FA301626Q0287 SOW Sheet Metal Storage Rack Attachment 3 Amend 01.pdf
PDF 249 KB Posted
- Solicitation number
- FA301626Q0287
About this file
This is a Statement of Work (SOW) for JBSA-Randolph detailing the purchase and installation of a Sheetmaster 100 Roll-Out Shelf Storage System manufactured by Rack Engineering Division. The contractor must supply, deliver, assemble, and safely anchor the system at 10900 5th East, Hangar 5, located on JBSA-Randolph, TX 78150. The system specifications include a 5,500 lbs. uniformly distributed load capacity per shelf, 100% full extension on four heavy-duty roller bearings, 84" overall height (7 feet), seven shelves at 60" deep by 144" wide, all-welded steel construction with powder-coated finish, and an automatic locking system. The facility information indicates a 943 square-foot concrete warehouse/maintenance shop with a 20-foot ceiling and truss construction.
Contractor responsibilities include conducting a pre-installation site survey to verify floor space, overhead clearance, and slab load limits; delivering and offloading all components; providing rigging and forklifts; professional assembly and structural anchoring to the concrete floor slab; conducting dry-run testing to demonstrate 100% shelf extension and proper automatic locking mechanism engagement; and removing all crating, pallets, and debris from the work area. The contractor must also provide all operations manuals and warranty paperwork to 502 LRS/LGRMSS. Work must be performed between 0700-1500 Central Time, Monday through Friday, excluding federal holidays. All contractor personnel are required to in-process and out-process through the 502d Security Forces Squadron Visitor Control Center to receive base passes. The contractor must provide a designated point of contact with full authority to act on all contract matters and must maintain workforce stability and continuity. No security clearance is required, though physical security protocols and installation access procedures apply.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK (SOW)
JBSA-RANDOLPH
PURCHASE AND INSTALLATION OF SHEETMETAL RACK
PART 1
GENERALINFORMATION
1.0 Scope: The contractor shall supply, deliver, assemble, and safely anchor the Sheetmaster 100 Roll-Out
Shelf Storage System (manufactured by Rack Engineering Division) at the designated facility. The goal of this acquisition is to optimize vertical space in redesign of new warehouse.
1.1 Equipment Specifications & Requirements
The system delivered must meet or exceed the following technical thresholds:
Parameter: Performance & Physical Requirements
System Identity: Sheetmaster 100 (Roll-Out Heavy Duty Shelf System)
Load Capacity: 5,500 lbs. uniformly distributed load per shelf
Extension Rate: 100% full extension on 4 heavy-duty roller bearings
Standard Dimensions: 84" overall height (7 feet); Standard shelf width and depth listed in Salient
Characteristics
Shelf Configuration:7 Shelves 60" Deep x 144" Wide
Material Construction: All-welded steel construction with a powder-coated finish
Safety Features: Automatic locking system securing shelves at 100% open or closed
1.2 General Information
1.2.1 Recognized Holidays: Contractor is not required to perform services on holidays.
New Year’s Day Labor Day
Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day
Memorial Day
Juneteenth Thanksgiving Day
Independence Day Christmas Day
1.2.2 Hours of Operation: The Contractor is responsible for conducting business, between the hours of
0700 – 1500 (7:00 a.m. to 3:00 p.m.) Central Time, Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar
Government directed facility closings. The Contractor must, at all times, maintain an adequate workforce for the uninterrupted performance of all tasks defined within this SOW when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.
1.2.3 Place of Performance: The work to be performed under this contract will be performed at 10900
5th East, Hangar 5, located on JBSA-Randolph, TX 78150.
1.2.4 Security Requirements: Contractor personnel performing work under this contract are not required to have a security clearance for this contract.
1.2.4.1 Physical Security: The Contractor shall be responsible for safeguarding all Government equipment, information, and property provided for Contractor use. At the close of each work period, Government facilities, equipment, and materials shall be secured.
1.2.4.2 Installation Access: Some travel on and off JBSA installations will be limited at times due to
JBSA-controlled gate openings and closures. Unscheduled gate closures may occur at any time, and the personnel entering or exiting the installation may experience some delays. If the Contractor is denied entry to the base due to enhanced security, Contractor personnel should immediately contact the base sponsor
(502 LRS point of contact). Privately-owned vehicles of Contractor personnel are subject to being
FA301626Q0287
Attachment 3
Amend 01 searched pursuant to applicable regulations. The award of this contract does not create a right to have access to any military installation. Any violation of an installation regulation or of a state or federal statute may result in the termination of the privilege to enter any JBSA installation.
1.2.4.3 Installation In/Out Processing. All Contractor personnel performing services under this contract shall be required to in-process and out-process through the 502d Security Forces Squadron Visitor Control
Center to receive or return base passes.
1.2.5 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office if requested by the
Contracting Officer or customer POC TBD. The Contracting Officer, Customer POC TBD, and other
Government personnel, as appropriate, may meet as necessary with the Contractor to review the
Contractor's performance. Either the Government or the Contractor may request a meeting. At these meetings, the Contracting Officer will apprise the Contractor of how the Government views the
Contractor's performance and the Contractor shall apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.
1.2.6 Contractor POC: The Contractor shall provide a POC to be responsible for the performance of work under this contract. The POC shall act for the contractor and shall be designated, in writing, to the
Contracting Officer. The POC shall have full authority to act for the Contractor on all contract matters relating to any issues that may arise during work performance. The POC shall be available from 0700 –
1500 (7:00 a.m. to 3:00 p.m.) Central Time, Monday thru Friday except Federal holidays or when the
Government facility is closed for administrative reasons.
