Q and A 4-5.pdf
PDF 138 KB Posted
- Attached to
- Amendment - ADA Shower and Restroom Trailers Federal contract opportunity
- Solicitation number
- FA301620U0216
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Q and A 6-11.pdf | ||
| Q and A 12-16.pdf | ||
| Attachment 1_Statement of Work - Addendum 1.pdf | ||
| Q and A 1-3.pdf | ||
| Attachment 1_Statement of Work_7 August 2020_2 pages.pdf | ||
| RFQ.pdf | ||
| Attachment 3_Placement Overhead View.pdf | ||
| Attachment 2_ADA Technical Specifications_1 page.pdf | ||
| Q and A Sheet.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
502 CONS/JBKAE FA301620U0216
JBSA Lackland, TX 78236 Shower Trailers
QUESTIONS & ANSWERS
Cut-off date for contractor questions is: 12:00 PM CST, 14 August 2020.
Questions
Question 4: Does the contractor designated POC need to be available to be on site physically during all hours of operation? Or does that person need to be available by phone/email/text etc., with the ability to get on site if need be?
Government Response: Yes, the contractor is responsible for all work on site. Yes, the government will communicate by all electronic means.
Question 5: What is the expected term length of the contract?
Government Response: The terms are based on each suppliers availability of delivery and reasonable lead time.