This document is a Statement of Work (SOW) for the purchase and installation of sheetmetal storage equipment at JBSA-Randolph in Texas.

The contractor must supply, deliver, assemble, and safely anchor one Sheetmaster 100 Roll-Out Shelf Storage System manufactured by Rack Engineering Division in blue color at Building 171, 555 A Street East, JBSA-Randolph, TX. The system must meet specific technical requirements including a 5,500 lbs. uniformly distributed load capacity per shelf, 100% full extension on 4 heavy-duty roller bearings, 84-inch overall height, 3 to 8 shelves per unit, all-welded steel construction with powder-coated finish, and an automatic locking system securing shelves at full open or closed positions. Standard shelf dimensions include depth options of 48", 60", or 72" and width options of 96", 120", or 144". The facility is a 943 square-foot concrete warehouse/maintenance shop with 20-foot ceiling height and truss construction. Contractor-specific tasks include conducting a pre-installation site survey to verify floor space and overhead clearance, delivery and offloading of all components, professional assembly and structural anchoring to the concrete floor slab, testing and acceptance through dry-run demonstrations of 100% shelf extension and automatic locking mechanism engagement, cleanup of all crating and debris, and delivery of operations manuals and warranty paperwork to the 502d Logistics Readiness Squadron. Work hours are 0700-1500 Central Time Monday through Friday, excluding federal holidays. The contractor must furnish all personnel, supplies, equipment, facilities, transportation, tools, and materials, with the Government providing only temporary storage space and utilities.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA301626Q0287

Attachment 3

STATEMENT OF WORK (SOW)

JBSA-RANDOLPH

PURCHASE AND INSTALLATION OF SHEETMETAL RACK

PART 1

GENERAL INFORMATION

1.0 Scope: The contractor shall supply, deliver, assemble, and safely anchor the Sheetmaster 100 Roll-Out Shelf

Storage System (manufactured by Rack Engineering Division) in the color blue at the designated facility. The goal of this acquisition is to optimize vertical space in redesign of new warehouse.

1.1 Equipment Specifications & Requirements

The system delivered must meet or exceed the following technical thresholds:

Parameter: Performance & Physical Requirements System Identity: Sheetmaster 100 (Roll-Out Heavy Duty Shelf System) Load Capacity: 5,500 lbs. uniformly distributed load per shelf Extension Rate: 100% full extension on 4 heavy-duty roller bearings Standard Dimensions: 84"overall height (7feet); Standard shelf width and depth listed in Salient Characteristics Shelf Configuration: 3 to 8 shelves per unit Material Construction: All-welded steel construction with a powder-coated finish Safety Features: Automatic locking system securing shelves at 100% open or closed

1.1.2 General Information

1.1.3 Recognized Holidays: Contractor is not required to perform services on holidays.

New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Juneteenth Thanksgiving Day Independence Day Christmas Day

1.1.4 Hours of Operation: The Contractor is responsible for conducting business, between the hours of 0700 – 1500 (7:00 a.m. to 3:00 p.m.) Central Time, Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. The Contractor must, at all times, maintain an adequate workforce for the uninterrupted performance of all tasks defined within this SOW when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.

1.1.5 Place of Performance: The work to be performed under this contract will be performed at 555 A Street East, Bldg. 171, located on JBSA-Randolph, TX.

1.2 Security Requirements: Contractor personnel performing work under this contract are not required to have a security clearance for this contract.

1.2.1 Physical Security: The Contractor shall be responsible for safeguarding all Government equipment, information, and property provided for Contractor use. At the close of each work period, Government facilities, equipment, and materials shall be secured.

1.2.3 Installation Access: Some travel on and off JBSA installations will be limited at times due to JBSA-controlled gate openings and closures. Unscheduled gate closures may occur at any time, and the personnel entering or exiting the installation may experience some delays. If the Contractor is denied entry to the base due to enhanced security, Contractor personnel should immediately contact the base sponsor

(502d Logistics Readiness Squadron (LRS) point of contact). Privately-owned vehicles of Contractor personnel are subject to being searched pursuant to applicable regulations. The award of this contract does not create a right to have access to any military installation. Any violation of an installation regulation or of a state or federal statute may result in the termination of the privilege to enter any JBSA installation.

1.2.4 Installation In/Out Processing. All Contractor personnel performing services under this contract shall be required to in-process and out-process through the 502d Security Forces Squadron Visitor Control Center to receive or return base passes.

1.2.5 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office if requested by the Contracting Officer or customer POC TBD. The Contracting Officer, Customer POC TBD, and other Government personnel, as appropriate, may meet as necessary with the Contractor to review the Contractor's performance. Either the Government or the Contractor may request a meeting. At these meetings, the Contracting Officer will apprise the Contractor of how the Government views the Contractor's performance and the Contractor shall apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.

1.2.6 Contractor POC: The Contractor shall provide a POC to be responsible for the performance of work under this contract. The POC shall act for the contractor and shall be designated, in writing, to the Contracting Officer. The POC shall have full authority to act for the Contractor on all contract matters relating to any issues that may arise during work performance. The POC shall be available from 0700 – 1500 (7:00 a.m. to 3:00 p.m.) Central Time, Monday thru Friday except Federal holidays or when the Government facility is closed for administrative reasons.

1.2.7 Identification of Contractor Employees: All contract personnel working in situations where their Contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by Contractors are suitably marked as Contractor products or that Contractor participation in meetings is appropriately disclosed.

PART 2

DEFINITIONS AND ACRONYMS

2..DEFINITIONS AND ACRONYMS:

2.1 DEFINITIONS:

2.1.1 CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.

2.1.2 CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the Government.

2.1.3 DELIVERABLE. Anything that can be physically delivered but may include non-manufactured things such as meeting minutes or reports.

