This document contains questions and responses related to a solicitation for renovating and equipping 17 Basic Rehabilitation Units throughout four Mexican states. The solicitation seeks a contractor to complete renovations at each site and purchase all required medical equipment within an 18-month period. The contractor will be responsible for shipping, importing, and sourcing equipment and supplies in the most economical manner. Subcontractors may be used if work is batched by region. Acceptable equipment substitutions are allowed. The U.S. Embassy in Mexico City will assist with vetting subcontractors. Labor costs must be broken down by category and materials listed in a bill of materials. Finishes should be commercially comparable to the local region. All questions must be submitted by August 7, 2020. The Department of the Air Force Space Command issued the solicitation.

View the file

Other files for this federal contract opportunity

Other files attached to NORAD/ USNORTHCOM J49 Mexico Basic Rehabilitation Units, newest first.
File Type Posted
Project 63972.pdf PDF
Project 63977.pdf PDF
Project 63975.pdf PDF
Project 63981.pdf PDF
Project 40827.pdf PDF
Project 63973.pdf PDF
Project 63967.pdf PDF
Project 63969.pdf PDF
Project 63968.pdf PDF
Project 63978.pdf PDF
Project 63979.pdf PDF
Project 63976.pdf PDF
Project 63974.pdf PDF
Project 63971.pdf PDF
Project 63970.pdf PDF
Project 40826.pdf PDF
Project 40828.pdf PDF
Guerrero Metlatonoc 1.pdf PDF
Guerrero Coyuca De Catala.pdf PDF
Guerrero Xochistlahuaca 2.pdf PDF
Chiapas Oxchuc one of two.pdf PDF
Guerrero Zirandaro 1.pdf PDF
Guerrero Coyuca De Catala 2.pdf PDF
Chiapas El Parral.pdf PDF
Chiapas Zinacantan.pdf PDF
Guerrero BuenaVista De Cue 2.pdf PDF
Guerrero Tlapa de Comonfort 3.pdf PDF
Veracruz Playa Vicente.pdf PDF
Guerrero Tlapa de Comonfort 1.pdf PDF
Guerrero BuenaVista De Cue.pdf PDF
Chiapas Oxchuc two of two.pdf PDF
Oaxaca San Juan Bautista Valle.pdf PDF
Guerrero Coyuca De Benitez.pdf PDF
Guerrero Metlatonoc 2.pdf PDF
Guerrero Xochistlahuaca 1.pdf PDF
Chiapas Altamirano.pdf PDF
Oaxaca San Felipe Jalapa de d.pdf PDF
Chiapas Ocosingo Two of two.pdf PDF
Guerrero Zirandaro 2.pdf PDF
Guerrero Tlapa de Comonfort 2.pdf PDF
Chiapas Ocosingo One of two.pdf PDF
Updated J49_Mexico_UBRs_Combo L and M.docx.docx DOCX document
QASP_J49_CRB 20-0011_29 May 20.docx DOCX document
Facility Schematics Compilation_UBRs.docx DOCX document
Attch 5 - FFP Pricing Summary Page.xlsx XLSX spreadsheet
J49_Mexico_UBRs_Combo L and M.docx DOCX document
Anticipated UBR Equipment.docx DOCX document
Solicitation - FA259520R0007.pdf PDF
6 PWS-Mexico_UBR Final.pdf PDF
Show all 49

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Who will purchase the medical equipment for each UBR?

A: Winning contractor should be able to complete the renovations and purchase the medical equipment.

2. Will any governmental agency (MX Agency) be performing any of the work, if so which ones?

A: No. However, in some localities, local governmental agencies are involved in current UBR’s facilities improvements (not included in the SOW), like painting, gardening, roofing, etc.

3. Will the shipping and delivery of the UBR equipment be arranged by United States government channels/agents or will the contractor/selected equipment vendor be responsible for the shipping of this equipment from its origin to each location?

A: Winning contractor is responsible for purchasing and shipping of all equipment and supplies listed. (Including importation processes in its case)

4. If the contractor intends to use locally licensed and qualified subcontractors/trades would it be acceptable for the contractor to batch the UBR’s by geographic region and assign them to specific, selected subcontractors?

A: The contractor can provide a schedule of when and how the work can be completed within the 18 month

5. Will the issuance of a certificate of occupancy (CO), or Mexican equivalent, and the installation of the medical equipment be sufficient to declare a specific UBR as completed and that particular phase of the project as “closed”?

A: Yes

6. Will the US Embassy staff in Mexico City be available to assist the contractor with any needed information regarding the business credentials, reputation or competency related to a specific subcontractor being vetted for possible local performance of work award?

A: Yes, ODC MX/HAP personnel will be available to assist the contractor, as far as possible, considering access limitations for needed information

7. Will contracts with potential subcontractors be required to be submitted in the initial response to the solicitation?

A: No

8. Is the anticipated UBR equipment list attached in the solicitation representative of the equipment for a single UBR or is it a combined list for all of them?

A: Combined list for all

9. Will the contracting officer allow clinically qualified substitutions to the UBR equipment list for items prohibited for transport or import to Mexico - i.e., paraffin, laser?

A: An or equal substitution is allowable. Proposed equipment list should be provided by contractor.

10. Is there a requirement for the contractor to purchase the medical equipment in Mexico or the United States or is the contractor free to choose the most economical and practically available sourcing?

A: Contractor should propose the most economical and practical sourcing.

11. The solicitation requires a breakdown in UBR construction costs. The breakdown consists of two items, burdened labor and materials. Will these two items need to be further broken down and if so to what specificity or will the contracting officer accept a roll up of the specific costs (total burdened labor and total material costs) for each UBR and then a total for all 17 sites?

A: Labor rates should be broken down to the individual labor categories, hours, and rates. Material should be broken down in a bill of materials so a fair and reasonable price can be determined.

12. Is the goal of the solicitation to accept the finished product detail work (paint, laminate’s, flooring, etc) to be consistent with the usual, reasonable and commercially comparable finishes for this type of setting available in the selected region or will a universal standard for this type of setting be acceptable?

A: We encourage final product detail to be consistent with usual, reasonable and commercially comparable local/regional finishes, but a universal standard is acceptable.