QUESTIONS AND ANSWERS (Round 1) Solicitation No. FA3002-10-R-0009 Air Combat Training System (ACTS) ***The Government’s answers are in red.***
1. Please clarify if there will be only one award or more than one award for this work. The cited FAR clause below implies multiple awards. Please clarify how this will be done if you are making more than one award.
Reference: 52.216-27 SINGLE OR MULTIPLE AWARDS. (OCT 1995) The Government may elect to award a single delivery order contract or task order contract or to award multiple delivery order contracts or task order contracts for the same or similar supplies or services to two or more sources under this solicitation. This acquisition will result in a single contract award.
2. Please clarify, isn’t DOD’s Small Business goals that the percentage of subcontracted work is to be of total contract dollars. Section L.2 is unclear. If the Government’s goal is to develop qualified small businesses to compete as primes, therefore shouldn’t the SB goal and sub-sets be of total contract dollars otherwise these percentages become minuscule amounts if the prime only subcontracts 2% or 3% of the total contract dollars.
Reference: Section L. 2. PART II – SMALL BUSINESS SUBCONTRACTING PLAN:
Small Business (SB) 23% of total subcontracting dollars Small Disadvantaged Business (SDB) 5% of total subcontracting dollars Service Disabled Veteran Owned SB (SDVOSB) 3% of total subcontracting dollars Veteran Owned Small Business 3% of total subcontracting dollars HUBZone 3% of total subcontracting dollars Woman Owned Small Business 5% of total subcontracting dollars
See FAR 52.219-9(d)(1)—The offeror’s subcontracting plan shall include the following: goals, expressed in terms of percentages of total planned subcontracting dollars, for the use of small business, veteran-owned small business, service-disabled veteran-owned small business…
3.
Reference the RFP subcontracting plan information which indicates the requirement to support goals which are a percentage of the subcontracted dollars. Is the Government planning to establish any guidelines in what must be subcontracted (either by dollar amount or type of expenditure) or will that be left to the contractor? The Government cannot tell the contractor what work should be subcontracted. The contractor is responsible to determine the most cost effective way to subcontract out portions of the work according to the Government wide subcontracting goals stated above.
4. For graphics, tables, charts and diagrams, can we use a smaller font size no smaller than 8 pt? Yes
5. For the technical proposal, are the tables of contents, acronyms list, cover page and tabs excluded from page count? The tables of contents, acronyms list, cover page and tabs are excluded from the 50 page count.
6. Is an Adobe pdf file format acceptable for the electronic submission? And/or what version of Word is required format 2003 or 2007? Adobe pdf file format is acceptable. Either 2003 or 2007 MS Office Suite format is acceptable.
7. PWS 2.4:
a. Which sites are accessible by helicopter only (UMTE, TIS, Comm, etc)? 6 RRU sites
b. On average, how many helicopter hours are flown in support of Luke AFB ACTS maintenance? Contractor is required to fund helicopter flights. The Government doesn’t track number of flight hours.
8. PWS 7.4.2 Information System Security:
a. Clarify the requirement for maintaining an AISSP. Is the requirement to “develop and maintain” a Certification and Accreditation package on both Luke and Tyndall ABFB ACTS systems? Yes
b. If so, under what guidance? Local IA
c. When and under what program is the current C&A under (DITSCAP or DIACAP)? The AISSP is pertinent to each (Tyndall and Luke) independently. While the basis systems are the same, there are differences and the hardware integration is also different. The AISSP is revised every three (3) years and/or when major changes are made.
9. PWS 7.9.1 External Agency Support:
Are there any external agency support agreements currently in place? If so, what are they? No
10. PWS 4.4.7 Operational Engineering Support:
If the project cost is under $15,000.00 dollars, is it still a cost reimbursable? Yes. The $15K limit is approved by the Functional Director (FD) locally. Above $15K, the CO must approve.
11. PWS 4.2 Maintenance:
a. What systems rely solely on generator power? None
b. What systems have commercial power and have generator back-up? All major systems.
c. Of those sites that have generators, what size of fuel tanks do they have? Who is responsible for refueling those sites? Is the cost of fuel a reimbursable cost? The Gila Bend AFAF O&M contractor is responsible for refueling the generators. The cost is taken out of the Gila Bend AFAF O&M reimbursable fund.
12. PWS 2.2 Operations:
What “Threat Kits” are the UMTEs? 2 threat kit 1’s, one Threat kit 4 and 1 threat kit 2
13. PWS 3.9 Weapons Duty Officer (WDO):
How many vaults require a WDO? Tyndall has two (2) vaults. The WDO maintains access control over one (SAPF).