1.2.7 Identification of Contractor Employees: All contract personnel working in situations where their
Contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. They must also ensure that all documents or reports produced by Contractors are suitably marked as Contractor products or that Contractor participation in meetings is appropriately disclosed.
PART 2
DEFINITIONS & ACRONYMS
2.. DEFINITIONS AND ACRONYMS:
2.1 DEFINITIONS:
2.1.1 CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the Government. The term used in this contract refers to the prime.
2.1.2 CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the Government.
2.1.3 DELIVERABLE. Anything that can be physically delivered but may include non-manufactured things such as meeting minutes or reports.
2.1.4 PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.
2.1.5 POINTS OF CONTACT (CONTRACTOR). Those individuals identified, in writing by the
Contractor, with authority to act on behalf of the Contractor with regard to this contract.
2.1.6 SUBCONTRACTOR. One that enters into a contract with a prime Contractor. The Government does not have privity of contract with the subcontractor.
2.1.7 ACRONYMS:
FAR Federal Acquisition Regulation OCI Organizational Conflict of Interest
POC Point of Contact
SOW Statement of Work
TE Technical Exhibit
PART 3
GOVERNMENT-FURNISHED ITEMS AND SERVICES
3. GOVERNMENT-FURNISHED ITEMS AND SERVICES:
3.1 Services: The Government will not provide any property, equipment, or services in support of this contract.
3.2 Facilities: The Government will provide temporary storage space for materials while work is being accomplished.
3.3 Utilities: The Government will provide all utilities in the facility for the contractor’s use in performance of tasks outlined in this SOW. The Contractor shall instruct employees in utilities conservation practices.
3.4 Equipment: The Government will not provide any property, equipment, or services in support of this contract.
3.5 Materials: The Government will not provide any property, equipment, or services in support of this contract.
PART 4
CONTRACTOR-FURNISHED ITEMS AND SERVICES
4. CONTRACTOR-FURNISHED ITEMS AND RESPONSIBILITIES:
4.1 General: The Contractor shall furnish all personnel, supplies, equipment, facilities, transportation, tools, materials, and supervision required to meet the requirements of this SOW.
4.2 Materials/Equipment:
4.2.1 The Contractor shall furnish materials, supplies, and equipment necessary to meet the requirements under this SOW.
4.2.2 The Contractor shall provide and install one Sheetmaster 100 Roll-Out Shelf Storage
System (manufactured by Rack Engineering Division) at the designated facility. The goal of this acquisition is to optimize vertical space in new redesign
4.2.3 The Contractor shall provide all operations manuals and warranty paperwork with 502
LRS/LGRMSS
PART 5
SPECIFIC TASKS
5. SPECIFIC TASKS:
• After award, before shipment a pre-installation site survey should be complete. Pre-Installation Site Survey: Verify exact floor space, overhead clearance, and slab load limits directly adjacent to designated fabrication machinery (e.g., lasers, shears, or turret punches) before shipping.
• Delivery & Offloading: Deliver all components to the facility.
• The contractor is responsible for their own rigging/forklifts
• Installation & Anchoring: Professional assembly and structural anchoring to the concrete floor slab.
• Testing & Acceptance: Conduct a dry-run test demonstrating 100% shelf extension and proper engagement of the automatic locking mechanisms under standard conditions.
• Clean-Up: Remove all crating, pallets, and debris from the work area.
PART 6
APPLICABLE PUBLICATIONS
6. APPLICABLE PUBLICATIONS (CURRENT EDITIONS)
6.1 The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures.
PART 7
ATTACHMENTS/TECHNICAL EXHIBITS LISTING
1. ATTACHMENTS/TECHNICAL EXHIBITS LIST:
TECHNICAL EXHIBIT
ATTACHMENT 1
SALIENT CHARACTERISTICS
Sheetmaster 100 (Roll-Out Heavy Duty Shelf System)
Salient Characteristics
The Rack Engineering Division (RED) Sheetmaster 100 is a heavy-duty, space-saving roll-out shelf storage system specifically engineered for the metal fabrication industry to store fixtures and sheet metal
Key Specifications & Performance
• Parameter Standard Specification
• Load Capacity 5,500 lbs. per shelf
• Shelf Extension 100% full extension on 4 roller bearings
• Unit Height: 84" (7 feet)
• Shelf Depth: 60” x 144”
• Over All Shelf Metal Rack Dimensions: OAH 84", OAW 159", OAD 129.5"
• Shelves per Unit: 7 Shelves
• Shelf Clearance Range: 7 3/16"
• Standard & Ergonomic Features
• All-Welded Construction: Shelves are built with highly durable, all-welded steel to withstand harsh industrial environments
• Ergonomic T-Handles: Provides operator assistance to easily roll out heavily loaded shelves.
• Automatic Locking System: Integrated safety locks automatically secure the shelves in place when they are fully opened or completely closed
• Multi-Directional Access: Designed for highly flexible material handling; shelves can be accessed from either side or via an overhead crane
• Handling Equipment Compatibility: Engineered for seamless integration with vacuum lifts, hoists, sheet lifts, magnets, and forklifts
• Color: Safety Blue
*Lift equipment is not available
(Facility Information)
• Approximate Square Footage: 943
• Type Building: Concrete (Warehouse/Maintenance Shop)
• Ceiling Height: 20'
• Type of ceiling construction: Truss