Attach_1_Paving_Specifications.pdf

PDF 534 KB Posted

Attached to
Paving IDIQ Federal contract opportunity
Solicitation number
FA2823-14-R-4019
Issued by
Department of the Air Force Materiel Command Test Center

About this file

Paving Specification

View the file

Other files for this federal contract opportunity

Other files attached to Paving IDIQ, newest first.
File Type Posted
FA2823-14-R-4019_Amendment_04.pdf PDF
FA2823-14-R-4019_Paving_IDIQ_20_August_2014.pdf PDF
Attach_3_Bid_Schedule_Revised_18_Aug_14.xlsx XLSX spreadsheet
Q A_2.pdf PDF
FA2823-14-R-4019_Paving_IDIQ_11_August_2014.pdf PDF
Amendment_03_FA2823-14-R-4019.pdf PDF
Aerial_Photo.pdf PDF
FA2823-13-R-4019_L M_Paving_Rev_8-8-2014.pdf PDF
Attach_3_Bid_Schedule_Revised_8-8-14.xlsx XLSX spreadsheet
Paving_IDIQ_Q A_30_July_14.pdf PDF
Attach_3_Bid_Schedule.xlsx XLSX spreadsheet
FA2823-14-R-4019_Paving_IDIQ_Revised_Solicitation.doc DOC document
Amendment_02_FA2823-14-R-4019.pdf PDF
Amendment_01_FA2823-14-R-4019.doc DOC document
Attach_3_Bid_Schedule.pdf PDF
Attach_9_APPENDIX_C.pdf PDF
Attach_12_Seed_Statement_of_Work.pdf PDF
FA2823-14-R-4019_Paving_IDIQ_2014.doc DOC document
Attach_5_CAB_Affidavit.pdf PDF
Attach_7_APPENDIX_A.pdf PDF
Attach_8_APPENDIX_B.pdf PDF
Attach_4_Contract_Bonds_Checklist.pdf PDF
Attach_10_WD_3_Jan_2014.pdf PDF
Attach_11_Statement_of_Work.pdf PDF
Attach_6_Base_Access_Memorandum_Template.doc DOC document
Attach_2_Safety_Requirements.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT NO. EGL 13-1129 SPECIFICATION NO. 13AJ

HEADQUARTERS

AIR ARMAMENT CENTER (AFMC)

EGLIN AIR FORCE BASE, FLORIDA

SPECIFICATION

FOR

IDIQ FOR PAVING

EGLIN AIR FORCE BASE, FLORIDA

11 March 2013

96 CIVIL ENGINEERING GROUP (96 CEG/CECC)

INDEX

SECTION NUMBER TITLE PAGE NO.

01010 GENERAL PARAGRAPHS 01010-1 - 01010-2

01500 ENVIRONMENTAL PROTECTION 01500-1 - 01500-2

01540 AFFIRMATIVE PROCUREMENT 01540-1 - 01540-7

02050 DEMOLITION AND REMOVAL 02050-1 - 02050-2

02210 GRADING AND EARTHWORK 02210-1 - 02210-3

02221 EXCAVATION, TRENCHING, AND BACKFILLING 02221-1 - 02221-2

FOR UTILITY LINES

02234 BASE AND SUBBASE COURSES FOR

AIFFIELD PAVEMENTS 02234-1 - 02234-5

02430 STORM DRAINAGE 02430-1 - 02430-3

02485 GRASSING BY SEEDING AND 02485-1 - 02485-2

SODDING

02500 PAVING 02500-1 - 02500-3

02513 BITUMINOUS PAVEMENT FOR

AIRFIELD 02513-1 - 02513-17

02561 CONCRETE PAVEMENT FOR AIRFIELD

PAVEMENTS 02561-1 - 02561-14

02577 AIRFIELD AND ROADWAY TRAFFIC

MARKINGS 02577-1 - 02577-3

02578 JOINT SEALING IN CONCRETE

PAVEMENTS, PREFORMED ELASTOMERIC

TYPE 02578-1 - 02578-3

02579 SEALING AND RESEALING OF JOINTS AND 02579 - 1 - 02579 - 4

CRACKS IN CONCRETE PAVEMENT

02590 RUBBER AND PAINT REMOVAL ON AIRFIELD 02590-1

SURFACES

03300 CONCRETE WORK 03300-1 - 03300-7

10450 MISCELLANEOUS SPECIALTIES 10450-1

SECTION 01010

GENERAL PARAGRAPHS

1. GENERAL INTENTION: It is the declared and acknowledged intention for the contractor to provide three Delivery Orders, paving, grading, drainage construction, and other associated work.

2. GENERAL DESCRIPTION: In general, the work under this contract consists of furnishing all labor, materials as required, travel, surveying, equipment and service, and performing all operations required, in accordance with Plans and Technical Specifications. The principal items of work described here will in no way limit the responsibility of the Contractor to perform all items of construction specified on the drawings or in the Technical Specifications. The work may consist of resurfacing, full depth reconstruction, and new full depth construction of bituminous concrete and portland cement concrete pavements to include roadways, parking lots, and sidewalks, coldplaning of bituminous concrete pavement, construction of curb return widenings, new construction of bituminous concrete ramp-downs, crack repair in bituminous concrete pavement, new construction of concrete foundation walls and footings, slabs on grade adjusting of covers and frames and grates to be flush with new pavements, removal and resetting of existing concrete curbing, painting new pavement markings, rubber removal from airfield surfaces, and removal and reinstallation of existing parking bumper blocks and traffic control devices as well as placement of new parking bumper blocks and traffic control devices as required.

The above general description of work does not in any way limit the responsibility of the contractor to perform all work and furnish all labor, materials, and equipment complete in accordance with the plans and specifications.

3. LOCATION: The work shall be located at Eglin Air Force Base, Florida. The exact location of work will be indicated by the Contracting Officer with each delivery order.

