made to the attachment to Amendment 0004, Amendment_0004_RFP_RFIs_Combined_6_5_2026, Item No. 30 which asked for clarification relative to previous questions asked on comm room door locks. One answer/response from the government states that the government does not want the contractor to provide KABA (cypher) locks on the comm room doors, but in another answer/response from the government (RFI 005 question 88) it states that the government does want the contractor to provide keyed locks on each of the NIPR comm rooms. The government ‘s answer to questions 11 and 30 was equating Cypher locks to X-10’s. My question is not about x-10’s locks, X-10’s are for the operations center. My question addresses the placement of KABA cyber locks on NIPR comm rooms outside the operations center.
Does the government want the contractor to provide Kaba (cypher) locks on all the NIPR comm room doors (FSH’s Standard)?
Yes, cypher locks shall be installed on NIPR comm room doors. Assume lockset must also include a key core.
ESP OSP Fiber Cable:
Reference is made to the attachment to Amendment 0004, Amendment_0004_RFP_RFIs_Combined_6_5_2026, Item No. 38, which asked "The OSP fiber cables enter building 2263 in the middle of the building on the Stanley Street side of B-2263. There are four OSP fiber cables that are cut off right where they enter building 2263 (at the entrance duct)." The response to the question was "Please provide a specific question on the concern." The concern is that the cables are too short to splice on to in the building, so does the government want the contractor to pull all four fiber cables back into the MH and splice on to them in the MH and bring them back into the building with a longer piece of fiber that will reach to a data rack?"
Investigation from 502 COMM Squadron states there is enough fiber within the room to splice to.
Existing OSP Coppper Cable:
The OSP copper cable enters building 2263 in the middle of the building on the Stanley Street side of B-2263. The 600 pair OSP cable enters the building and is terminated on PETs on the wall where the cable enters the building. Does the government want the contractor to leave the PET as is where they are?
502 CS has confirmed that the PET does not require relocation.
Copper & Fiber Entrance Cables:
During the site walks, it was identified to the Government Representatives that existing Copper and Fiber Entrance Cable could not be used in their current condition. The fiber cables have been cut off at the entrance conduit. The existing configuration of the copper entrance may not meet the facility needs. The Government Representative suggested that we ask for a meeting to with the 502nd Communications Squadron to address the concerns. This meeting could provide better insight on the needs and allow the contractors to effectively bid this portion of the project.
Can a meeting be scheduled with the 502nd Communications Squadron to obtain clarification on the desired work relative to the copper and fiber entrance cables?
KTR shall refer to response in line Item #76 & 77: Investigation from 502 COMM Squadron states there is enough fiber within the room to splice to. and 502 CS has confirmed that the PET does not require relocation.
Voice & Data Drops:
Section J Attachment 15, RFI-Combined_Spec Updates RFI005, question 92, asked the following "Many of the rooms on the prints do not show their usage. Does the government want the contractor to assume all of these empty rooms will have 8x10 cubicles in them and the contractor is to provide 2 voice drops and 2 data drops in every cubical. The response indicated that 2 voice and 2 data drops were required. This appears to be excessive.
Please confirm that 2 voice and 2 data drops will be required to each cubical.
KTR shall refer to Specification 01 11 00 Appx A_01 11 00_ATT-07_MEDCOM Requirements
Voice & Data Cables:
Section J Attachment 15, RFI-Combined_Spec Updates RFI005, question 93 addressed installation of voice and data drops for the furniture. The response was that The cable installation piece for the cubicles shall be part of separate furniture acquisition. This leads one to understand that a sufficient length of cabling for each voice and data drop be left coiled for installation by the furniture contractor at a later date.
Please confirm that it is the government's intent that the contractor leave sufficient cabling for each and every voice and data drop so as to have continuous cabling to the outlet in each cubical. This cabling to be installed in the furniture by the furniture contractor.
Confirmed
CATV to Command Suite:
Section J Attachment 15, RFI-Combined_Spec Updates RFI005, question 96 addresses CATV outlet locations. The response indicates that CATV outlets are only required in the Ops Center.
Please confirm that CATV Outlets are not required in the Command Suite.
Answered in the previous round of RFIs. Please refer to those responses.