Attachment_1_-_MACSPO_Statement_of_Work.pdf
PDF 224 KB Posted
- Attached to
- MULTIPLE AWARD CONTRACT FOR SMALL PURCHASES Federal contract opportunity
- Solicitation number
- FA283519RA039
About this file
Attachment 1- MACSPO STATMENT OF WORK
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| MACSPO_Site_Visit_Attendees.pdf | ||
| Solicitation_-_FA283519RA039.pdf | ||
| Ordering_Procedures.pdf | ||
| MACSPO_RFI_contd.pdf | ||
| Casement_windows_being_replaced.pdf | ||
| MACSPO_RFIs.pdf | ||
| Solicitation_-_FA283519RA039.pdf | ||
| Attachment_5_-_Section_L_-_Instructions,_Conditions,_and_Notices_to_Offerors.pdf | ||
| Attachment_7_-_Task_Order_Statement_Of_Work.pdf | ||
| Attachment_2_-_Ordering_Procedures.pdf | ||
| DBA_Wage_Determination_-_Middlesex,_Essex,_Barnstable.pdf | ||
| Attachment_6_-_Section_M_-_Evaluation_Factors_For_Award.pdf | ||
| Task_Order_Bid_Schedule.pdf | ||
| Attachment_5_-_Section_L_-_Instructions,_Conditions,_and_Notices_to_Offerors.pdf | ||
| DBA_Wage_Determination_-_Plymouth.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Contract No: TBD
Statement of Work for
Multiple Award Contract for Small Purchase Orders
(MACSPO)
66/ABG CIVIL ENGINEERING SQUADRON
Hanscom Air Force Base
11 June 2019
Table of Contents
Section Title
1 Description 2 Definitions 3 Technical Design Support Capabilities 4 Standard vs. Non-Standard Work Hours 5 Contract Start-up and Completion Period 6 Contractor-Provided Materials 7 Task Order Procedures 8 Proposal Submittal 9 Performance of Work by the Contractor 10 Final Inspections and Acceptance 11 Government-Furnished Equipment/Materials (GFE/GFM) 12 Security Requirements 13 Work by the Government 14 Scheduling Work 15 Work Clearance 16 Utilities 17 As-Built Drawings 18 Environmental Protection 19 Construction Site Maintenance 20 Grounds Maintenance 21 Construction Signs 22 Barriers and Enclosures 23 Noise Control 24 Equipment On the Site 25 Access Roads and Trucking 26 Elevators 27 Safety and Health 28 Recording and Preserving Historical and Archeological Finds 29 Professional Registration, Certifications, and Contractor Liability 30 Communications 31 Government Liability for Loss or Damage to Contractor Property 32 Construction Requirements 33 Data for Warranty/Guarantee Items 34 Quality Control Program 35 Project Manager
1. DESCRIPTION:
1.1. The IDIQ is for a broad range of commercial services, supplies and maintenance, repair, alteration, and minor construction projects on real property at the following locations: Hanscom Air Force Base (HAFB), MA; Sagamore Hill Electronics Research Annex – Hamilton, MA;
Fourth Cliff Recreation Annex – Humarock, MA; and Cape Cod Air Force Station – Sagamore, MA. The Contractor is required to furnish all requirements including but not limited to materials, labor, plans, tools, equipment, transportation, supervision, management, and quality assurance in accordance with the basic contract specifications and individual task order requirements.
1.2. Work shall include but not be limited to the following:
1.2.1. Flooring – Replace and/or repair flooring to include but not limited to carpet, hardwood, tiles and concrete.
1.2.1.1. Carpeting must be purchased through one of the following mandatory sources below. Additional information on this process will be included in the Task Order Statement of Work.
1.2.2. Paint – Clean, sand, prime and paint interior and exterior projects to include walls, doors, buildings, and aircraft.
1.2.3. Alarms – Repair and/or replace door alarms.
1.2.4. Doors – Remove and dispose of existing door and install door including but not limited to door frame, doors, weather seals door sweeps, handles and locks.
1.2.5. Fencing – Removing and installing new fencing to include but not limited to chain-link fencing, gates, and barbed wire with outriggers.
1.2.6. Landscaping – General landscaping to include but not limited to installing topsoil, seeding, sodding, mulch, tree removal, and hardscaping.
1.3. The contracting office will issue a request for proposal (RFP) and the resulting task orders to the
Contractor for accomplishing the identified work. The Contractor shall be required to furnish all equipment, materials, and personnel necessary accomplish construction, manage the task orders in the time period, and to the quality required in the contract.
Company Contract Number POC Phone Web Site Carpet Selected from each vendor
Shaw FA8057-1-C-0002 Farrah Finley 888-393-2830 Pin 2273 Base www.shawcontractgroup.com 69401 Everlasting 69703 Border
J&J Flooring FA8057-17-C-0003 Kay Henderson 800-241-4586 x 8389 www.jjflooringgroup.com 1807 Jump right in 1308 Call an old
Mohawk FA8057-17-C-0004 Annaleigh 800-622-6228 www.mohawkgroup.com 588 Hammer down Warmack x 46554 984 Super Rally
CMA-
Mililken
FA8057-17-C-0005 Paul Snyder/Betty King
888-669-9772 www.cma-gsa.com 1GD6759 Lahar CTR119 Effervesce Chatter
1.4. Work will require expertise in various trades to include, but not limited to: carpentry, interior renovation, electrical, plumbing, HVAC, sheet metal, welding, painting, demolition, and concrete masonry.
1.5. Upon issuance of a task order, the Contractor will diligently complete all work within the time frames specified in the task order and approved progress schedules. The Contractor shall perform all necessary quality control functions to ensure the work is executed in compliance with the terms of the task order and this contract.
2. DEFINITIONS:
2.1. The following definitions apply to all work required by this solicitation and the resulting contract:
2.2. Red-Line Drawings: Final red-line drawings prepared by the Contractor in sufficient detail to accurately reflect the project as fully constructed, complete with all changes, modifications, and deletions from prior award drawings.
2.3. Calendar Day: Each day of the calendar year including workdays, holidays, and weekends
(Saturdays and Sundays). The following are the identified federal holidays:
New Year’s Day Labor Day Martin Luther King’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Thanksgiving Day Independence Day Christmas Day
2.4. Government-Furnished Equipment / Government-Furnished Property (GFE / GFP): Items provided by the Government to the Contractor for use in performance of this contract. Any Government Furnished Items will be identified per task order.
2.5. Pre-Final Inspection: An examination requested by the Contractor, with Government representatives present, to identify and correct all work discrepancies prior to requesting a final inspection by the Government.
2.6. Progress Meeting: A meeting attended by designated representatives of the Government and Contractor to discuss progress on existing and/or potential projects as well as the basic contract performance. The Government may hold Progress Meetings bi-weekly, with Contractor attendance to be provided upon request; the Government reserves the right to increase the frequency of progress meetings if so desired.
2.7. Restricted Work Areas: Areas of performance on Government property with increased security requirements within which the Contractor is not allowed free access to the work site, cannot enter and exit freely, and will be required to be under escort during performance of the project.
Personnel and equipment entry will be subject to delays due to security processing.
2.8. Site Visits: A visits to a location at which work has been proposed by the Government.
2.9. Statement of Work (SOW): A specific written description (in the quality, detail, and professionalism necessary) documenting the specific work required for each Government project
3. TECHNICAL DESIGN SUPPORT CAPABILITIES:
3.1. Design will not be required in the majority of work performed under this contract. If required, it will entail very minimal design requirements, which should not necessitate hiring additional expertise beyond that normally required by a general Contractor, except for state requirements such as fire suppression & detection system design engineering requirements, structural design and/or calculations, and Professional Engineering stamps and certifications for these items specifically.
3.2. Contactor are encouraged to have engineers or master craftsmen available on an “as needed” basis that are capable of design in civil, structural, mechanical, and electrical construction. They must be experienced with building codes, safety regulations, and environmental protection requirements associated with construction, as well as having technical support to handle architectural and drafting services that are familiar with standard drafting conventions. The Contractor should expect to produce any supporting technical calculations or any other data required by the Contracting Officer in order that the Government may verify the accuracy and validity of the Contractor design. The Contractor must submit basic plans/schematic drawings for all mechanical and electrical systems being installed (i.e. fire suppression, HVAC, electrical system panels). The Contracting Officer’s Representative (COR) shall be the determining authority as to what data is needed from the Contractor for individual task orders. The data required may vary with each task order.
3.3. Depending on the Task Order, should a draftsman be required, drafting technicians shall have training in an accredited drafting program and at least of two (2) years applied experience in generating and modifying construction drawings using AutoCAD software.
3.4. Computer Aided Design (CAD) Drawing Formats and Standards:
3.4.1. All drawings will A/E/C CADD Standard published by the CADD/GIS Technology Center for
Facilities, Infrastructure and Environment for all computer-aided drafting and design-generated “as-built” drawings. The standard is published at https://cadbim.usace.army.mil.
3.4.2. Drawings shall be in the same format as the Hanscom AFB standard which is currently the
AutoCAD format. However, the format changes every few years and the Government holds the right to request AutoCAD Drawing Files at future formats at no additional charge.
3.4.3. CADD/GIS/Drawing standards shall adhere to Section 17 of the Hanscom AFB Design
Compatibility Guide.
3.5. Drawing Quality Assurance/Quality Control:
3.5.1. The Contractor shall insure that any and all products provided to the Government have received careful and complete Quality Assurance / Quality Control.
3.5.2. The Government will immediately return for remedial action (at the Contractor’s expense) any products that do not meet these specifications.
3.5.3. Before a file is placed on the delivery digital media, the following procedures shall be performed:
3.5.3.1. Remove all extraneous graphics outside the border area and set the active parameters to a standard setting.
3.5.3.2. X-refs shall be bound, without device or directory specifications, to the drawings that reference them.
3.5.3.3. All digital files shall be delivered to the Government uncompressed.
3.5.3.4. Include all files, both graphic and nongraphic, required for the project (i.e., color tables, pen tables, font libraries, symbol libraries, user command files, plot configuration files, AML plot routines, etc.). Applicable plotstyle (.ctb) files shall be provided with the drawings.
3.5.3.5. Each finished CADD drawing or map shall have its own separate plot file.
3.5.3.6. Make sure that all support files such as those listed above are in the same directory and that refers to those files do not include device or directory specifications.
3.5.3.7. Include any standard sheets (i.e., abbreviation sheets, standard symbol sheets, etc.) necessary for a complete project.
3.5.3.8. Document any fonts, tables, symbols, cells/blocks, line styles/types, details, reference drawings, etc., developed by the Contractor. The Contractor shall obtain Government approval before using anything other than the Government's standards.
3.6. Contractor Guidelines for Formatting GIS Files: If any GIS files are to be created and turned over to the Government, the Contractor must contact 66 ABG/CE for additional guidelines which must be followed.
4. STANDARD VS. NON-STANDARD WORK HOURS:
4.1. Standard Working Hours: The Contractor shall generally be prepared to pursue contracted tasks during the standard working period of 0700 to 1530 hours (7:00 a.m. to 3:30 p.m.), Monday through Friday, excluding federal holidays. The Contractor may elect to work hours other than standard duty hours provided that:
4.1.1. The request is submitted in writing at least three (3) workdays in advance.
4.1.2. The Contracting Officer approves the request.
4.1.3. Work performed outside standard working hours or on weekends or federal holidays that the
Contractor chooses to perform during non-standard hours will be completed at no additional cost to the Government.
4.2. Non-Standard Working Hours: Work required by the Government at other than standard duty hours will be considered nonstandard working hours, that is, Monday through Friday from 0700 to 1530 hours, Saturdays, Sundays, and federal holidays.
5. CONTRACT START-UP AND COMPLETION PERIOD:
5.1. Each task order will include a Period of Performance necessary to perform all elements of the
Task Order.
5.2. Although the Government may issue task orders against this contract through the final date of the contract period of performance, the Contractor must physically complete all work outlined in any task order within six months after the date of contract end.
5.3. The Contractor is required to vacate any and all areas provided to him, including any office areas and individual work sites or storage yards, and remove all Contractor-owned equipment, within three (3) days of the conclusion of the final task order issued under this contract, whether by termination or natural completion, or within (14) calendar days of being notified in writing by the Contracting Officer at any other period during performance.
5.4. After the contract completion period, within 7 days, the Government will conduct a walkthrough of the Contractor’s formerly occupied areas. Any discrepancies, damages, and required cleanup will be notified to the Contractor in writing. The Contractor will have 48 hours to resolve the notification(s) from the Government. If the Contractor fails to resolve adequate cleanup or repair of damages, the cost for identified items may be completed by the Government or services procured from a third party, and charges billed to the Contractor.
6. CONTRACTOR-PROVIDED MATERIALS:
6.1. All Contractor-provided materials shall become the sole property of the Government.
6.2. Software Programs, Licenses, and Upgrades: Any software, licenses, manuals, or system upgrades as a result of construction on Hanscom AFB shall become sole property of the Government.
7. TASK ORDER PROCEDURES:
7.1. As the need exists for performance under the terms of this contract, the Contracting Officer (CO) will notify the Contractor of a potential performance requirement.
7.1.1. The Contractor will be requested to provide proposals within the last quarter of the fiscal year in anticipation of fall out funds (money which is not yet obligated by the Government, but which is expected to become available prior to fiscal year end). In anticipation of this potential work, and the fast turnaround required at fiscal year-end to secure funds should they become available, the Contractor may be asked to provide a proposal at no liability to the Government to award the project.
7.2. Upon receipt of an RFP, the Contractor shall respond to the needs of the Government by attending a site visit as scheduled by the Government. The site visit will be conducted in the company of the Contractor, contracting personnel, the end user or facility manager, and 66 ABG/CE at the proposed work site. If specific disciplines are needed at the meeting, other base agencies (fire department, safety, communications, etc.) may also be invited to attend. The Contractor shall attend no less than 75% of the Government requested site visits.
7.3. Note: Any reference to any equipment, material, article or patented process by trade name, make or catalog number requested by the Government shall be regarded as establishing a standard of quality only.
7.4. Contractor will submit questions regarding the project in writing to the CO within 24 hours of the site visit.
7.5. An amendment to the RFP may be issued by the CO incorporating any changes to the Scope of Work as determined during the site visit, or as a result of other Contractor questions.
7.6. Upon establishment of the final scope of the individual requirement, the Contractor shall then prepare a proposal package for submission to the Contracting Officer.
7.7. The Contractor shall accomplish their proposal package and return it to the Contracting Officer by the suspense date reflected on the Request for Proposal. The suspense date will be determined by the CO based on the magnitude, complexity, and urgency of the project; generally a suspense date of five (5) workdays after the site visit will be determined, taking these factors into consideration. The Contractor shall have enough staff to ensure proposals are completed within the established suspense dates. The Contractor shall propose to no less than 75% of the total requests by the Government for proposals.
7.8. The CO will then forward the proposal to the 66 CE/ABG for review. Upon receipt of the
Contractor’s proposal, the Government will accomplish a technical evaluation of the proposal. If 66 CE/ABG has questions about the Contractor’s proposal, the Contract Administrator may call a fact-finding meeting in order to clarify Government questions and misunderstandings.
7.9. The Contractor’s proposal will be reviewed and approved by 66 CE/ABG.
7.10. The proposed price will remain valid for sixty (60) calendar days, unless otherwise negotiated with the Contracting Officer.
7.11. The Contracting Officer will issue a task order against the contract using DD Form 1155 and will distribute the award to all parties. Construction performance will be based the task order’s Statement of Work.
7.12. Typically, the work will not be complex and will not require a pre-construction meeting, bonding, a Contract Progress Schedule, or a contract progress report. However, when required, the Contractor, subcontractors, contracting, 66 CE/ABG, building manager, and other pertinent base officials (i.e. Safety, Security Forces, Communications) will have a pre-construction meeting to discuss specific issues for the task order.
7.13. The Contractor may request a pre-final inspection for the purpose of having the Government assist in identifying potential problems or areas of correction required prior to the final inspection. The Contractor will request the pre-final inspection from the Contracting Officer and a date will be scheduled by the contracting office. Pre-final inspections will typically include the Contracting Officer and Contracting Administrator, 66 ABG/CE, Contractor personnel (to include subcontractors), requirements/end user personnel, operations and maintenance personnel, and representatives throughout the installation (fire, safety, security, etc.), as needed.
7.14. The Contractor will request a final inspection from the Contracting Officer no later than three (3) working days prior to the desired date of inspection. The final inspection will typically include 9 CES66 ABG/CE, the Contractor, the CO, and other base entities as needed. More information regarding final inspections is included in Section 14. CE will have seven (7) working days to inspect the final work and establish acceptance or communicate discrepancies.
7.15. Prior to final invoicing, the Contractor will provide all as-builts, warranty items and documentation, and all other required documentation as outlined in this Statement of Work.
8. PROPOSAL SUBMITTAL:
8.1. The Contractor’s proposal must be supported by a cost proposal, technical proposal, and other accompanying documents.
8.2. The Contractor’s proposal package will be provided for review to CE and Contracting personnel
9. PERFORMANCE OF WORK BY THE CONTRACTOR:
9.1. The Contractor shall perform work in accordance with FAR 52.219-14, Limitations on
Subcontracting.
9.2. Contractor shall maintain a professional work area to include their on-site location as well as any job sites. Smoking shall not be allowed except in designated areas. No noxious or harmful fumes shall be allowed to infiltrate occupied facilities or work areas.
9.3. The Contractor shall store all supplies, materials, and equipment in an area approved by the
Government. The Contractor must propose a staging area for each task order if one is needed. The Contractor shall be responsible for securing materials and equipment to preclude theft or damage.
The site shall be maintained in a neat and orderly manner.
10. FINAL INSPECTIONS AND ACCEPTANCE:
10.1. The Contractor shall request a final inspection in writing at least three (3) working days prior to proposed inspection date. The Contractor shall have a quality control manager inspect the project and ensure all work is complete and meets the terms of the contract prior to the final.
10.2. Any punch list items noted during the final inspection shall be recorded by a Government representative and a copy given to the Contractor within 24 hours of the inspection. The Contractor must provide a written schedule showing completion dates for the punch list items.
10.3. After all discrepancies have been corrected the Contractor shall notify Contracting and request another inspection. Once work has met acceptable standards, as determined by CE and Contracting personnel, the work shall be accepted.
10.4. A maximum of ten percent (10%) of the award price of each task order will be withheld from final payment approval until receipt, acceptance, and approval of all, warranty letters, equipment lists, operation and maintenance manuals, certificates and all other required documents have been received for the task order.
11. GOVERNMENT-FURNISHED EQUIPMENT/MATERIALS (GFE/GFM):
11.1. Government-furnished equipment and material is not to be furnished under this contract unless specifically authorized by the CO.
11.2. The Contractor, with his own forces, shall load and transport all Government-furnished equipment/materials, if any is to be provided, as described on the task order. The equipment/materials shall be transported from the Government storage area to the work site indicated on the task order.
11.3. The Contractor shall follow the instructions of the Contracting Officer’s representative regarding the disposition of all Government-furnished property not consumed in performance of a task order.
12. SECURITY REQUIREMENTS:
12.1. The Contractor shall comply with security regulations imposed by the Installation Commander and the agency occupying the space where work is to be performed, including any necessary security clearances.
12.2. Prior to mobilization, the Contractor shall provide the Contracting Officer or authorized representative a list of personnel requiring authority to work on Hanscom AFB. The list shall be kept current and the Contracting Office or authorized representative must be notified as to any changes in the list. The Contractor’s employees will be required to obtain and display employee identification as prescribed by Air Force directives. The Contracting Officer shall provide these requirements upon request.
12.3. Whenever facility security is breached to perform work required under this contract, the
Contractor will be responsible for providing temporary measures in order to assure security is maintained at the level existing prior to construction. This may include such security items as fencing around a facility or closing all openings in a structure during non-work hours.
13. WORK BY THE GOVERNMENT:
13.1. The Government reserves the right to undertake performance, by whatever means available or necessary, of the same type or similar work as contracted for herein. To do so will not breach or otherwise violate this contract.
14. SCHEDULING WORK:
14.1. Before any work is initiated under an individual task order, the Contractor and Contracting, with the coordination of the CE representative and other base entities as needed, shall agree on a sequence of procedures for execution. Items discussed shall include: means of access to premises and facilities, space for storage of materials and equipment, delivery of materials and use of approaches, use of corridors, stairways, elevators, spaces, and restrooms for the Contractor’s employees.
14.2. Delivery and storage of materials and equipment shall be made with minimum interference to Government operations and personnel.
14.3. The work shall, so far as practicable, be done in definite sections or divisions and confined to limited areas which shall be completed before work in other sections or divisions are begun.
14.4. The Contractor shall obtain a permit from the Base Fire Chief for all hot work (use of oxyacetylene gas or welding machine).
15. WORK CLEARANCE:
15.1. The Contractor shall apply for and obtain a properly approved and coordinated AF Form 103
(Base Civil Engineering Work Clearance Request) prior to beginning performance under any task order, including any digging, drilling, or excavation. The Contractor shall obtain digging permits directly from 66 CE/ABG. The Contractor may have to provide, at no additional cost, drawings and/or details showing the exact location and description of the type of excavations to be accomplished.
15.2. The Contractor shall request the AF 103 at least fourteen (14) days prior to the expected start date of work; failure to request the AF 103 in a timely manner does not constitute an acceptable delay of the negotiated project period of performance.
15.3. Digging permit markings for a specified area expire thirty (30) days after the issue date. The
Contractor must re-apply for a new digging permit to perform excavation in the area if the excavation was not started within the thirty (30) day period. Permits will identify all underground utilities within five (5) feet (1500 mm) of the designated area.
15.4. The Contractor shall insure that the location of all underground utilities, once located and marked by the Government, are adequately maintained to preclude remarking by Government personnel.
Should any one of the coordination points indicate an additional underground utility or structure over and above those shown on the contract drawing either by sketch on the Contractor's drawing, by field pointing, or by flagging, the Contractor shall be responsible for protection of each of the items indicated. If the Contractor damages any of the items indicated, he shall be responsible for prompt repair of the damage to return the item to its original workable condition.
16. UTILITIES:
16.1. Available water, electrical and local telephone services at the job site may be used in the performance of work under this contract at no cost to the Contractor. The Government shall not be held liable for interruptions of utilities. Electricity will not be used for heating purposes. The Contractor shall make arrangements for such services with the Contracting Officer or his designated representative.
16.2. At least ten (10) working days prior to a requested outage the Contractor shall request, and the
Base Civil Engineer shall approve, all temporary outages of any utility services required for the performance of work under this contract. No outage will be performed without prior written approval from 66 ABG/CE.
17. AS-BUILT DRAWINGS:
17.1. Red-line Drawings: During the progress of work, the Contractor shall keep a careful record at the job site of all changes and corrections from the layouts shown on the previously-existing drawings, if applicable. The Contractor shall enter such changes and corrections on contract or record drawings promptly and submit drawings to 66 ABG/CEin accordance with the schedule provided in the task order. Certified as-builts will not be required.
18. ENVIRONMENTAL PROTECTION:
18.1. Solid, Liquid, and Gaseous Contaminants. The Contractor shall be responsible for the proper disposal of all solid, liquid, and gaseous contaminants, including asbestos and lead-based paints, in accordance with all applicable Federal, State, and local codes and regulations.
18.2. Disposal of Refuse. The Contractor shall be required to remove all refuse from Hanscom AFB for negotiated task orders.
18.3. Covered Chutes. All chutes for refuse or other materials disposed of during execution of a task order shall be covered or of such design as to fully confine the material to prevent dissemination of dust.
18.4. Contractor shall not incorporate any asbestos containing material in any work.
18.5. Contractor shall submit the initial asbestos and lead base paint abatement plans as part of the task order design/proposal submittals.
18.6. The applicable items from the list below will be included in the Contractor’s proposed schedule and will be submitted by the Contractor once the task order has been awarded:
18.6.1. Request for use of Ionizing Radiation (if required)
18.6.2. Request for use of Lasers (if required)
18.6.3. Request for use of Radioactive Materials (if required)
18.6.4. Request for use of Radio Frequency radiation (if required)
18.6.5. Request for use of Ultraviolet Radiation (if required)
18.6.6. Environmental Protection Plan (if required)
18.6.7. Contaminated Soil Sampling and Analysis Plan (if required)
18.6.8. Storm Water Pollution Prevention Plan (if required)
18.6.9. Copy of NPDES NOI and EPA approval (if required)
18.6.10. Wetlands Permit (if Contractor-obtained)
18.6.11. Dewatering Permit (if required)
18.6.12. Phase I Environmental Assessment Certificate for Imported Borrow Materials (if required)
18.6.13. Any other Environmental Plans or Permits the Contractor is required to obtain in order to legally perform the work of the task order.
18.7. Environmental Management System:
18.7.1. The Contractor must comply with the Environmental Management System. Personnel will begin by completing EMS General Awareness Training prior to project commencement, so they may accurately identify the environmental aspects related to their daily activities. If personnel have already begun work on HAFB they shall complete the training as soon as feasibly possible.
Personnel are responsible for maintaining proof of completion for this training. EMS General Awareness Training can be completed at the Environmental, Safety, and Occupational Health Training Network (ESOHTN).
18.7.2. Instructions for registering at ESOHTN are listed below:
18.7.2.1. Go to the website: http://esohtn.com and click on "Enter"
18.7.2.2. Click on the title of your Command (ACC).
18.7.2.3. At the welcome page, click on "Enter"
18.7.2.4. At the login screen, locate the box on the right side that is labeled, "Register - New Users."
-- Enter esohtn into the Registration Password box.
-- Click on Create an Account.
18.7.2.5. For the next several screens, enter the information in the boxes as requested.
18.7.2.6. Read the disclaimer and if you agree, click on "I Agree" to complete your registration.
19. CONSTRUCTION SITE MAINTENANCE:
19.1. Contractors may request an area for the storage of trailers, but the request may not be granted. If granted, the contractor will be responsible for all costs associated with the maintenance and utilization of the trailer in accordance with Hanscom AFB policies.
19.2. Storage Trailers and Boxes. All trailers and boxes shall:
19.2.1. Be free from damage to an acceptable condition.
19.2.2. Ensure proper storage of project materials/equipment.
19.2.3. Be free from graffiti.
19.2.4. Be neat and clean in appearance.
19.2.5. All sides of storage trailers/boxes shall have professionally manufactured applicable warning placards mounted for each HAZMAT stored.
19.2.6. All storage trailer/box shall have a 5” x 7” Contractor Identification Placard in a weatherproof holder affixed to the right entrance door indicating:
19.2.6.1. Contractor’s Name.
19.2.6.2. Contract and Task Order Number.
19.2.6.3. Project Number and Title.
19.2.6.4. Contracting Office Point of Contact.
19.2.7. Storage of materials and debris under trailers is prohibited.
19.2.8. All storage trailers/boxes shall be removed from the worksite prior to the final inspection date.
19.3. Laydown/Bulk/Stockpile Storage:
19.3.1. All equipment materials shall be stored on pallets, dunnage and racks as appropriate, and shall not be stored directly on the ground at any time.
19.3.2. All materials sensitive to sunlight shall be covered at all times.
19.3.3. All loose or stockpile material, to include excavated earthworks staged for screening and re-utilization shall be fully covered by tarpaulins and properly staked against winds. Active stock piles will be covered in the same manner at the end of each business day.
19.3.4. Contractor shall enclose the lay-down area with fencing appropriate for the task order.
Contractor’s lay-down area shall also be screened from view.
19.4. Refuse / Solid Waste Disposal:
19.4.1. All solid waste materials generated by any work under this contract performed on a Government installation shall be handled, transported, stored, and disposed of by the Contractor and by his/her subcontractors at any time in accordance with these specifications, all applicable Federal, state, or local laws, applicable AFI’s and UFC’s, ordinances, regulations, court orders, or other types of rules or rulings having the same effect of law.
19.4.2. Contractor shall remove and dispose of off-base, in compliance with all federal, state, local, and Hanscom AFB ordinances, all trash, debris, refuse, and etc., as stated above.
19.4.3. Contractor shall not use installation dumpsters or recycle containers for construction debris or waste.
19.4.4. Contractor shall either include dumpsters as a line item in each task order proposal or, for projects generating small quantities of debris, remove the debris from the job site and dispose of off-base.
For Contractor-supplied dumpsters, the Contractor shall post signs on each dumpster stating "(Contractor Name) CONTRACTOR DUMPSTER" and "NOT FOR PUBLIC USE."
19.4.5. Contractor shall immediately clean up any and all spillage from equipment, material, supply, vehicle, container, and/or dumpster removals and/or deliveries, including mud on tires.
19.4.6. Contractor shall ensure any substance that can fall off delivery/pick-up vehicles is securely covered to prevent spillage.
19.5. Daily Cleanup:
19.5.1. Contractor shall maintain a worksite free from accumulation of debris.
19.5.2. Contractor shall empty trash receptacles on a regular basis throughout the day’s activity to avoid overflow or spillage.
19.5.3. Contractor shall perform daily general sweeping/pick-up of debris prior to close of a day’s worksite activity; empty all trash receptacles into worksite refuse containers; and shall comply with protection of existing Government property.
19.6. Salvageable Materials:
19.6.1. All salvageable material to be reused in the construction work shall be stored for reuse in a suitable location within the work area.
19.6.2. All such items shall be marked so as to be reinstalled in their proper locations.
19.6.3. All salvageable material, not to be used in the construction, shall be disposed of by the Contractor.
19.7. Unsalvageable Material:
19.7.1. All unsalvageable material shall become the sole property of the Contractor, unless designated otherwise by the Contracting Officer.
19.7.2. Unsalvageable material shall be promptly removed from the site and disposed of.
19.8. Trash Receptacles:
19.8.1. Worksite barrels/carts used for general daily debris accumulation.
19.8.2. Trash receptacles shall be free from graffiti, and shall have “TRASH” stenciled on opposite sides of the receptacle.
19.8.3. Contractor shall provide a minimum of one (1) trash container for each 10,000 square feet of worksite area.
19.9. Demolition/Bulk Debris:
19.9.1. When required, the Contractor shall provide refuse containers for the large accumulation of demolition waste and other debris.
19.9.2. Hauling of demolition/bulk debris to refuse containers shall comply with protection of existing Government property.
19.9.3. Trucks may be utilized for removal of demolition/bulk debris, but shall not be utilized for demolition/bulk debris accumulation.
19.9.4. Contractor shall empty refuse containers and trucks on a regular basis to avoid overflow, spillage, and remain below tonnage allowances for travel on municipal and base roadways in accordance with current local, state, and federal regulations.
19.10. Refuse Containers:
19.10.1. All refuse containers shall be free from graffiti, and be equipped with a securable tarpaulin or cover (NOTE: The cover shall be in place at all times, except when waste is being deposited or removed).
19.11. Trucking:
19.11.1. Contractor shall remove all loose debris on truck sidewalls prior to leaving the worksite.
19.11.2. Shall be loaded in a manner that shall prevent dropping of materials on roadways per in accordance with current local, state and federal ordinances and regulations.
19.11.3. Contractor shall provide suitable covers/tarpaulins over loads prior to leaving the worksite.
19.11.4. Contractor shall be responsible for any clean up, and liable for any resulting damage from any debris that may fall from trucks/refuse containers.
19.12. Sanitation Facilities:
19.12.1. Contractor shall provide self-contained portable/chemical toilet sanitation facilities, with hand cleansing capabilities and self-closing securable doors, for worksites without restroom facilities available unless otherwise specified by the CO.
19.12.2. Sanitation facilities shall be located in an out-of-view location if practical as approved by the
Government representative.
19.12.3. When specified, Contractor personnel may be permitted use of existing Government restroom facilities.
19.12.4. If the restrooms at worksites are under Contractors’ full jurisdictions, then such facilities shall be kept neat and clean.
19.12.5. The Contractor shall not use sanitary facilities for cleaning of work tools or equipment.
20. GROUNDS MAINTENANCE:
20.1. Grass:
20.1.1. Contractor shall maintain all grass that is sectioned off within a work site and is not accessible by grounds maintenance.
20.1.2. Maintain all work sites in a presentable manner that is not accessible by grounds maintenance.
20.1.3. Contractor employees, to include subcontractor employees and deliveries, shall not park any vehicle or equipment on grassed areas, unless otherwise authorized by 66 ABG/CE. When authorized, parking on grassed areas shall only be for short-term delivery purposes (to include heavy tools, equipment, construction materials etc.), vehicles shall then be promptly removed.
20.1.4. Tire/ track impressions (ruts) created on wet or soft soils by vehicles and/or equipment operated by the Contractor shall be restored to original state by the end of the project, or as otherwise directed by the CO.
20.2. Trees/Shrubs/Bushes: All trees/shrubs/bushes within a worksite that is not accessible by grounds maintenance shall be maintained during growing seasons, and pruned as directed by the CO.
20.3. Vegetation:
20.3.1. All trees, shrubs, bushes, vegetation beds and grass shall be protected from damage at all times.
20.3.2. During painting and stucco operations, or as otherwise directed, all trees, shrubs and bushes shall be tied and/or bundled, and vegetation beds and grass covered to protect from splatter and or damage.
20.4. Damaged Curbs, Pedestrian Walkways, and Roadways: Contractor shall repair/replace all damaged locations resulting from Contractor operations/negligence, to include subcontractors and deliveries, at no additional cost to the Government.
21. CONSTRUCTION SIGNS:
21.1. All construction sites shall have signs posted that say, “Construction Area—Authorized Personnel
Only”, “Hard-Hat Area—Construction in Progress”, and “Detour” (with an arrow), as applicable.
Signs that comply with OSHA and ANZI standards shall be made of metal or thick plastic with vinyl letters that can be easily read. INFORMATION, SIGNS, OR DIRECTIONS WILL NOT BE PRINTED ON PAPER. Signs used for indoor renovation projects will be large enough to ensure the hazard is easily identified from a safe distance.
22. BARRIERS AND ENCLOSURES:
22.1.1. All worksites with exterior work, i.e., additions, new parking lots, and window replacement, should have safety fencing around the area to prevent base personnel from entering the site, and for safety.
22.2. Erosion Control Fencing: Contractor shall use silt fencing, hay bales or other best management practice during and after construction activities in accordance with local, state and federal regulations where applicable, to prevent site runoff.
23. NOISE CONTROL:
23.1. The Contractor shall comply with all applicable state, local, and installation laws, ordinances, and regulations relative to noise control.
24. EQUIPMENT ON THE SITE:
24.1. The Contractor shall ensure all occupant equipment that is to remain in place within the area of contract operations is covered and protected against damage or loss. Equipment that is removed in the performance of work shall be stored where directed or reused in work as required by drawings and specifications. Equipment temporarily removed shall be protected, cleaned, and replaced equal to or better than its condition prior to starting work. Security for equipment or material that is to be reused and is removed for temporary storage shall be the sole responsibility of the Contractor.
25. ACCESS ROADS AND TRUCKING:
25.1. The Contractor shall be responsible for cleaning up any materials that fall from vehicles associated with a work site operating under this contract. The Contractor shall be solely responsible for any damage caused by debris falling from Contractor or subcontractor-operated vehicles, equipment, and machinery.
25.2. At the end of each day, the Contractor’s Quality Control Manager / Site Inspector shall inspect for and clear all mud, dirt, debris, foreign objects, or spills of any kind from the Contractor’s operations (including subcontractors and suppliers) on streets and parking lots used as access to the work or staging areas. The Contractor shall ensure all taxiways, runways, parking aprons and hard surfaces in or around the airfield, used to access the work or staging areas, remain clean at all times.
25.3. The Contractor shall provide a temporary stabilized construction entrances and exits at transitions from non-paved to paved areas to adequately remove sediment from vehicle tires.
25.3.1. Entrances and exits shall be constructed in accordance with the Sediment and Storm Water
Management Plan Permit drawings.
25.3.2. Contractor shall maintain this entrance to function as designed. Stones shall periodically be rotated or exchanged to ensure vehicle tires are clean when exiting the worksite.
25.3.3. The Contractor shall remove and restore soils at all entrances and exits prior to final inspection.
26. ELEVATORS:
26.1. Unless the Contracting Officer grants specific permission, the Contractor shall not use any elevators in Government facilities during the execution of a task order. If specific permission is granted for use of an elevator during an individual task order, the Contractor shall be bound by rules provided by the Government at the time of approval for the use and maintenance of the elevator(s) in question.
27. SAFETY AND HEALTH:
27.1. Applicable Publications: The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
Whenever referenced, the reference is understood to be the MOST CURRENT PUBLICATION.
27.1.1. Code of Federal Regulations (CFR).
27.1.2. OSHA General Industry Safety and Health Standards (29 CFR 1910) Publication V2206; OSHA
Construction Industry Standards (29 CFR 1926).
27.1.3. National Emission Standards for Hazardous Air Pollutants (40 CFR, Part 61)
27.1.4. Federal Standard (Fed. Std.).
27.1.5. A Material Safety Data Sheets, Preparation and the Submission of Safety and Health Requirements Manual, EM 385-1-1.
27.1.6. Use of Asbestos Containing Material, ETL 1110-1-118; Policy & Guidelines for Asbestos Management, DA Circular 40-83-4.
27.1.7. Definition of Hazardous Materials. Refer to hazardous and toxic materials/substances included in Subparts H and Z of 29 CFR 1910, and to others as additionally defined in Fed. Std. 313. Those most commonly encountered include asbestos, polychlorinated biphenyls (PCBs), explosives, and radioactive material, but may include others. The most likely products to contain asbestos are sprayed on fireproofing, insulation, boiler lagging, and pipe covering.
27.2. Asbestos:
27.2.1. The Contractor is warned that exposure to airborne asbestos has been associated with four diseases: lung cancer, certain gastrointestinal cancers, pleural or peritoneal mesothelioma, and asbestosis.
27.2.2. Studies indicate there are significantly increased health dangers to persons exposed to asbestos who smoke, and further to family members and other persons who become indirectly exposed as a result of the exposed worker bringing asbestos laden work clothing home to be laundered.
27.2.3. The Contractor is advised that friable and/or non-friable asbestos containing material may be encountered in areas where contract work is to be performed. Friable asbestos containing materials are any materials that contain more than one percent asbestos by weight that hand pressure can crumble, pulverize, or reduce to powder when dry. Non-friable asbestos containing materials are materials in which asbestos fibers are bound by a matrix material, saturant, impregnate or coating. Non-friable asbestos containing materials do not normally release airborne asbestos fiber during routine handling and end use. However, excessive fiber concentrations may be produced during controlled abrading, sanding, drilling, cutting, machining, removing, demolishing, or other similar activities.
27.2.4. Care must be taken to avoid releasing, or causing to be released, asbestos fiber into the atmosphere where they may be inhaled or ingested.
27.2.5. OSHA has set standards at 29 CFR 1926.1101 for exposure to airborne concentrations of asbestos fibers, methods of compliance, medical surveillance, housekeeping procedures and measures that must be taken when working with or around asbestos containing materials. 29 CFR 1926 has been identified as applicable to construction. The Environmental Protection Agency (EPA) has established standards at 40 CFR 61.140-156 for the control of asbestos emissions to the environment and the handling and disposal of asbestos wastes.
27.2.6. Friable asbestos containing materials are not permitted by current criteria and shall not be used in new construction or modification projects (ETL 1110-1-118, 27 May 83). Plans and specifications for all new construction and modification projects will be reviewed to ensure that friable asbestos containing materials are not used.
27.2.7. Maintenance, modification, or demolition activities where exposure to asbestos dust may occur from previously installed friable or non-friable asbestos containing materials will be identified.
All precautions, to include proper work practices, medical surveillance, respiratory protection, industrial hygiene, and environmental protection requirements of OSHA, EPA, and DA Circular 40-83-4, as applicable, shall be strictly adhered to.
27.3. Safety Assurance:
27.3.1. Safety Meeting. If required, representatives of the Contractor shall meet with the CO prior to task order implementation for the purpose of reviewing the Contractor’s safety and health programs and discussing implementation of all safety and health provisions pertinent to work to be performed under the contract. The Contractor shall be prepared to discuss, in detail, the measures intended to be taken in order to control any unsafe or unhealthy conditions associated with the work to be performed under the contract. This meeting may be held in conjunction with the preconstruction conference, if so directed by the Contracting Officer. The conduct of this meeting is not contingent upon a general preconstruction meeting. The level of detail for the safety meeting is dependent on the nature of the work and the potential inherent hazards. The Contractor’s principal on-site representative(s), the general superintendent, and the safety representative shall attend this meeting.
27.3.2. Compliance with Regulations. All work, including the handling of hazardous materials or the disturbance or dismantling of structures containing hazardous materials shall comply with the applicable requirements of 29 CFR 1926/1910. Work involving the disturbance or dismantling of asbestos or asbestos containing materials, the demolition of structures containing asbestos, and the disposal and removal of asbestos shall also comply with the requirements of 40 CFR, Part 61, subparts A and M; ETL 1110-1-118; and DA Circular 40-83-4. All work shall comply with applicable state and local safety and health requirements. Where there is a conflict between applicable regulations, the most stringent requirement shall apply. The Contractor or any of his subcontractors responsible for handling hazardous or toxic materials shall have the necessary certification(s) before doing so.
27.3.3. Contractor Responsibility. The Contractor shall assume full responsibility and liability for compliance with the applicable regulations pertaining to the health and safety of personnel during the execution of work. The Contractor not shall hold the Government responsible for any action on the part of the Contractor, or that of the Contractor’s employees or subcontractors, which results in illness, injury, or death.
27.3.4. Inspections, Tests and Reports. The inspections, tests, and reports made by the Contractor, subcontractors, specially trained technicians, equipment manufacturers, or others as required by a task order, shall be furnished in accordance with the terms of the task order. A report shall consist of the results of the tests with explanations and recommendations.
27.3.5. Materials and Equipment. Special facilities, devices, equipment, clothing, and similar items used by the Contractor in the execution of work shall comply with applicable regulations.
27.3.6. Hazardous Materials. The Contractor shall bring to the attention of the Contracting Officer any previously unknown material suspected of being hazardous which is encountered during the execution of work. 66 CES personnel will make a determination on how to proceed in such instances, and the Contractor shall be promptly notified of the subsequent actions to take.
28. RECORDING AND PRESERVING HISTORICAL AND ARCHEOLOGICAL FINDS:
28.1. All items having any apparent historical or archeological interest which is discovered in the course of any contract activities shall be carefully preserved. The Contractor shall leave archeological finds undisturbed and shall immediately report the find to 66 ABG/CEso that proper authorities may be notified.