4. SITE INSPECTION: The contractor shall be expected to visit the area of work and verify all conditions and dimensions.

5. RECORD DRAWINGS: The contractor shall maintain at the job site two sets of full size contract drawings, marking them in red to show all variations between the construction actually provided and that indicated or specified in the contract documents, including buried or concealed construction. Where variations in scope or character of work from that of the original contract are authorized, the drawings shall be marked to define the construction actually provided. The representations of such changes shall conform to standard drafting practice and shall include such supplementary notes, legends, and details as necessary to clearly portray the as-built construction. On completion of the work, both sets of marked-up drawings shall be delivered to the Contracting Officer and shall be subject to this approval before acceptance.

6. STORM PROTECTION: Should warnings of wind of gale force or stronger be issued, the contractor shall take every practicable precaution to minimize danger to persons, to the work, and to adjacent property. These precautions shall include closing all openings, removing all loose materials, tools, and equipment from exposed locations, and removing or securing scaffolding and other temporary work.

7. INTERFERENCE WITH STATION OPERATIONS: Permission to interrupt any station utility, communication, operational or traffic service or pattern in accordance with a delivery order shall be requested in writing at least 10 days prior to the date of the desired interruption. The Contractor shall receive approval in writing from the Contracting Officer before the requested interruption may be put into effect.

8. DEFINITION OF CONTRACTING OFFICER: Any reference made herein to the Contracting Officer shall include the Contracting Officer as well as a designated representative, which could be the Project Engineer and/or the Construction Inspector.

01010-1

9. TIME OF WORK: In addition to normal daytime work, the Contractor shall be required to conduct all operations specified herein during evenings and weekends, if so directed by the Contracting Officer. The evening shall be defined as the period after official sunset and before official sunrise. Weekends shall be defined as the period between 12:00 a.m. Saturday morning through 11:59 p.m. on Sunday evening. Work during all other times shall be considered daytime work. Costs associated with work done during evening/weekend hours shall be kept separate from costs associated with work done during the day. To accomplish this, the Contractor shall have an evening/weekend factor rate, by which he can multiply the day prices in order to come up with an evening/weekend cost. Should evening/weekend work be required in addition to normal daytime work, the Contracting Officer will work provide the Contractor with an overall percentage of work to be accomplished during evening/weekend hours.

10. EMERGENCIES: The Contracting Officer may require the contractor to work hours and days not considered normal business hours to repair infrastructure/roads due to natural disasters such as hurricanes. The contractor shall reflect his work schedule pricing as night work/weekend for such emergency work. Past emergency work due to named hurricanes which have impacted the Eglin AFB ranges requires these mission critical sites and the infrastructure supporting these sites be repaired in a timely manner. Contractor shall have the capacity in his work schedule, materials, personnel, and equipment to support such a need should a natural disaster occur.

11. SPECIFICATIONS: The specifications and standards listed herein are subject to change due to rewrites, updates, or changes in industry standards. Therefore, any specifications/standards which have been rewritten and or updated as the current specification/standard shall supersede the previous specification/standard for which it replaced.

01010-2

SECTION 01500

GENERAL ENVIRONMENTAL PROTECTION

1. SCOPE: This section covers environmental protection in general. Specific environmental requirements are included in other appropriate sections of the specifications. Additional general environmental requirements are included in the General Provisions of the contract. The provisions of this section are in addition to the aforementioned requirements. Where the general provisions of this section conflict with specific requirements elsewhere, the specific requirements shall control.

2. GENERAL: The contractor shall comply with all applicable local, state, federal, and Air Force environmental regulations. These items include, but are not limited to the following:

a. Vehicles and other powered equipment shall meet all applicable air quality regulations for emissions.

Equipment shall be mechanically sound and have all seals, grease rings, and other containment systems in place to prevent leakage. Drip pans shall be maintained such that overflow and spills do not occur. Associated waste shall be handled in accordance with all applicable regulations. There shall be no activities for equipment maintenance including oil changes, filter replacements, or hydraulic equipment repair performed on base without prior approval by the contracting officer.

b. All solid waste shall be collected and disposed of on a daily basis. There shall be no accumulation of solid waste unless properly containerized or put within a fenced area to prevent material from being blown about by the wind. No liquids shall be put into base dumpsters. This includes paints, oils, chemicals, compressed gas, pesticides, and other similar materials. Dried paint cans will be allowed in dumpsters only if such cans do not contain lead, chromium, cadmium, or other hazardous materials.

c. All Hazardous wastes such as sandblast media, chlorinated solvents, paint, paint thinners, cleaners, and fuels shall be labeled and an inventory management system shall be initiated to ensure timely removal and proper disposal.

No on-base disposal will be allowed.

(1) All drums shall be labeled with a hazardous waste label. The label shall include the proper DOT shipping name, UN or NA, EPA waste number, generator information, and accumulation start date. The label shall be placed on the side of the drum.

(2) All drums used to store hazardous waste shall be nonleaking and safe to handle. Drums that are rusted, dented, or leaking shall be overpacked. Drums and/or overpacks shall be provided by the contractor. All drums shall be DOT approved containers.

(3) Storage of drums shall be approved by the Contracting Officer prior to the generation of hazardous waste. The contractor shall document inspection of drums for leaks on a daily basis or if not working in the area daily, then a weekly inspection will suffice. A drum shall be disposed within 90 days of the first drop in the container. A copy of the inspection checklist shall be forwarded to the Contracting Officer every Friday.

(4) Hazardous waste drums shall be stored at an approved accumulation site. A sign identifying the site as an accumulation site, and listing two points of contact, shall be placed in a highly visible location.

(5) Hazardous waste transportation and disposal shall be coordinated through the Contracting Officer. The transporters and disposal facilities shall be approved by the Contracting Officer prior to their use.

01500-1

d. Hazardous Materials: The contractor shall submit to the Contracting Officer a list of all hazardous materials to be brought onto Eglin AFB property prior to the onset of any work. The list shall include all paints, solvents, POL products, pesticides, etc. to be used during the duration of the contract. All newly identified requirements for hazardous materials shall be coordinated with and approved by the Contracting Officer, who will work with the Compliance Division of the Environmental Management Directorate (EMC), prior to bringing the material on Eglin property.

e. Fuel storage shall be limited to 500 gallons and shall be contained in a government approved portable tank. Siting of the tanks shall be approved by the Contracting Officer, with coordination through the Base Fire Department and AFDTC/EMC.

f. Storage of oils, greases, chemicals, or other liquids shall require a fully contained facility for spill prevention and security. A minimum of 40 pounds of absorbent material per 44 gallons of chemical/oil/grease shall be on hand for spill control.

g. All spills shall immediately be reported to the Eglin Consolidated Command Post (882- 3278) or the Base Fire Department dispatch desk (911). Information as to spill location, type of material, and estimated time when the spill occurred shall be provided. The contractor shall ensure appropriate personnel protective equipment (PPE) is available to take care of spill cleanup and handling of residues of materials under their control.

h. Spray painting shall be conducted by using low-volatile organic chemical (VOC) paint technology or water base paints.

i. Contractor sites (i.e. trailer and storage sites) shall be properly maintained at all times. Repair of all damage due to improper erosion control shall be the responsibility of the contractor. Release of the site by the contractor will be accomplished by a final contractor site review, at which time site deficiencies will be noted.

The contractor shall have 14 calendar days ( beyond the contract completion date if necessary) to correct all deficiencies. The contract completion date will not be changed due to any of the required site review actions.

Contractor shall obtain approval from the contracting officer for on base storage areas. The contractor shall remove any and all surplus materials and demolition debris from Eglin property per each delivery order. Storage of any reusable surplus material at an approved storage area will require approval from the contracting officer.

Final payment on a delivery order will not be made until the construction site and storage area has been inspected and approved by the contracting officer’s representative.

j. Asbestos: If the contractor encounters unforeseen site conditions including, but not limited to, suspected asbestos containing materials during the performance of this contract, the contractor shall cease operations in the suspect area, immediately evacuate all personnel, and notify the Contracting Officer, the construction inspector, and EM. Samples will be taken and analyzed by the Government.

k. Banned Ozone Depleting Chemicals: All equipment using any Class 1 ozone depleting chemicals (ODCs) for a fire suppressant, refrigerant or solvent shall be banned from acquisition or use unless it has an Air Force waiver. This shall include, but is not limited to, systems using Class 1 ODCs such as halon 1211, halon 1301, R-11 (trichlorofluoromethane), R-12 (dichlorodifluoromethane), R-113 (trichlorotrifluoroethane), R-114 (dichlorotetrafluoroethane), R-115 (chloropentafluoroethane), and all azeotropic mixtures containing controlled chemicals such as CFC 500, 501, 502, and 504.

l. Ground Contamination: If suspected contamination is encountered during excavation activities (often indicated by unusual colors or odors), the contractor shall contact the Contracting Officer immediately.

m. Environmental Training: Specific contractor personnel may be required to attend Hazard Communications (HazCom) Training and Hazardous Waste Seminars held bi-annually at Eglin AFB at no expense to the contractor. If the contractor has a HazCom Program in place and can provide proof of such program, then the HazCom Training can be waived. Proof of an existing HazCom Program shall be provided to the environmental management representative at the pre-construction meeting and updated annually.

1500-2

SECTION 01540

AFFIRMATIVE PROCUREMENT

PART 1 GENERAL

1.01 RELATED SPECIFICATION SECTIONS:

A. Section 01010 – GENERAL REQUIREMENTS

1.02 AFFIRMATIVE PROCUREMENT & POLLUTION PREVENTION

A. Affirmative Procurement is a mandatory component of the Air Force pollution prevention program. The AF Installation Pollution Prevention Program Guide includes this goal for Affirmative Procurement: “100% of all products purchased each year in each of U.S.

EPA’s ‘Guideline Item’ categories shall contain recycled materials meeting U.S. EPA’s Guideline Criteria.”

B. Currently, reporting of affirmative procurement purchases is limited to contracts having a total value greater than $100,000 which includes the purchase of any amount of U.S. EPA-designated items.

C. This document contains guidelines for implementing the RCRA, EO, DOD, and Air Force requirements.

1.03 INTENT

A. The intent of this section is to increase the awareness of all contractors as to the availability of products manufactured from or that contain recycled materials, thereby increasing the use of these products in the construction of this project.

B. The various sections of the specifications contain references to products to be used in the construction of this project. The listed product may or may not be manufactured from or contain recycled materials. Therefore all contractor(s), subcontractors, equipment suppliers and material suppliers are responsible for compliance with this specification, particularly paragraph

1.09 and those items/products listed in paragraph 2.01. Recycled products shall be used wherever possible subject to the exemptions as per paragraph 1.09.

C. Substitution of recycled materials or recycled products for specified products are subject to the provisions of paragraph 1.05 Submittals.

1.04 AUTHORITY & REFERENCES:

A. The Resource Conservation and Recovery Act (RCRA), section 6002 (42 U.S.C. 6962)

B. Executive Order (EO) 13101, Greening the Government through Waste Prevention, Recycling, and Federal Acquisition.

C. Title 40, Code of Federal Regulations (CFR), Part 247, Comprehensive Procurement

Guideline for Products containing Recovered Material.

D. Federal Acquisition Regulations (FAR)

E. Engineering Technical Letter (ETL) 00-1: EPA Guideline Items in Construction and Other Civil Engineering Specifications

01540-1

1.05 SUBMITTALS

A. Product Data: Submit manufacturer’s material specifications, installation instructions, physical characteristics, B. Manufacturer’s Certificate: Certify that products meet or exceed the specified requirements.

1.06 RECYCLED OR RECOVERED PRODUCTS

A. Those construction materials identified in paragraph 2.01 at the end of this section.

1.07 QUALITY ASSURANCE

A. Manufacturer: Companies specializing in the manufacture of products that comply with the requirements of this section with a minimum of three (3) years documented experience.

1.08 DEFINITIONS:

A. AFFIRMATIVE PROCUREMENT: The purchase of environmentally preferable products manufactured from recycled and reclaimed materials.

B. ACQUISITION: The acquiring by contract with appropriated funds for supplies or services (including construction) by and for the use of the Federal Government through purchase or lease, whether the supplies or services are already in existence or must be created, developed, demonstrated, and evaluated. Acquisition begins at the point when agency needs are established and includes the description of requirements to satisfy agency needs, solicitation and selection of sources, award of contracts, contract financing, contract performance, contract administration, and those technical and management functions directly related to the process of fulfilling agency needs by contract.

C. CONTRACTOR (S): The prime contractor, subcontractors, material suppliers, and equipment suppliers who provide the products that will be used in the construction of this project.

D. ENVIRONMENTALLY PREFERABLE: Products or services having a lesser or reduced effect on human health and the environment when compared to competing products or services, serving the same purpose. This comparison may consider raw materials acquisition, production, manufacturing, packing, distribution, reuse, operation, maintenance, or product or service disposal. (EO 13101)

E. EPA DESIGNATED ITEM: An item that is or can be made with recovered material; that is listed by the Environmental Protection Agency (EPA) in a procurement guideline (40CFR, part 427); and for which EPA has advised purchasing recommendations in a related Recovered materials Advisory Notice (RMAN). (FAR 23.402)

F. EXECUTIVE AGENCY OR AGENCY: An executive agency as defined in 5 U.S.C. 105.

For the purpose of this order, military departments, as defined in 5 U.S.C. 102 are covered under the auspices of the Department of Defense.

G. FORM: The Affirmative Procurement Reporting Form found at the end of this section.

H. POLLUTION PREVENTION: Source reduction as defined in the Pollution Prevention Act of 1990 (42 U.S.C. 13102), and other practices that reduce or eliminate the creation of pollutants through (a) increased efficiency in the use of raw materials, energy, water, or other resources; or (b) protection of natural resources by conservation.

01540-2

I. PRODUCT: Materials and equipment that will be used in the construction of this project.

J. POSTCONSUMER MATERIAL: A material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. “Postconsumer material” is a part of the broader category of “recovered material”.

K. PROCUREMENT: The purchase and providing of products to be used in the construction of this project.

L. RECOVERED MATERIALS: Waste materials and by-products which have been recovered or diverted from solid waste, but such term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process. (EO 13101, 42 U.S.C. 6903 (19) and FAR 23.402)

M. RECYCLABILITY: The ability of a product or material to be recovered from or otherwise diverted from the solid waste stream for the purpose of recycling. (EO 13101)

N. RECYCLING: The series of activities, including collection, separation, and processing by which products or other materials are recovered from the solid waste steam for use in form of raw materials in the manufacture of new products other than fuel for producing heat or power by combustion. (EO 13101)

O. RECYCLED MATERIAL: A material utilized in place of raw or virgin material in product manufacturing consisting of materials derived from postconsumer waste, industrial scrap, materila derivived from agricultureal wastes, and other items, all of which can be used in new product manufacturer. (EPA Guidelines & OFPP Policy Letter 92-4)

P. RECYCLED PRODUCT: A recycled product is one made completely or partially from waste materials or by-products recovered or diverted from the solid waste stream.

Q. SOLID WASTE: Garbage, refuse, sludges and other discarded materials including those from industrial, commercial, and agricultural operations, and from community activities. This excludes solids or dissolved materials in domestic sewage or other significant pollutants in water resources, such as silt, dissolved or suspended solids in industrial waste water effluents, dissolved materials in irrigation return flow, etc. (EPA Guidelines)

R. SPECIFICATION (S): A clear and accurate description of the technical requirements for materials, products, or services including the minimum requirement for materials’ quality and construction and any equipment necessary for an acceptable product. In general, specifications are in the form of written descriptions, drawings, prints, commercial designations, industry standards, and other descriptive references.

S. UNREASONABLE PRICE: If the cost of the recycled content product exceeds the cost of a non-recycled item, the Air Force considers the cost to be unreasonable. (Air Force Affirmative Procurement Plan)

T. VERIFICATION: Procedures used by procuring agencies to confirm both vendor estimates and certifications of the percentages of recovered materials contained in the products supplied to them or to be used in the performance of a contract. (EPA Guidelines)

U. WASTE PREVENTION: Any change in the design, manufacturing, purchase, or use of materials or products (including packaging) to reduce their amount or toxicity before they are discarded. Waste prevention also refers to the reuse of products or materials.

01540-3

V. WASTE REDUCTION: Preventing or decreasing the amount of waste being generated through waste prevention, recycling, or purchasing recycled and environmentally preferable products.

1.09 EXEMPTIONS

A. U.S. EPA recommends minimum content levels for those items listed at paragraph 1.10. The minimum content levels can be found at www.epa.gov/cpg. These levels are mandatory unless one of the following exemptions applies. RCRA provides the following exemptions from the requirement to purchase EPA-designated items:

1. The product is not available from a sufficient number of sources to maintain a satisfactory level of competition (i.e., available from two or more sources).

2. The product is not available within a reasonable period of time.

3 The product does not meet the performance standards in applicable specifications or fails to meet reasonable performance standards of the procuring agency.

4. The product is not available at a reasonable price. For Air Force purposes, “unreasonable price” is defined as follows: If the price of the recycled-content product exceeds the cost of a non-recycled item, then the price is considered unreasonable.

1.10 U.S. EPA-DESIGNATED ITEMS

A. The 54 U.S. EPA-designated items are listed below. Not all of these materials may be required in the construction of this project. Please refer to the drawings and specifications.

B.

1. PAPER PRODUCTS

Item 1: All paper and paper products, excluding building and construction paper grades.

2. VEHICULAR PRODUCTS

Item 2: Lubricating oils containing re-refined oil, including engine lubricating oils, hydraulic fluids, and gear oils, but excluding marine and aviation oils.

Item 3: Tires, excluding airplane tires.

Item 4: Reclaimed engine coolants, excluding coolants used in non-vehicular applications.

3. CONSTRUCTION PRODUCTS

Item 5: Building insulation products.

Item 6: Structural fiberboard products for applications other than building insulation.

Item 7: Laminated paperboard products for applications other than building insulation.

Item 8: Cement and concrete, including products such as pipe and block, containing fly ash.

Item 9: Cement and concrete, including concrete products such as pipe and block, containing ground-granulated blast furnace (GGBF) slag.

Item 10: Carpet made of polyester fiber for use in low- and medium-wear applications.

Item 11: Floor tiles containing recovered rubber or plastic.

Item 12: Patio blocks containing recovered rubber or plastic.

Item 25: Shower and restroom dividers/partitions containing recovered steel or plastic.

Item 26: Reprocessed and consolidated latex paint for specific uses.

Item 37: Carpet cushion.

Item 38: Flowable fill.

Item 39: Railroad grade crossing surfaces.

01540-4

4. TRANSPORTATION PRODUCTS

Item 13: Traffic barricades used in controlling or restricting vehicular traffic.

Item 14: Traffic cones used in controlling or restricting vehicular traffic.

Item 27: Parking stops.

Item 28: Channelizers used as temporary traffic control devices.

Item 29: Delineators used as temporary traffic control devices.

Item 30: Flexible delineators used as temporary traffic control devices.

5. PARK AND RECREATION PRODUCTS

Item 15: Playground surfaces containing recovered rubber or plastic.

Item 16: Running tracks containing recovered rubber or plastic.

Item 31: Plastic fencing.

Item 40: Park benches and picnic tables.

Item 41: Playground equipment.

6. LANDSCAPING PRODUCTS

Item 17: Hydraulic mulch products containing recovered paper or recovered wood.

Item 18: Compost made from yard trimmings, leaves, and/or grass clippings.

Item 32: Garden and soaker hoses containing recovered rubber or plastic.

Item 33: Lawn and garden edging containing recovered rubber or plastic.

Item 42: Food waste compost.

Item 43: Plastic lumber landscaping timbers and posts.

7. NON-PAPER OFFICE PRODUCTS

Item 19: Office recycling containers.

Item 20: Office waste receptacles.

Item 16: Plastic desktop accessories.

Item 22: Toner cartridges.

Item 23: Binders.

Item 24: Plastic trash bags.

Item 34: Printer ribbons (re-inked ribbons or re-inking equipment/service for ribbons).

Item 35: Plastic envelops.

Item 44: Solid plastic binders.

Item 45: Plastic clipboards.

Item 46: Plastic file folders.

Item 47: Plastic clip portfolios.

Item 48: Plastic presentation folders.

8. MISCELLANEOUS PRODUCTS

Item 36: Pallets.

Item 49: Sorbents.

Item 50: Industrial drums.

Item 51: Awards and plaques.

Item 52: Mats.

Item 53: Signage, including supports and posts.

Item 54: Manual grade strapping.

1.11 APPLICABILITY

A. These requirements apply to all contractors employed in the construction of this project.

B. Please direct all questions regarding the plan to the contracting officer or designated representative.

01540-5

PART II PRODUCTS

2.01 PARTIAL LIST OF PRODUCT SOURCES & INFORMATION

GENERAL DATA:

1. Comprehensive Procurement Guidelines, epa.gov/cpg 2 Environmental Building News, www.ebuild.com

3. Certified Forest Products Council, www.cerifiedwood.org/

4. Wiley Series in Sustainable Design, www.wiley.com/

5. The Carpet and Rug Institute, www.carpet-rug.com/

6. Information, McGraw-Hill, dialogue@mcgraw-hill.com

7. Florida Directory of Recycled Product Vendors, www.2.dep.state.fl.us/waste/programs/rbac/downloads/rbac_dir.pd

8. Oikos Green Building Source, News, searchable products data base, library, www.oikos.com

9. Green Design Network, News, publications, databases, www.greendesign.net

10. Green Works Recycled Content7 Product Guide, detailed vendors directory, www.metrokc.gov/greenworks/recycontent.htm>

B. DIVISION 03, CONCRETE

1. GranCem, granulated blast-furnace slag, www.grancem.com/

2. Syndesis, cement-based, pre-cast product workable with wood tools, www.syndesisinc.com/

C. DIVISION 04, MASONRY

1. Heble Building Systems, autoclaved aerated concrete blocks, www.heble.com/ 2 Ytong Florida Ltd., autoclaved aerated concrete blocks, www.ytong-usa.com/