2.1.4 PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.

2.1.5 POINTS OF CONTACT (CONTRACTOR). Those individuals identified, in writing by the Contractor, with authority to act on behalf of the Contractor with regard to this contract.

2.1.6 SUBCONTRACTOR. One that enters into a contract with a prime Contractor. The Government does not have privity of contract with the subcontractor.

2.1.7 ACRONYMS:

RFO Revolutionary Federal Acquisition Regulation (FAR) Overhaul POC Point of Contact SOW Statement of Work TE Technical Exhibit

PART 3

GOVERNMENT-FURNISHED ITEMS AND SERVICES

3. GOVERNMENT-FURNISHED ITEMS AND SERVICES:

3.1 Services: The Government will not provide any property, equipment, or services in support of this contract.

3.1.2 Facilities: The Government will provide temporary storage space for materials while work is being accomplished.

3.1.3 Utilities: The Government will provide all utilities in the facility for the contractor’s use in performance of tasks outlined in this SOW. The Contractor shall instruct employees in utilities conservation practices.

3.1.4 Equipment: The Government will not provide any property, equipment, or services in support of this contract.

3.1.5 Materials: The Government will not provide any property, equipment, or services in support of this contract.

PART 4

CONTRACTOR-FURNISHED ITEMS AND SERVICES

4. CONTRACTOR-FURNISHED ITEMS AND SERVICES RESPONSIBILITIES:

4.1 General: The Contractor shall furnish all personnel, supplies, equipment, facilities, transportation, tools, materials, and supervision required to meet the requirements of this SOW.

4.1.2 Materials/Equipment:

4.1.3 The Contractor shall furnish materials, supplies, and equipment necessary to meet the requirements under this SOW.

4.1.4 The Contractor shall provide and install one Sheetmaster 100 Roll-Out Shelf Storage System (manufactured by Rack Engineering Division) at the designated facility. The goal of this acquisition is to optimize vertical space in new redesign

4.1.5 The Contractor shall provide all operations manuals and warranty paperwork with 502

LRS/LGRMSS

PART 5

CONTRACTOR SPECIFIC TASKS

5. SPECIFIC TASKS:

• Pre-Installation Site Survey: Verify exact floor space, overhead clearance, and slab load limits directly adjacent to designated fabrication machinery (e.g., lasers, shears, or turret punches) before shipping.

• Delivery & Offloading: Deliver all components to the facility.

• The contractor is responsible for their own rigging/forklifts

• Installation & Anchoring: Professional assembly and structural anchoring to the concrete floor slab.

• Testing & Acceptance: Conduct a dry-run test demonstrating 100% shelf extension and proper engagement of the automatic locking mechanisms under standard conditions.

• Clean-Up: Remove all crating, pallets, and debris from the work area.

PART 6

APPLICABLE PUBLICATIONS

6. APPLICABLE PUBLICATIONS (CURRENT EDITIONS)

The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures.

PART 7

TECHNICAL EXHIBITS LIST/SALIENT CHARACTERISTICS

7. TECHNICAL EXHIBITS LIST/SALIENT CHARACTERISTICS:

• The Rack Engineering Division (RED) Sheetmaster 100 (Roll-Out Heavy Duty Shelf System)is a heavy-duty, space-saving roll-out shelf storage system specifically engineered for the metal fabrication industry to store fixtures and sheet metal.

• Key Specifications & Performance

• Load Capacity 5,500 lbs. per shelf

• Shelf Extension 100% full extension on 4 roller bearings

• Standard Unit Height 84" (7 feet)

• Standard Shelf Depth Options 48", 60", 72"

• Standard Shelf Width Options 96", 120", 144"

• Shelves per Unit 3 to 8 shelves standard

• Shelf Clearance Range 5 7/8" to 15 9/32" (depending on the number of shelves)

• Standard & Ergonomic Features

• All-Welded Construction: Shelves are built with highly durable, all-welded steel to withstand harsh industrial environments

• Ergonomic T-Handles: Provides operator assistance to easily roll out heavily loaded shelves.

• Automatic Locking System: Integrated safety locks automatically secure the shelves in place when they are fully opened or completely closed

• Multi-Directional Access: Designed for highly flexible material handling; shelves can be accessed from either side or via an overhead crane

• Handling Equipment Compatibility: Engineered for seamless integration with vacuum lifts, hoists, sheet lifts, magnets, and forklifts

• Color: Safety Blue

*Lift equipment is not available

(Facility Information)

• Approximate Square Footage: 943

• Type Building: Concrete (Warehouse/Maintenance Shop)

• Ceiling Height: 20'

• Type of ceiling construction: Truss

Hangar 05 Evacuation BUILDING PLAN

Shelter In Place is Break Room Rm 107. For a Fire, the primary location is the Unaccompanied Enlisted Dorms parking lot on the corner of 5th St East/C St East, West side of Hangar 05. The alternate fire evacuation assembly point is Hangar 03 or 07 parking lots based upon direction of Fire Dept Chief. Bomb Theat: Evacuate to the primary location--Bldg. 224.

The alternate Bomb evacuation assembly point is Bldg. 45.

Office/ COMM Rm

Room 108 Office/Break

Room 107

Tire Carousel

New Current

STATEMENT OF WORK (SOW) JBSA-RANDOLPH
2..DEFINITIONS AND ACRONYMS:
2.1 DEFINITIONS:
3. GOVERNMENT-FURNISHED ITEMS AND SERVICES:
4. CONTRACTOR-FURNISHED ITEMS AND SERVICES RESPONSIBILITIES:
5. SPECIFIC TASKS:
6. APPLICABLE PUBLICATIONS (CURRENT EDITIONS)
7. TECHNICAL EXHIBITS LIST/SALIENT CHARACTERISTICS: