QUESTIONS AND ANSWERS
25 KB Posted
- Attached to
- Air Combat Training System (ACTS)
- Solicitation number
- FA3002-10-R-0009
Text of this file
QUESTIONS AND ANSWERS (Round 2)
1. Is personal PPE (Safety shoes, Prescription safety glasses, personal hearing protection, etc.) reimbursable under the contract? No
2. Are fuel costs for vehicles and watercraft reimbursable under the contract? Fuel cost is also covered in the lease fee and the per mile cost and is reimbursed by the government.
3. Regarding the PWS, Para 2.4: Are all non-labor costs associated with the helicopter support reimbursable to the contractor? Helicopter support costs are the sole responsibility of the contractor for maintenance unless the travel is government directed.
4. Appendix 7 to Attachment 1 Reports, Plans and Appointment requires seven (7) plans [Plan 1: Quality Control Plan, Plan 2: Phase-In Plan, Plan 5: Transportation Plan, Plan 7: Security Program Plan, Plan 8: Environmental Management Plan, Plan 9: Configuration Management Plan, And Plan 10: Strike Plan] to be submitted “Initial plan due NLT 60 days prior to contract start” This is 30 days before the Phase-in is scheduled to begin and is at approximately the planned award announcement date. This is highly unrealistic since to develop effective plans the contractor need to be on-site and have access to all contract documentation, manuals and policies. Recommend that the initial due date be after phase in begins and with sufficient time to review all ACTS documentation. Detailed description of the Quality Control Plan and Phase-In Plan are a part of the Technical Proposal submission requirements that will be evaluated on a pass or fail basis. The PWS para 1.2.2.1. states, “The contractor shall establish, implement, adhere to, and update a QC Plan and submit to the Contracting Officer for Government acceptance prior to contract award.” and para 1.2.4.5. states, “The successor contractor shall develop and submit a phase-in plan to the CO thirty (30) days prior to contract start (day one of phase-in).” Because the QCP and Phase-In Plan will be reviewed and evaluated during the pre-award phase, “initial plan due NLT 60 days” requirement will be automatically met. Considering the final QCP and Phase-In Plan will be based on the Govt’s previous acceptance during the source selection phase, submitting them 30 days prior to contract start date as stated in the PWS is deemed reasonable, therefore, no change will be made.
However, Transportation Plan, Security Program Plan, Environmental Management Plan, Configuration Management Plan and Strike Plan can be submitted during the phase-in period and Appendix 7 will be revised accordingly.
5. Appendix 7 to Attachment 1 Reports, Plans and Appointment requires two appointments to be submitted in conjunction with the start of Phase In. [Appointment 1: Site Managers And Alternates And Appointment 2: COMSEC Manager And Alternate] This would require two individual be hired by the new contractor prior to start of Phase-in so all HR and Security clearance paperwork can be processed. Recommend that the date for submittal for these two be changed to 15 days prior to CSD as the requirement for the other required appointment letters listed in Appendix 7.
The submission of Site Managers/Alternates and COMSEC Manager/Alternates 15 days before the contract start day is acceptable and Appendix 7 will be amended accordingly.
6. GSA Vehicles:
a. Who is responsible for Operation and Maintenance costs of contractor leased GSA vehicles? It is included in the lease fee and the per mile cost.
b. Does the customer provide for vehicle fuel? How is it paid for? No, fuel cost is also covered in the lease fee and the per mile cost.
7. PWS 2.2.2.1.1 ROCC Hours of Operation:
a. Understand that the ROCC hours of operation will be within the 0700-2300 (0730-2330 winter) timeframe. Does this mean that the ROCC will be manned during this entire time? Or does the ROCC only need to be manned during the scheduled Luke AFB 12 hr flight window? No, the range will be manned in accordance with the daily range flying schedule.
b. Will other non-Luke AFB units be using ROCC controlled airspace outside of the Luke AFB scheduled flight window? If so, will the contractor be required to man the ROCC to support this activity? No, all user’s of the range will be on the daily Range flying schedule.
8. PWS 2.2.2.2.1 RCO: Clarify contractor RCO duty day period. Is it the daily Luke AFB 12 hr flight schedule? Or is it during the entire published airspace window of 0700-2300? RCO duty day will be determined by the daily Range flying schedule.
9. PWS 2.3.5 and 3.4.4 LINK 16: Are the LINK 16 systems at Luke and Tyndall AFBs fielded and fully functional? LINK 16 systems at both sites are fully functional.
10. Luke AFB Range Control Officer: How much time does it nominally take to drive from Gila Bend to each of the four conventional ranges? Range 1 50min, Range 2 40min Range 3 20min Range 4 45min.
11. ACMI Debriefs
a. How many simultaneous ACMI debriefs are to be supported at Tyndall and Eglin AFBs? There are no debriefs contracted for Eglin. Tyndall can support 10 simultaneous debriefings.
b. How many simultaneous ACMI debriefs are to be supported at Luke AFB? Luke, has the ability to debrief 9 simultaneous debriefs.
12. PWS Amended Appendix 4 (GFP), pg. 13
a. The list indicated only two (2) P4G AIS pods. Is this correct? Appendix 4 was corrected/updated again on 24 May 10 and was posted on FBO with Amendment 002 on 26 May 2010.
b. Is there any work at Luke, Gila Bend or Tyndall that requires the worker (company employee) to posses any kind of Commercial Drivers License (CDL)? Is so, state what that work is and what type of CDL and endorsements is required. A CDL is required for Luke. The contractor will be required to transport high explosives (Smoky Sams). No such requirement exists at Tyndall.
13. PWS 2.2.2.2.1.4.2.6 Strafe Pit Maintenance:
a. To what extent is the contractor responsible for strafe pit inspection, maintenance and clean-up? The PWS mentions several tasks but the GFP does not list any of the equipment needed to perform some of the tasks, such as “Contractor personnel shall ensure strafe pits have a minimum of 12” depth of loose, sandy soil and are surface-cleared of all spent projectiles, all rocks three inches in diameter or larger, and any other hazardous debris. The RCO shall inspect the impact area(s) immediately after hand-policing and before the first mission each day to ensure compliance. The RCO’s responsibility as directed in the PWS is “minor” maintenance, and inspection of pits for determination of a safe range. The RCO will utilize a T-bar device located at each range to check pits for 12” depth of sand, if it is determined that the required 12” of sand is not there, the RCO will call job control to open a job with the GB O&M contractor for the actual intensive maintenance (filling of sand, etc.) needed on the pit.
b. A tractor with a 24-inch disk is the usual tool used to perform some of these tasks. This would indicate major maintenance and as directed in the PWS is not required by the RCO, this duty falls under the GB O&M contractor.
14. AFI 13-212 Luke Sup1: The Luke AFB supplement to AFI 13-212 is not listed on the AF Publication web site. Can the supplement be provided as a PDF to all ACTS contract bidders? Currently we are having a technical difficulty downloading AFI 13-212 Luke Sup 1. As soon as the system comes back, it will be posted on FedBizOpps.
15. Reference: 3.1.1. GOALS AND OBJECTIVES: Operation and Maintenance (O&M) of all ACTS equipment and associated systems; (2) ACTS Range radio control and coordination; (3) Deployed unit operations hosting (in support of 325 FW); (4) ACTS aircraft pod loading and maintenance; (5) Remote debrief station operation and maintenance; (6) ACTS watercraft operations for ocean tower requirements, Search and Rescue (SAR) operations and water survival training as required; (7) O&M of ACTS facilities at Tyndall, communication/watercraft site at Carrabelle, six ocean towers and four land towers; (8) Coordinate exercises to provide the customer with a realistic training environment; and (9) support range and equipment research, testing & development.
Please clarify what specifically is the contractor requirements for Search and Rescue (SAR) operations and water survival training as required, the insurance underwriters require this information for insurance quotes since it involves watercraft and on water operations. 325 OG/OI 10-1 is provided (the last page of this Q&A). The ACMI contractor will deploy the 34’ Fast Response boat (Warlock) or the 65’ work boat (Jukebox) in response to a Search and Rescue requirement. Conditions permitting the Warlock is preferred. A recovery basket and/or horse collar is available for use with the crane on either boat. There is a First Aid kit on each boat. The rescued person(s) will be transported to the nearest port to meet emergency transport.
Also Appendix 6 did not have any work load data or frequency of occurrences for Search and Rescue (SAR) operations and water survival training as required. There have been two SAR incidents in the last 8 years. There are 3-4 aircrew training sessions each spring/summer, approx 2-3 hrs long. Training includes pulling aircrew behind the boat and recovery utilizing the basket or horse collar.
16. Unmanned Threat Emitter (UMTE): What is the five-year projected Depot level maintenance schedule for the four UMTEs? At present, the Depot has no “5 yr maintenance plan” due to lack of funds/resources, and there appears to be no change in this situation for the foreseeable future. As this is a Govt function, the Contractor’s involvement will not be different than normal duties performed in association with UMTE, and financially the Government will fund the depot level maintenance.
17. LESM
a. During the 17 May Luke AFB site visit there was mention of a laser scoring system called “LESM”. There is no reference to this system in the PWS nor is it in Appendix 1 Definitions and Ancronyms. Will this be changed? LESM is in Appendix 4 pages 39 and 40.
b. Is it part of the contract? Yes.
c. What is the contractor’s specific responsibilities with regards to the LESM? Contractor is responsible for "first look" maintenance on the LESM ie: determine if LESM is faulty, ship to Navy Depot. Contractor is required to maintain the solar panel system associated with the LESM.
18. Operational Effectiveness and Equipment Availability Ratings (OER and EAR):
a. What were the past years OER and EAR for the following systems for:
i. UMTE: Oct 08-Sept 09 data: 97.195% OER
ii. ACMI (CCS/SOC/ICADS/RRU/AIS): Oct 08-Sept 09 data: 99.35% OER
iii. WISS: Oct 08-Sept 09 data: 99.99% EAR
iv. LSTSS: Oct 08-Sept 09 data: 100% EAR
v. IRSSS: Oct 08-Sept 09 data: 99.78% EAR
vi. LESM: Oct 08-Sept 09 data: 100% EAR
vii. MTS: Jan 10–Apr 10 data (system officially online to track Jan 10): 85.63% OER
viii. Communications: Oct 08-Sept 09 data: 99.58% EAR
ix. Remote power generation: not applicable, data not tracked.
19. Range maintenance demarcation points: Clarify demarcation points for range maintenance responsibilities. Who is responsible for delivering water to Ranges 1 – 4? Gila Bend O&M contractor.
20. PWS 2.2.2.2.1.4.1.1 and 2.2.2.2.1.4.2.6: Define “minor maintenance” as it relates to strafe pits? PWS paragraphs 2.2.2.2.1.4.1.1 (Strafe Pit Setup), and 2.2.2.2.1.4.1.2 (Soil Condition and Depth Testing) clearly defines the "minor" maintenance required by RCO personnel. AFI 13-212, Luke Sup 1 further identifies the maintenance required and a copy will be provided via the CO.
21. Clarify what the incumbent contractor is still responsible for and what the new ACTS contractor (RCO) is responsible for. New contractor will be responsible for those duties outlined in the PWS concerning RCO’s, effective the 1st day of contract start date (1 OCT 10).
22. Weekly and daily range schedules: Request a copy of a typical weekly and daily range and MOA schedule for Luke AFB ROCC controlled airspace and Tyndall AFB airspace.
The daily range and MOA schedule can be found at the following link, there is no “typical” week when referring to the range schedule. Bookings, changes and cancelations are so frequent/infrequent that no realistic typical document could be provided with any accuracy.
https://www.my.af.mil/afknprod/ASPs/docman/Process/ProcessDOCFunctions.asp?DocID=8512721&Function=ViewDocument&FolderID=AE-OP-00-64-2&Filter=AE-OP-00-64
23. How are or who is the deciding authority between the GB Range contractor and the ACTS contractor. For example the ACTS RCO says the strafe pits is not disced IAW 13-212 yet the GB BOSS contractor’s QAE says it is. Who will make the ruling? This is just an example. The two contracts (Gila Bend O&M, Luke ACTS) QAP’s will work together to resolve any differences and the Functional Directors can also be involved should it become necessary. Ultimate responsibility lies with each contracts Contracting Officer.
BY ORDER OF THE COMMANDER 325 OG Operating Instruction 10-1 325th OPERATIONS GROUP (AETC)
| Tyndall Air Force Base, Florida 32403-5214 | 1 Apr 2009 | ||
| Operations | |||
| ACMI - EMERGENCY BOAT OPERATIONS |
This operating instruction (OI) establishes basic guidelines, policies and procedures for boat operations in support of aircraft emergencies using the Air Combat and Maneuvering Instrumentation (ACMI) Operations and Maintenance (O&M) watercraft. Contractor support requirements for emergency boat operations are covered in contract number F41689-02-D-0044, Paragraphs 1.1.6 and 4.15.1.
1. TASKING
1.1. The 325th Operations Group Commander (325 OG/CC) is responsible for directing the use of the ACMI watercraft in support of search and rescue (SAR) operations in the Gulf.
1.2. The ACMI Functional Director, or his alternate, will advise the O&M contractor of watercraft requirements and will provide coordination during these operations.
1.3. The O&M contractor will provide ACMI watercraft to support emergency watercraft operations with a minimum crew consistent with Coast Guard regulations.
2. PROCEDURES
2.1. Upon notification of an emergency requirement, by the Supervisor of Flying (SOF) or 325th Fighter Wing (FW) Command Post, the ACMI O&M contractor will secure the necessary crew to accomplish the SAR mission and proceed as directed.
2.2. All necessary emergency and support equipment will be made available in advance of the mission.
2.3. Contact with the vessel will be maintained the entire time of the directed mission through ACMI Operations. 325 FW Command Post will coordinate with Range Communications to utilize an ACMI radio (usually radio 3 at Carrabelle or radio 7 on South Master) to coordinate rescue operations. ACMI Operations will change the appropriate radio to frequency 282.8 and provide coordination between the rescue aircraft and the ACMI watercraft utilizing ACMI UHF and/or VHF frequencies. Command Post/command direction may be delegated through ACMI Operations.
2.4. All fuel and overtime costs will be borne by the government as provided in the ACMI O&M contract.
2.5. If required, medical assistance will be coordinated through 325 FW Command Post.
2.6. Upon return to the docking facilities, a report of any incident will be provided by the boat captain. Any and all recovered equipment and/or aircraft parts will be returned to the 325 FW Flying Safety Office.
| WILLIAM H. MOTT V, Colonel, USAF | |||
| Commander, 325th Operations Group | |||
| Supersedes OG OI 10-1, 25 Jun 2007 | Certified by: Col William H. Mott V | ||
| OPR: 325 OSS/OSTI (Mr. Skip Sanders) | Pages: 1/Distribution: X |
Other files
Show all 48
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .