Attachment 8 - MAHG 211099 Renovate B412 DCSA Ph-2 MSS.xls
XLS spreadsheet 77 KB Posted
- Attached to
- Renovate B412 for DCSA Phase 2
- Solicitation number
- FA301023R0040
About this file
This document is a material submittal schedule for a federal contract renovation project. The schedule lists 90 line items for products and services required for the Renovate B412 for DCSA Phase 2 project solicited by the Department of the Air Force Air Education and Training Command. Submittals are due within 10 days of award for items including carpentry, architectural woodwork, flooring, lighting, HVAC, electrical systems, fire alarm, and telecommunications work. The schedule includes columns for the contractor to provide dates for initial submissions, resubmittals, and final approval for each line item. Upon project completion, the contractor must submit operation and maintenance manuals along with as-built documentation.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedule
| Project Number: | |||
| MAHG211099 | Project Title: | ||
| Renovation B412 for DCSA | Solicitation / Contract Number: |
Attachment 8 / FA301023R0040
| Line Number | (To be completed by Project Engineer) | (To be completed by Contract Administrator) | ||||||||||||||||||||
| Number of Copies Required (if not electronically submitted) | Remarks | |||||||||||||||||||||
| Item or Description of Item, Contract Reference, Type of Submittal | Certificate of Compliance | Shop Drawings | Samples | Color Selection | Manufacturer's Recommendation | Warranty-Manufacturer and/or Workmanship | Catalog Data | Operating Instructions | Schedules, Listings, Reports, Plans | Technical Data | Test Reports | Field Reports | Required Submission Date | Date Received in Contracting | Date to Civil Engineering | Return Suspense Date | Submittal Numbers | Date Contractor | ||||
| Notified | Contractor Resubmittal | Final Approval | ||||||||||||||||||||
| Approved | Disapproved | |||||||||||||||||||||
| 1 | 1 | |||||||||||||||||||||
| 2 | 06 20 00 Finish Carpentry | 1 | 10 Days after Issuance of Award | |||||||||||||||||||
| 3 | 06 40 20 Interior Architectural Woodwork - Cabinet Hardware | 1 | 1 | 1 | 10 Days after Issuance of Award | |||||||||||||||||
| 4 | 06 40 20 Interior Architectural Woodwork - Millwork | 1 | 1 | 10 Days after Issuance of Award | ||||||||||||||||||
| 5 | 06 65 00 Solid Surface Fabrications | 1 | 1 | 1 | 1 | 1 | 10 Days after Issuance of Award | |||||||||||||||
| 6 | 07 20 00 Insulation | 1 | 1 | 10 Days after Issuance of Award | ||||||||||||||||||
| 7 | 07 92 00 Joint Sealants | 1 | 1 | 1 | 1 | 10 Days after Issuance of Award | ||||||||||||||||
| 8 | 08 10 10 Steel Doors and Frames | 1 | 1 | 10 Days after Issuance of Award | ||||||||||||||||||
| 9 | 08 20 00 Wood Doors | 1 | 1 | 10 Days after Issuance of Award | ||||||||||||||||||
| 10 | 08 41 13 Aluminun Frames, Entrances and Storefronts | 1 | 1 | 1 | 1 | 10 Days after Issuance of Award | ||||||||||||||||
| 11 | 08 71 00 Door Hardware | 1 | 1 | 1 | 10 Days after Issuance of Award | |||||||||||||||||
| 12 | 08 72 00 Thresholds | 1 | 1 | 10 Days after Issuance of Award | ||||||||||||||||||
| 13 | 08 80 00 Glaziing | 1 | 1 | 10 Days after Issuance of Award | ||||||||||||||||||
| 14 | 09 22 16 Non-structural Metal Framing | 1 | 1 | 10 Days after Issuance of Award | ||||||||||||||||||
| 15 | 09 25 00 Gypsum Board | 1 | 1 | 10 Days after Issuance of Award | ||||||||||||||||||