14. PWS 5.4 Performance Standards:
a. If non-effective missions (OER non-effective) are due to circumstance beyond contractor control, are there procedures for relief to be granted? Yes, relief is granted dependant on the circumstances. Contractor QA will submit appropriate explanation of circumstances to local QAP via Memorandum for Record, who will determine if the relief is warranted.
b. If equipment in not available (awaiting maintenance) due to circumstances beyond contractor control, are there procedures for relief to be granted? Yes, contractor QA again will work in tandem with local QAPs to ensure they are aware of equipment down for maintenance. Contractor QAs can submit memorandums to local QAPs, informing them of down equipment and will then not need to include identified equipment into their calculations. Contractor QA and local QAPs at Luke hold weekly meetings to which equipment statuses and maintenance issues are relayed, therefore, may not need memorandums. Bottom line, as long as contractor QA has provided local QAPs with an acceptable and reasonable explanation of situation, relief is granted.
15. What is the current timeline for the F-15 deactivation mentioned for the Tyndall ACTS support? The number of remaining F-15s as of 30 Sep 2010 (the end of FY10) will be zero.
16. PWS Appendix 5, Facilities:
Several Luke AFB associated facilities, shelters and structures are contractor supported for maintenance. Are all material costs involved with the maintenance reimbursable? No
17. PWS 2.1.2: Employee Work Hours:
Does the 14-hour debrief window start the same time the 12-hour flight window does? If not, when in relation to the flight window does the debrief window start? Yes, flight schedule begins in concert with debrief schedule, example, 0730 fly mission would require “live” recording (debrief capabilities). The last mission of the day (12 hours later 1930) would need the debrief crew to remain around until the last mission has returned and had utilized the debrief service (up to 2 hours after last mission 2130, thus 14 hours of debrief window).
18. Site locations: Request locations (coordinates) of all site locations (other than Primary and Ancillary locations). See updated Appendix 5 para 3.1 and 3.2.
19. Is contractor helicopter support allowed to operate from Luke AFB and/or Gila Bend AFAF? If so, are services such as fuel available? Under what arrangement? No, helicopter support is obtained from “off-base” sources and in no way will be associated with Luke AFB, or Gila Bend AFAF. As such, all fuel, helo crew, support, etc will be provided by the local helicopter contractor and paid for by the ACTS contractor.
20. PWS 2.2.3.1.5 Weapons Impact Scoring System:
Do the tactical ranges on BMGR have WISS scoring capability? No
21. PWS 2.1.2.1 Gila Bend AFAF Operation Hours and PWS 2.2.2.1.1 ROCC Operations Hours:
a. What services can be requested during the “four weekend day” per month? EW/RCO/WISS/LSTSS/ACMI etc? ROCC services must be available for the four weekend days per month. All other services may be requested by Luke customers and they will be reimbursed via reimbursable CLIN for overtime incurred.
b. Will employee over-time incurred for this support be reimbursed by the customer? No.
c. Is it customer directed that the Southern Airspace, Northern Airspace and Ground positions be manned by individual controllers? Or can they be manned as described in the “evening shift”? As stated in the PWS: “Contractor shall: Operate with certified operators to ensure thorough coverage: Southern Airspace, Northern Airspace and Ground positions throughout day shift operations. The evening shift shall operate the Northern airspace and Southern airspace; the ground position duty can be shared by the Northern airspace and Southern airspace operators as needed.” As this paragraph clearly explains, the “day-shift” will have individual controllers at the Southern, Northern, and ground positions. The evening shift will have individual controllers at the Northern and Southern positions both “sharing” the ground position as needed.
22. PWS 2.2.2.1 ROCC:
a. Where is the ROCC facility that the contractor will work in? Building 470 Luke AFB.
b. What type of radar display is used n the ROCC? 2 monitors are 37” Dynex brand monitors, all remaining monitors are Dell brand. Radar feeds: 3 FAA ARSR-4 primary feeds, and 1 AMOC feed (Air Marine Operations Center) utilized as back-up.
c. Understand that contractor is not responsible for any maintenance or sustainment of any equipment/systems associated with the ROCC. If this is not correct, list the equipment (type and location), that the contractor is responsible for. Not correct. Equipment listed in Appendix 4.
23. PWS 2.2.2.2.1.4.2.6 RCO Maintenance:
Is the contractor responsible for target maintenance/build-up? Minor Maintenance as required by PWS Yes
24. PWS 2.2.2.2.1.4.2.5 Crash Response:
Clarify the following requirement: “The contractor shall provide trained and designated personnel to assist the RCO in crash response and crash site security, as required” As stated in the beginning of the paragraph 2.2.2.2.1.4.2.5. CRASH RESPONSE, it clarifies RCO responsibilities regarding crash response. Training will be conducted for each RCO on these “On-Range” procedures as outlined in para: 2.2.2.2.1.2.4. ON-RANGE TRAINING.