D. DIVISION 06, WOOD & PLASTICS

1. Avonite, solid surfacing, www.avonite.com/

2. Chemical Specialties, wood treatment, www.treatedwood.com/

3. Homasote Company, structural fiberboard, www.homasote.com/

4. Isobar, fiberboard composed of straw fibers and non-toxic resins, www.isoboard.com/

5. Trashiest Mac Millan, engineered wood products, www.homasote.com/

E. DIVISION 07, Thermal & Moisture Protection

1. Duro-Last Roofing, recycled PVC walkway pads, 1-800-2480280

2. Johns Manville, Insulation products, www.jm.com/

3. Majestic Skylines, rubber-based slate-look roofing for steep roofs, www.majesticskylines.com/

4. Owens-Corning, insulation products, www.owenscorning.com/

F. DIVISION 08, DOORS & WINDOWS

1. Marvin Window & Door, windows, some meeting “Energy Star Label”, www.marvin.com/

2. Pella, energy efficient windows, www/pella.com/

G. DIVISION 09, FINISHES

1. Armstrong World Industries, Inc.-Flooring Systems, www.armstrong-floors.com/

2. Armstrong World Industries, Inc.-Ceiling Systems, www.ceilings.com/

3. Benjamin Moore & Co., VOC free acrylic interior latex paint, www.benjaminmoore.com/

4. CanFibre Group Ltd., all-green medium-density fiberboard, www.canfibre.com

5. Chemrex Inc., low-e interior paint, www.chemrex.com/

6. Collins & Aikman Floor coverings, carpet with 100% post-consumer backing, www.powerbond.com/

01540-6 http://epa.gov/cpg http://www.ebuild.com/ http://www.cerifiedwood.org/ http://www.wiley.com/ http://www.carpet-rug.com/ mailto:dialogue@mcgraw-hill.com http://www.2.dep.state.fl.us/waste/programs/rbac/downloads/rbac_dir.pd http://www.oikos.com/ http://www.greendesign.net/ http://www.metrokc.gov/greenworks/recycontent.htm http://www.grancem.com/ http://www.syndesisinc.com/ http://www.heble.com/ http://www.ytong-usa.com/ http://www.avonite.com/ http://www.treatedwood.com/ http://www.homasote.com/ http://www.isoboard.com/ http://www.homasote.com/ http://www.jm.com/ http://www.majesticskylines.com/ http://www.owenscorning.com/ http://www.marvin.com/ http://www.armstrong-floors.com/ http://www.ceilings.com/ http://www.benjaminmoore.com/ http://www.canfibre.com/ http://www.chemrex.com/ http://www.powerbond.com/

7. DesignTex, Inc., polyester panel fabric made from 100% PET fiber, www.dtex.com/

8. Dodge-Regupol, Inc., 100% recycled rubber-flooring, www.regupol.com/

9. Eco-sensitive modular tile, vinyl tile with 100% recycled carpet-backing, www.powerbond.com/

10. Environmental Stone Products, stone manufactured from 100% recycled glass, www.environmentalstone.com/

11. Glidden: residential interior latex paints 100% free of VOC, www.icipaintstores.com/ 12 Homasote Inc., sound barrier, www.homasote.com/

13. Isobar Enterprises, Inc. panel made from wheat straw and non-toxic resins, 1-503-2427345

14. Marley-Flexco Co., flooring made form 95% recycled truck and bus tires, www.marleyflexco.com/

15. The Mat Factory, Inc., interlocking roll-up tiles made from 100% postconsumer tire rubber and PVC plastic from electric cable covers, 1-949-6453122

16. Permafirm Pad Co., carpet pads made from almost 100% recycled content, 1-800-3446977

17. Sherwin Williams, VOC compliant paints and enamels, www.sherwin.com/

18. SierraPine Limited, formaldehyde-free particleboard and medium density fiberboard containing recycled/recovered wood fiber, www.sierrapine.com/

19. Summittville Tiles, impervious porcelain tiles using feldspar tailings, www.summitville.com/ 20 Tectum, natural-fiber acoustical ceiling and wall panels, www.tectum.com/

21. Tiles with natural fibers, tiles made of a bio-alloy material and natural fibers, www.maderatile.com

22. USG Interiors, Inc., synthetic gypsum board, www.usg.com/

23. Decorative Architectural Tiles, floor, counter & wall tile made from 100 % postconsumer glass, 1-808-8857812

24. Forbo, linoleum-flooring utilizing renewable resources, www.forbo.com/

H. DIVISION 10, SPECIALTIES

1. The Access Store, modular ramping system made from 100% recycled rubber, www.accessstoe.com/

2. BP Solar, photovoltaic modules and systems, www.bp.com/bpsolar/index

3. Mecho Shade Systems, interior shadecloths, www.mechoshade.com/

4. R Control, structural insulated panel (SIP), www.mechoshade.com/

I. DIVISION 12, FURNISHINGS

1. Guilford of Maine, fabric from 100% recycled materials, www.terratex.com/

2. Phenix Biocomposites, tabletops made from soy based products free of petrochemicals, 1-

800-3248187

3. Safe Solutions, LLC, furniture manufactured from waste wood, 1-970-2473333

J. DIVISION 16, ELECTRICAL

1. Advance Transformer Company, linear reactor ballast, www.advancetransformer.com/

2. Artemide Inc., energy efficient cold-cathode lighting, www.artemide.com/

3. Edison Price Lighting, track mounted metal-halide PAR 30 &38 lamps, 1-212-5216995

4. Leviton Manufacturing Corporation, Inc., occupancy sensors, www.leviton.com/

5. Phillips Lighting, energy efficient compact fluorescent lamps, www.phillips.com/lighting 6 Osram Sylvania, mercury-free lamps and energy efficient fluorescent lamps, www.osramsylvania.com/

7. Sensor Switch, lighting control occupancy sensors, www.sensorswitch.com/

8. Venture Lighting, pulse-start high performance lamp and ballast system, www.venturelighting.com/

01540-7 http://www.dtex.com/ http://www.regupol.com/ http://www.powerbond.com/ http://www.environmentalstone.com/ http://www.icipaintstores.com/ http://www.homasote.com/ http://www.marleyflexco.com/ http://www.sherwin.com/ http://www.sierrapine.com/ http://www.summitville.com/ http://www.tectum.com/ http://www.maderatile.com/ http://www.usg.com/ http://www.forbo.com/ http://www.accessstoe.com/ http://www.bp.com/bpsolar/index http://www.mechoshade.com/ http://www.mechoshade.com/ http://www.terratex.com/ http://www.advancetransformer.com/ http://www.artemide.com/ http://www.leviton.com/ http://www.phillips.com/lighting http://www.osramsylvania.com/ http://www.sensorswitch.com/ http://www.venturelighting.com/

SECTION 02050

DEMOLITION AND REMOVAL

1. SCOPE: This section covers milling of existing asphalt pavement, complete.

2. APPLICABLE PUBLICATIONS. The publications listed below form a part of this specification and are incorporated herein. The publications are referred to in text by the basic designation only.

EM 385-1-1, 1 Jun 77, General Safety Requirements.

FL DOT SSRBC Section 327, Standard Specifications for Road and Bridge Construction, latest edition, Milling Existing Asphaltic Pavement.

3. UTILITY SERVICES: Contractor shall notify Contracting Officer for approval prior to removal or disconnecting of government-owned utilities.

4. PROTECTION OF EXISTING WORK: All existing building surfaces, utilities, equipment, and fixtures shall be protected by the contractor from damaged during work under this contract, and any damage to such items due to work under this contract shall be promptly repaired by the contractor at his own expense. Any taxiway lighting damaged by construction shall be repaired by the contractor at his expense.

5. DESCRIPTION OF WORK: a. Work specified shall consist of removing existing asphaltic concrete pavement by cold milling. Contour (header) cuts shall be required. The resulting asphalt aggregate shall become the property of the contractor and shall be removed from Government property and legally disposed of by the end of the project delivery order.

(1) Traffic Maintenance. The contractor shall maintain at least one lane of traffic in each direction;

however, from 7:30 a.m. to 3:30 p.m. local time, the contractor may be allowed to restrict traffic to one-way operations for short periods of time, provided adequate means of traffic control are effected, traffic is not unreasonably delayed and subject to Contracting Officer approval. The contractor shall be required to provide all flagmen, traffic cones, barricades, warning lights, signs, etc., necessary to provide for the safe and efficient flow of traffic. Also, the contractor shall submit a traffic plan for each delivery order at least 10 days in advance for review and approval by the Contracting Officer. Work shall not begin until this traffic plan has been approved.

The traffic plan shall include expected traffic flow and placement of flagmen, signs, cones, barricades, etc. All flagmen and traffic control personnel shall be required to have on their person a two-way radio or other communication device that gives them instant access to every member of the traffic control team and the contractor's general superintendent.

(2) Equipment. The equipment for this operation shall be a machine capable of maintaining a depth of cut and cross slope which will achieve the results specified herein. The machine shall be equipped with automatic grade controls which operate by sensing from one or more skids moving along the pavement surface and where required shall produce a skid resistant surface texture.

The machine shall be equipped with a means to effectively limit the amount of dust escaping from the removal operation. If the machine is equipped with preheating devices, special attention is directed to the fact that local environmental and other regulations governing operation of this type equipment may vary considerably from place to place. It shall be the contractor's responsibility to familiarize himself and comply with all such local regulations, as well as State and Federal rules, and to obtain all necessary permits.

(3) Construction. Where indicated on the drawings, removal shall be to a specified depth and shall produce a specified cross slope. The longitudinal profile of the milled surface shall be established by a skid sensor on the side of the cut nearest the centerline of the taxiway, street, road or parking lot. The cross slope of the milled surface shall be established by a second skid sensing device near the outside edge of the cut or by an automatic cross slope control mechanism. The contractor may elect to make multiple cuts to achieve the required configuration or depth of cut. The milling machine shall be operated to effectively minimize the amount of dust being emitted from the machine.

Prewetting of the pavement may be required.

02050-1

(4) Finished Surface. The finished base shall have a reasonably uniform texture and shall be within 1/4" of a true profile grade and shall have no deviation in excess of 1/4" from a 15' straightedge applied to the pavement perpendicular to the centerline. The contractor shall be required to have one 15' straightedge at the job site during all operations. Areas varying from a true surface in excess of the above stated tolerances may be accepted without correction if the Contracting Officer determines that they were caused by conditions over which the contractor could not have reasonably exercised control. Any unsuitable texture or profile, as determined by the Contracting Officer, shall be corrected by the contractor at no additional cost to the government.

(5) Milling Machine Travel Speed. The milling machine shall not mill at a rate faster than 20 feet per minute (FPM).

02050-2

SECTION 02210

GRADING (EARTHWORK)

1. SCOPE: The work covered by this section consists of furnishing all plant, labor, equipment and materials and performing all operations necessary in the clearing, excavating, grading and associated operations related to the construction of airfield pavements, roads, streets, railroads and culverts complete. Contractor to obtain NPDES Permits as necessary and pay all fees associated with obtaining such permits.

2. APPLICABLE PUBLICATIONS: The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.

a. Military Standards.

AFJMAN 32-1221 (I) Appendix B, Unified Soil Classification System AFJMAN 32-1221 (I) Chapter 2, Soils

b. American Society for Testing and Materials (ASTM) Publications.

D 698, Laboratory Compaction Characteristics of Soil Using Standard Effort

D 1196, Nonrepetitive Static Load Tests of Soils and Flexible Pavement Components, for Use in

Evaluation and Design of Airport and Highway Pavements

D 1556, Density of Soil in Place by the Sand-Cone Method.

D 1557-91, Laboratory Compaction Characteristics of Soil Using Modified Effort

D 1883, CBR of Laboratory-Compacted Soils

D 2167, Density of Soil in Place by the Rubber-Balloon Method.

D 2216 Laboratory Determination of Water Content of Soil and Rock

D 2487, Classification of Soils for Engineering Purposes (USCS)

D 6938, Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate in

Place by Nuclear Methods (Shallow Depth).

D 2937, Density of Soil in Place by the Drive-Cylinder Method

D 4318, Liquid Limit, Plastic Limit and Plasticity Index of Soils

c. Florida Department of Transportation Standard Specifications for Road and Bridge Construction (FLDOTSSRBC), latest edition.

Section 110, Clearing and Grubbing.

Section 120, Excavation and Embankment.

Section 125, Excavation for Structures and Pipe.

3. DEFINITIONS: a. Satisfactory Materials. Materials classified in ASTM D 2487, Unified Soil Classification System, as SC, SW, SP, GW, and GP are satisfactory.

b. Unsatisfactory Materials. Materials classified in ASTM D 2487, Unified Soil Classification System, as Pt, OH, and OL are unsatisfactory.

Unsatisfactory materials also include man-made fills, refuse or backfills for previous construction.

02210-1

c. Cohesionless and Cohesive Materials. Cohesive materials include materials classified as GG, SC, Ml, CL, MH, and CH. Cohesionless materials include materials classified in ASTM D 2487 as GW, GP, SW, and SP.

Materials classified as GM and SM will be identified as cohesionless only when the fines have a plasticity index of zero.

d. Degree of Compaction. Degree of compaction is a percentage of the maximum density obtained by the test procedure presented in ASTM D1557-91, Laboratory Compaction Characteristics of Soil Using Modified Effort. This will be abbreviated herein as a percent ASTM 1557-91 maximum density.

4. CLEARING AND GRUBBING: Clearing and grubbing shall be in accordance with FLDOTSSRBC, latest edition, Section 110, with the following exceptions:

a. Designation of Authority. Unless otherwise specified, wherever the designation "Engineer" or other state authority occurs in these specifications, such designations shall be changed to "Contracting Officer."

b. Sampling and Testing. Unless otherwise specified, all sampling and testing necessary to determine conformance with the requirements of this specification shall be performed by an approved commercial testing laboratory at the contractor's expense. Within 7 days after the samples were taken, results of all sampling and testing shall be submitted directly to the Contracting Officer by the lab for approval.

c. Payment. Delete reference to "payment" in the Florida specifications.

5. EXCAVATION: After all stripping has been completed, excavation of every description, regardless of material encountered, within the grading limits of the project shall be performed to the lines and grades indicated. Satisfactory excavation material shall be transported to and placed in fill areas within the limits of the work. All unsatisfactory material, including any soil which is disturbed by the contractor's operations or softened due to exposure to the elements and water, and surplus material shall be disposed of at locations indicated on the plans. Excavations carried below the depths indicated, without specific directions, shall, except as otherwise specified, be refilled to the proper grade with satisfactory material as directed. All additional work of this nature shall be at the contractor's expense.

Excavation and filling shall be performed in a manner and sequence that will provide drainage at all times.

Excavations shall be kept free from water while construction therein is in progress. Material required for fills in excess of that produced by excavation within the grading limits shall be obtained from borrow areas.

6. DITCHES, GUTTERS, AND CHANNEL CHANGES: Ditches, gutters, and channel changes shall be cut accurately to the cross sections and grades indicated. All roots, stumps, rock, and foreign matter in the sides and bottom of ditches, gutters, and channel changes shall be trimmed and dressed or removed to conform to the slope, grade, and shape of the section indicated. Care shall be taken not to excavate below the grades indicated. Excessive ditch and gutter excavation shall be backfilled to grade either with satisfactory, thoroughly compacted material or with suitable stone or cobble to form an adequate gutter paving as directed. All ditches and gutters excavated under this section shall be maintained until final acceptance of the work. Satisfactory material excavated from ditches and channel changes shall be placed in fill areas. Unsatisfactory and excess excavated material shall be disposed of in accordance with directions in paragraph, "Excavation". No excavated material shall be deposited closer to the edges of the ditches than indicated and in no case less than 3 feet.

7. BACKFILL ADJACENT TO STRUCTURES: Backfill adjacent to structures shall be placed and compacted uniformly in such manner as to prevent wedging action or eccentric loading upon or against the structures. Slopes bounding or within areas to be backfilled shall be stepped or serrated to prevent sliding of the fill. During backfilling operations and in the formation of embankments, equipment that will overload the structure in passing over and compacting these fills shall not be used. Backfill for storm drains and subdrains, including the bedding and backfill for structures other than culverts and drains, shall conform to the additional requirements in other applicable sections.

02210-2

8. PREPARATION OF GROUND SURFACE FOR FILL: All vegetation, such as roots, brush, heavy sods, heavy growth of grass, and all decayed vegetable matter, rubbish, and other unsatisfactory material within the area upon which fill is to be placed shall be stripped or otherwise removed before the fill is started. In no case will unsatisfactory material remain in or under the fill area. Sloped ground surfaces steeper than one vertical to four horizontal on which fill is to be placed shall be plowed, stepped or benched, or broken up, as directed, in such manner that the fill material will bond with the existing surface. Prepared surfaces on which compacted fill is to be placed shall be wetted or dried as may be required to obtain the compaction specified.

9. FILLS AND EMBANKMENTS: Fills and embankments shall be constructed at the locations and to lines and grades indicated. The completed fill shall conform to the shape of the typical sections indicated or shall meet the requirements of the particular case. Material removed from the excavation shall be used in forming the fill. Fill shall be satisfactory material and shall be reasonably free from roots, other organic material, and trash. The material shall be placed in successive horizontal layers of 8 to 12 inches in loose depth for the full width of the cross section and shall be compacted as required. Each layer shall be compacted before the overlaying lift is placed. If the material is excessively moist, it shall be aerated by blade graders, harrows, or other approved equipment.

10. COMPACTION: a. Other Than Paved Areas. Each layer of the fill or embankment shall be compacted by rolling with an approved tamping roller, pneumatic-tired roller, three-wheel power roller, or other compaction equipment or, where approved, by the construction equipment to at least 90 percent ASTM 1557-91 maximum density.

b. Paved Areas. Areas to be paved and other areas indicated as requiring compaction suitable for paved areas shall be compacted to at least the percentage of ASTM 1557-91 maximum density where for specific ranges of depth below the surface of the pavement. Compaction shall be accomplished by approved tamping rollers, pneumatic-tired rollers, three-wheel power rollers, or other approved compaction equipment. Compaction for base courses shall be IAW FL DOT Standard Specifications for Road and Bridge Construction, 2013 Section 204-6.3.

11. FINISHED EXCAVATION, FILLS, AND EMBANKMENTS: All areas covered by the project, including excavated and filled sections and adjacent transition areas, shall be uniformly smooth-graded. The finished surface shall be reasonably smooth, compacted, and free from irregular surface changes. The degree of finish shall be that ordinarily obtainable from blade-grader operations, except as otherwise specified. Ditches and gutters shall be finished to permit adequate drainage. The surface of areas to be turfed shall be finished to smoothness suitable for the application of turfing materials.