| 16 | 09 51 00 Acoustical Panel Ceilings | 1 | 1 | 1 | 1 | 10 Days after Issuance of Award | ||||||||||||||||
| 17 | 09 65 00 Resilient and LVT Flooring | 1 | 1 | 1 | 1 | 10 Days after Issuance of Award | ||||||||||||||||
| 18 | 09 65 13 Rubber Wall Base | 1 | 1 | 1 | 1 | 10 Days after Issuance of Award | ||||||||||||||||
| 19 | 09 65 50 Resilient Accessories | 1 | 1 | 1 | 10 Days after Issuance of Award | |||||||||||||||||
| 20 | 09 68 13 Tile Carpeting | 1 | 1 | 1 | 1 | 10 Days after Issuance of Award | ||||||||||||||||
| 21 | 09 91 00 Paiint | 1 | 1 | 1 | 10 Days after Issuance of Award | |||||||||||||||||
| 22 | 09 93 23 Stains and Transparent Finishes | 1 | 1 | 1 | 10 Days after Issuance of Award | |||||||||||||||||
| 23 | 22 00 00 Plumbing and Piping | 1 | 10 Days after Issuance of Award | |||||||||||||||||||
| 24 | 22 00 00 Plumbing and Piping - Kitchen Sink | 1 | 1 | 1 | 10 Days after Issuance of Award | |||||||||||||||||
| 25 | 22 00 00 Plumbing and Piping - Dringing/Water Coolers | 1 | 1 | 10 Days after Issuance of Award | ||||||||||||||||||
| 26 | 22 00 00 - Plumbing and Piping - Water Heaters | 1 | 1 | 10 Days after Issuance of Award | ||||||||||||||||||
| 27 | 23 30 00 HVAC Air Distribution - Insulated Metal Flexible Duct | 1 | 1 | 1 | 1 | 1 | 10 Days after Issuance of Award | |||||||||||||||
| 28 | 23 30 00 HVAC Air Distribution - Rect. Metal Duct | 1 | 1 | 1 | 1 | 10 Days after Issuance of Award | ||||||||||||||||
| 29 | 23 30 00 HVAC Air Distribution - Rect. Metal Duct Fittings |
Splitter Tees, Vaned Elbows,
| Transitions to Terminals | 1 | 1 | 1 | 1 | 10 Days after Issuance of Award | ||||||||||
| 30 | 23 30 00 HVAC Air Distribution - Duct Insulation | 1 | 1 | 1 | 1 | 10 Days after Issuance of Award | |||||||||
| 31 | 23 30 00 HVAC Air Distribution - Duct Connectors | 1 | 1 | 1 | 1 | 10 Days after Issuance of Award | |||||||||
| 32 | 23 30 00 HVAC Air Distribution - Duct Access Doors | 1 | 1 | 1 | 1 | 10 Days after Issuance of Award | |||||||||
| 33 | 23 30 00 HVAC Air Distribution - Dampers | 1 | 1 | 1 | 1 | 10 Days after Issuance of Award | |||||||||
| 34 | 23 30 00 HVAC Air Distribution - Diffuers | 1 | 1 | 1 | 1 | 10 Days after Issuance of Award | |||||||||
| 35 | 23 30 00 HVAC Air Distribution - Registers and Grilles | 1 | 1 | 1 | 1 | 10 Days after Issuance of Award | |||||||||
| 36 | 23 30 00 HVAC Air Distribution - | 1 | 1 | 1 | 10 Days after Issuance of Award | ||||||||||
| 37 | 23 30 00 HVAC Air DistributionThermostat, Temp Controller, | ||||||||||||||
| AHU1 Temp Input | 1 | 1 | 1 | 10 Days after Issuance of Award | |||||||||||
| 38 | 23 30 00 HVAC Air Distribution - HVAC TAB REPORT | 1 | 1 | 1 | 1 | 1 | 3 Days after test | ||||||||
| 23 82 10.00 Fan Coil Units - SD-03 Product Data | 1 | 1 | 1 | 1 | 10 Days after Issuance of Award | ||||||||||
| 39 | 26 05 00.00 40 Common Work results for Electrical - Conduits and Raceways | 1 | 10 Days after Issuance of Award | ||||||||||||
| 40 | 26 05 00.00 40 Common Work results for Electrical - Wire and Cable | 1 | 10 Days after Issuance of Award | ||||||||||||
| 41 | 26 05 00.00 40 Common Work results for Electrical - Splices and Connectors | 1 | 10 Days after Issuance of Award | ||||||||||||
| 42 | 26 05 00.00 40 Common Work results for Electrical - Receptacles | 1 | 10 Days after Issuance of Award | ||||||||||||
| 43 | 26 05 00.00 40 Common Work results for Electrical - Outlet Boxes, Pull Boxes and Junction Boxes | 1 | 10 Days after Issuance of Award | ||||||||||||
| 44 | 26 05 00.00 40 Common Work results for Electrical - Circuit Breakers | 1 | 10 Days after Issuance of Award | ||||||||||||
| 45 | 26 05 00.00 40 Common Work results for Electrical - Device Plates | 1 | 10 Days after Issuance of Award | ||||||||||||
| 46 | 26 05 00.00 40 Common Work results for Electrical - Wall Switches and Devices | 1 | 10 Days after Issuance of Award | ||||||||||||
| 47 | 26 05 00.00 40 Common Work results for Electrical - Continuity Test | 1 | 3 Days After Test | ||||||||||||
| 48 | 26 05 00.00 40 Common Work results for Electrical - Insulation Resistance Test | 1 | 3 Days After Test | ||||||||||||
| 49 | 26 05 00.00 40 Common Work results for Electrical - Ground-Fault Receptacle Test | 1 | 3 Days After Test | ||||||||||||
| 50 | 26 51 00 Interior Lighting - Photometric Plan | 1 | 10 Days after Issuance of Award | ||||||||||||
| 51 | 26 51 00 Interior Lighting -Luminaires | 1 | 1 | 10 Days after Issuance of Award | |||||||||||
| 52 | 26 51 00 Interior Lighting -Occupancy/Vacancy Sensors | 1 | 1 | 1 | 10 Days after Issuance of Award | ||||||||||
| 53 | 26 51 00 Interior Lighting -Sequence of Operation for Lighting Controls | 1 | 10 Days after Issuance of Award | ||||||||||||
| 54 | 26 51 00 Interior Lighting -Light Sources | 1 | 10 Days after Issuance of Award | ||||||||||||
| 55 | 26 51 00 Interior Lighting -LED Drivers | 1 | 1 | 10 Days after Issuance of Award | |||||||||||
| 56 | 26 51 00 Interior Lighting -Switches | 1 | 10 Days after Issuance of Award | ||||||||||||
| 57 | 26 51 00 Interior Lighting -Photo Sensors | 1 | 1 | 1 | 10 Days after Issuance of Award | ||||||||||
| 58 | 26 51 00 Interior Lighting -Power Packs | 1 | 10 Days after Issuance of Award | ||||||||||||
| 59 | 26 51 00 Interior Lighting -Exit Signs | 1 | 10 Days after Issuance of Award | ||||||||||||
| 60 | 26 51 00 Interior Lighting -Emergency Drivers | 1 | 1 | 10 Days after Issuance of Award | |||||||||||
| 61 | 26 51 00 Interior Lighting -Local Area Controller | 1 | 10 Days after Issuance of Award | ||||||||||||
| 62 | 26 51 00 Interior Lighting -Wall Box Dimmer | 1 | 10 Days after Issuance of Award | ||||||||||||
| 63 | 27 10 00 Building Telecommunications Cabling System - Telecommunication Drawings | 1 | Project Completion | ||||||||||||
| 64 | 27 10 00 Building Telecommunications Cabling System -Telecommunication Cabling | 1 | 1 | 1 | 10 Days after Issuance of Award | ||||||||||
| 65 | 27 10 00 Building Telecommunications Cabling System -Telecommunication Outlet / Connector Assembly | 1 | 10 Days after Issuance of Award | ||||||||||||
| 66 | 27 10 00 Building Telecommunications Cabling System -Telecommunication Contractor Qualifications | 1 | 10 Days after Issuance of Award | ||||||||||||
| 67 | 27 10 00 Building Telecommunications Cabling System -Telecommunication As-Builts | 1 | Project Completion | ||||||||||||
| 68 | 28 31 76 Interior Fire Alarm and Mass Notification System Addressable - QFPE | 1 | 10 Days after Issuance of Award | ||||||||||||
| 69 | 28 31 76 Interior Fire Alarm and Mass Notification System Addressable -Fire Alarm Personnel | 1 | 10 Days after Issuance of Award | ||||||||||||
| 70 | Fire Alarm Instructions | 1 | 10 Days after Issuance of Award | ||||||||||||
| 71 | Wiring Diagrams | 1 | 10 Days after Issuance of Award | ||||||||||||
| 72 | 28 31 76 Interior Fire Alarm and Mass Notification System Addressable -System Layout | 1 | 10 Days after Issuance of Award | ||||||||||||
| 73 | 28 31 76 Interior Fire Alarm and Mass Notification System Addressable -Notification Appliances | 1 | 1 | 10 Days after Issuance of Award | |||||||||||
| 74 | 28 31 76 Interior Fire Alarm and Mass Notification System Addressable -Initiating Devices | 1 | 10 Days after Issuance of Award | ||||||||||||
| 75 | 28 31 76 Interior Fire Alarm and Mass Notification System Addressable -Voltage Drop Calculations | 1 | 10 Days after Issuance of Award | ||||||||||||
| 76 | 28 31 76 Interior Fire Alarm and Mass Notification System Addressable -Manual Stations | 1 | 10 Days after Issuance of Award | ||||||||||||
| 77 | 28 31 76 Interior Fire Alarm and Mass Notification System Addressable -Smoke Detectors | 1 | 10 Days after Issuance of Award | ||||||||||||
| 78 | 28 31 76 Interior Fire Alarm and Mass Notification System Addressable -Addressable Interface Devices | 1 | 10 Days after Issuance of Award | ||||||||||||
| 79 | 28 31 76 Interior Fire Alarm and Mass Notification System Addressable -Isolation Modules | 1 | 10 Days after Issuance of Award | ||||||||||||
| 80 | 28 31 76 Interior Fire Alarm and Mass Notification System Addressable -Back Boxes and Conduit | 1 | 10 Days after Issuance of Award | ||||||||||||
| 81 | 28 31 76 Interior Fire Alarm and Mass Notification System Addressable -Ceiling Bridges | 1 | 10 Days after Issuance of Award | ||||||||||||
| 82 | 28 31 76 Interior Fire Alarm and Mass Notification System Addressable -Document Storage Cabinet | 1 | 10 Days after Issuance of Award | ||||||||||||
| 83 | 28 31 76 Interior Fire Alarm and Mass Notification System Addressable -Duct Smoke Detectors | 1 | 10 Days after Issuance of Award | ||||||||||||
| 84 | 28 31 76 Interior Fire Alarm and Mass Notification System Addressable -Addressable Control Modules | 1 | 10 Days after Issuance of Award | ||||||||||||
| 85 | 28 31 76 Interior Fire Alarm and Mass Notification System Addressable -Batteries | 1 | 10 Days after Issuance of Award | ||||||||||||
| 86 | 28 31 76 Interior Fire Alarm and Mass Notification System Addressable -Battery Chargers | 1 | 10 Days after Issuance of Award | ||||||||||||
| 87 | 28 31 76 Interior Fire Alarm and Mass Notification System Addressable -Test Procedures | 1 | 1 | 10 Days after Issuance of Award | |||||||||||
| 88 | 28 31 76 Interior Fire Alarm and Mass Notification System Addressable -Verification of Compliant Installation | 1 | 1 | 10 Days after Issuance of Award | |||||||||||
| 89 | 28 31 76 Interior Fire Alarm and Mass Notification System Addressable -Fire Alarm As Builts | 1 | Project Completion | ||||||||||||
| 90 | O and M Manuals | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | Project Completion | Provide 2 sets of bound hard copies and 2 cd/DVD's |
&L&"Verdana,Bold"&12Schedule of Material Submittals&C&12Print on Legal size paper ( 8 x 14 ).
&R&P of &N Enter the due date from the Contractor (MM/DD/YY) Enter the date received from the Contractor. (MM/DD/YY) Enter the date submittal was given to CE for review. (MM/DD/YY) Enter the date the submittal is due back from CE
(MM/DD/YY)
Enter the Submittal Number Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
Enter Resubmittal Number Enter the submittal final approval date
(MM/DD/YY)