Q and A 4-5.pdf

PDF 138 KB Posted

Attached to
Amendment - ADA Shower and Restroom Trailers
Solicitation number
FA301620U0216
Issued by

View the file

Other files

File Type Posted
Q and A 6-11.pdf PDF
Q and A 12-16.pdf PDF
Attachment 1_Statement of Work - Addendum 1.pdf PDF
Q and A 1-3.pdf PDF
RFQ.pdf PDF
Attachment 3_Placement Overhead View.pdf PDF
Q and A Sheet.docx DOCX document
Attachment 1_Statement of Work_7 August 2020_2 pages.pdf PDF
Attachment 2_ADA Technical Specifications_1 page.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

502 CONS/JBKAE FA301620U0216

JBSA Lackland, TX 78236 Shower Trailers

QUESTIONS & ANSWERS

Cut-off date for contractor questions is: 12:00 PM CST, 14 August 2020.

Questions

Question 4: Does the contractor designated POC need to be available to be on site physically during all hours of operation? Or does that person need to be available by phone/email/text etc., with the ability to get on site if need be?

Government Response: Yes, the contractor is responsible for all work on site. Yes, the government will communicate by all electronic means.

Question 5: What is the expected term length of the contract?

Government Response: The terms are based on each suppliers availability of delivery and reasonable lead time.