This document provides clarification regarding the fire alarm system requirements for the federal contract opportunity Renovate B412 for DCSA Phase 2. The existing EST 3 fire alarm panel will remain in place and continue to be supported with repair parts for the next five years. While the EST 3 panel will no longer be sold after December 2023, replacement parts will still be available. Additionally, all existing fire alarm devices are to be reused and relocated as required by the scope of work, specifications and drawings, and it is not necessary to replace all speaker strobes and mass notification system devices with new ones if the existing devices meet NFPA 101 compliance standards resulting from the floor reconfiguration. Textual signs are not required.

View the file

Other files

File Type Posted
Solicitation Amendment FA301023R00400002 SF 30.pdf PDF
Solicitation Amendment - FA301023R00400002.pdf PDF
Solicitation Amendment FA301023R00400001 SF 30.pdf PDF
Attachment 15 - MAHG21-1099 Reno B412 DCSA Phase 2 Questions and Answers.pdf PDF
Solicitation Amendment - FA301023R00400001.pdf PDF
FA301023R0040 Pre-Bid Site Visit Sign-in.pdf PDF
Mechanical Room Photos.pdf PDF
Attachment 1 - Renovate B412 DCSA Phase 2 SOW 8.10.2023.pdf PDF
Attachment 7 - Appendix C MECH RM - DUCT INSTALL.pdf PDF
Attachment 8 - MAHG 211099 Renovate B412 DCSA Ph-2 MSS.xls XLS spreadsheet
Attachment 10 - Manufacturer Carpet and Adhesive Pricing Sheet.pdf PDF
Attachment 11 - Past Performance Questionnaire.pdf PDF
Attachment 12 - Past Performance Reference List.pdf PDF
Solicitation - FA301023R0040.pdf PDF
Attachment 5 - Appendix A AIR BALANCE DIAGRAM.pdf PDF
Attachment 6 - Appendix B MECH RM - DUCT DEMO.pdf PDF
Attachment 13 - Wage Determination MS 20220050.pdf PDF
Attachment 14 - Submittal Procedures.pdf PDF
Attachment 2 - Renovate B412 DCSA Phase 2 Specifications 8.10.2023.pdf PDF
Attachment 3 - Renovate B412 DCSA Ph 2 Drawings 10.24.2022.pdf PDF
Attachment 4 - Keesler Guidance for Premise Wiring Jan 2023.pdf PDF
Attachment 9 - USAF Carpet Ordering Guide Jan2022.pdf PDF
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

6 September 2023 FA301023R0040

Attachment 16

FA301023R0040 Renovate B412 for DCSA Phase 2

Fire Alarm Clarification

1. Fire Alarm Panel Clarification – Currently in place at B412 is an EST 3 fire alarm panel which will remain. Although the Edwards EST 3 panel will cease production in December 2023, repair parts will be available for the next five years due to service agreements between Edwards and new customers. The EST 3 panel will not be sold after 30 December, but replacement parts will still be available.

2. Fire Alarm Devices Clarification - UFC 34-1.2.8 Does not require all the speaker strobes and MNS devices to be replaced with new ones (the ones that say alert and are clear lenses instead of amber). Since the floor reconfiguration is bringing the building more into compliance with NFPA 101 the change does not count towards a 50 percent floor area threshold. Textural Signs are not a requirement at Keesler AFB. The new MNS and speaker/strobes fall under current UFC

3-600-01. All existing devices are to be reused and relocated according to SOW, specs, and drawing.