AMENDED RFI QUESTIONS AND ANSWERS 3 OCT 22 MACSPO IDIQ FY23 SEED Project.pdf

PDF 171 KB Posted

Attached to
Multiple Award Contract for Small Purchase Orders (MACSPO) Indefinite Delivery/Indefinite Quantity (IDIQ) Hanscom Air Force Base, MA
Solicitation number
FA283522R0021
Issued by

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Information (RFI)

MACSPO IDIQ FY23 - SEED PROJECT, Building 1210

Site Visit 21 Sep 2022

RFI AMENDED 3 OCTOBER 2022

Questions and Answers

1.Q: If we have to provide price proposal for Seed project “install new shower stall in locker room” at B1210 in the SF1442 section 17 or in the proposal letter?

A: Proposal Letter (not in Section 17). Only provide a price proposal for the SEED project.

2.Q: Do we have to provide any price in solicitation section B “supplies or services & prices or costs”.

A: No, only provide a price proposal for the SEED project

3.Q: Plans call to remove and reinstall one smoke detector. What is the process for shutting down the fire alarm panel?

A: Contact CE and we will get ahold of techs to shut down alarms

4.Q: Plans call for a new exhaust fan through the roof. There is an existing exhaust fan through the roof in the ladies’ room 11 feet away. Can we tie into the existing exhaust for the ladies’ room?

A: Yes

5.Q: Statement of work calls for new water lines to be run from the mechanical room. Can we tie into the existing hot and cold-water lines at the ladies’ bathroom?

A: No

6.Q: Will off hours work be needed for the shutdowns to the heat and water?

A: No

7.Q: Will the shower base need to be ADA compliant?

A: No

8.Q: What is the makeup of the existing exterior wall for the infill at the windows?

A: CMU

9.Q: What is the color of the Drivit exterior wall? Fading of the existing will make it hard to match. Should that side of the building be painted to blend the patch?

A: Paint to match

10.Q: Is the precast sill being removed? Will a new precast sill be required?

A: Yes, sill being removed and no precast sill be required

11.Q: Shower walls don’t seem to have finish on both sides, are walls required on the outside of the shower walls to provide a finish side?

A: No outside will be tiled

12.Q: Will the base provide guidance on locations of valves and where equipment needs to be purged after the heater is installed?

A: No

Additional Questions added 3 October 2022

13. Q: How far from the shower area is the panel where fire alarm/detectors will are terminated?

A: 25 Feet

14. Q: If any security system is to be reinstalled in this area, how far away is the security panel/devices?

A: None

15. Q: How far is the run for the sanitary system (i.e. drain pipes from the shower, vanity sink, and bathroom)?

A: 12‐15 feet

16. Q: What is the true distance to run the vent for the exhaust fan?

A: 20‐25 Feet

17. Q: What is the true distance from the Mechanical room to the shower?

A: 50‐75 Feet

18. Q: How far is the nearest panel for the new electrical (Lighting and GFIs)?

A: 50 Feet

19. Q: How far is the run for the hot and cold water lines to the shower and vanity?

A: 50‐75 Feet

20. Q: What is the true distance of water piping to the mechanical room?

A: 50 ‐75 Feet

21. Q: What are the major obstacles for the plumbing between the shower and mechanical room?

A: CMS Walls

22. Q: Will the trench be smoothed and level?

A: yes

23. Q: Is the shower a fiberglass floor and wall unit?

A: Corian

24. Q: What is the planning approach for working around occupied work spaces?

A: Work around them they won’t be in your way.

25. Q: What are the working hours and is an Air Force/Contractor escort required?

A: 0730‐1600 No

26. Q: Please provide updated Arch drawings

A: N/A

27. Q: Please provide Life safety Drawings

A: N/A

28. Q: Please provide Mechanical, Electrical, and Plumbing Drawings

A: N/A