25. AIS Pod Maintenance at Luke and Tyndall AFBs:
a. PWS does not specifically mention AIS pod maintenance. Is AIS pod maintenance a part of this RFP? Yes
b. PWS Appendix 4 lists 23 P4RC pods and 70 P5 pods at Luke AFB. There is no mention of any pods at Tyndall. What and how many AIS pods at Tyndall AFB? Luke has no P4RC pods and Tyndall has fifty (50) P5 pods (38 V1/12 V2) and two (2) P4G pods. See the updated appendix 4.
26. PWS 3.1.2: Employee Work Hours:
Does the 14-hour debrief window start the same time the 10-hour flight window does? If not, when in relation to the flight window does the debrief window start? Yes, flight schedule begins in concert with debrief schedule, example, 0730 fly mission would require “live” recording (debrief capabilities). The last mission of the day (10 hours later at 1730) would need the debrief crew to remain around until the last mission has returned and had utilized the debrief service (up to 4 hours after the last mission at 2130, thus, 14 hours of debrief window). Personnel schedule must cover those time and whatever prep time to meet that schedule.
27. Attachment 2, Past and Present Performance Information Sheet, requires that the contract/program information be submitted “not later than 30 April 2010.” What is the correct date?
The due date was corrected from 30 Apr 10 to 28 May 10 through Amendment 001.
28. Reference the Government will reimburse the Service Provider for Gov’t directed travel, pre-approved contractor authorized purchases and other items to support the ACTS mission IAW the PWS. The govt. directed travel shall be IAW Joint Travel Regulation (JTR). Purchases made are considered contractor acquired Govt property. No overhead or profit will be paid on the cost for travels and purchases. Request clarification on the last statement which indicated no overhead or profit on the travel and purchases. If overhead is not included in the CLIN, there is an associated overhead which goes with the cost incurred. With an unpredictable amount of expenditure this amount cannot be estimated in advance. The contractor submits travel and purchase request to the local QAPs for pre-approval and the actual cost will be reimbursed to the contractor when invoices are submitted. There is no estimation involved in that process. Only the G&A will be allowed to be added into the actual cost of travel and purchases.
29. Also in accordance with generally accepted accounting procedures, the indirect costs would be tracked with direct cost. Will the overhead which is directly related to the labor expense on this CLIN be allowed to be invoiced on this cost CLIN? If not, please provide the estimated dollar value of what the labor expenditures will be under this CLIN. Overhead that are related to the labor expense will be allowed under the reimbursable CLIN.
30. Additionally, G&A and handling amounts under accounting procedures would have to be applied consistently. If the expense relates to the item purchased under this CLIN can it not be reimbursed under the CLIN? This is not profit or fee but the general cost of doing business and indirect rates which are commonly associated with direct costs. If this indirect rate cannot be invoiced under this CLIN, please provide the estimated value of each reimbursable CLIN in order for the costs to be accounted for elsewhere. As stated above, G&A will be allowed on travel and purchases.
31. Are the costs of the vehicle insurance (including Hazardous insurance coverage for hauling Smokey Sams) and maintenance of GSA leased vehicles reimbursable along with the cost of the lease and the fuel? Are modifications to the GSA vehicles allowed for installing POD racks? Who will incur the cost of manufacture and installation of the POD rack the government or the contractor?
According to the area GSA representative, the following is needed for operating the GSA vehicles:
a. Contractor personnel will need a valid State driver’s license to drive GSA vehicles.
b. Contractor must provide vehicle insurance and hazardous material insurance for all vehicles.
c. Contracting Officer must provide a copy of the contract to the GSA Rep authorizing the use of GSA vehicles (this will be accomplished during the phase-in period).
Maintenance and fuel costs are included in the per mile rate in GSA charges and will be reimbursed. Modification to GSA vehicles for installing pod racks is authorized. The contractor is responsible for procurement and installation of pod racks if the contractor chooses to do so.
32. The CBA between Yulista and the union will expire before the this contract start date. Is it the incoming contractor’s responsibility for negotiating the new CBA rates for the two positions (Range Control Officer and Range Tacker) after the contract is awarded? What will happen if Yulista does the re-negotiations and the renewed rates increase?
According to the Contracting Officer at Luke AFB who manages the Gila Bend O&M contract, Yulista plans to include RCO and Range Tracker poisitons in their CBA renewal. Discussions are set for mid-July and more than likely, the new CBA will be published by the end of July 2010. The offeror’s pricing for these union positions should be based on the current CBA that was posted with this RFP Amendment 001. After the contract award, these positions will have to be incorporated into the ACTS contract by an addendum to the existing CBA. If the wages increase in the renewed CBA, the incoming contractor will be compensated via wage pass-through/wage equitable adjustment request upon completion of the CBA addendum.
Other files
Show all 48
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .