RFIs_&_Responses_18_Jul_17.pdf
PDF 57 KB Posted
- Attached to
- Repair by Replace HVAC, Satellite Comm Station, B700 Federal contract opportunity
- Solicitation number
- FA2550-17-R-1021
About this file
RFIs & Responses 18 July 2017
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Wage_Determination.pdf | ||
| RFIs_19_Jul_17.pdf | ||
| GLEN191001_SOW_-_20_Jul_17.pdf | ||
| Generator_Fuel_Tank_rules.docx | DOCX document | |
| 23_64_10_-_Water_Chillers,_Vapor_Compression_Type.pdf | ||
| Wage_Determination.pdf | ||
| RFIs_and_Responses_GLEN_19-1001_17_Jul_17.pdf | ||
| GLEN_19-1001_Site_Visit_Attendance_Sheet_28_Jun_17.pdf | ||
| GLEN_19-1001_Site_Visit_Memo_28_Jun_17.pdf | ||
| SOW_Attch_2_-_Specifications.pdf | ||
| SOW_Attch_1_-_Project_Drawing_Package.pdf | ||
| RFP_Attch_2_-_Wage_Determination.pdf | ||
| RFP_Attch_1_-_Statement_of_Work_dated_8_May_17.pdf | ||
| FA2550-17-R-1021_RFP_Repair_HVAC_B700.pdf | ||
| SOW_Attch_3_-_AF_Form_66_Submittal_Registry.xls | XLS spreadsheet |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Repair by Replace HVAC, B700 GLEN 19-1001 Requests for Information (RFIs)
RFP FA2550-17-R-1021
1. The response to RFI 17 indicated there was an attachment to the answers called, “POL/Storage Tank Management” but it was not posted on the FBO site. Please provide.
Government Response: See attachment
2. RFI #7 –The original question was not in regard to recovering existing R‐22 refrigerant.
Specification 23 64 10 2.7.4.1 refers to a new, stand‐alone refrigerant recovery unit to be installed in the MER. There is no information on the project drawings for this unit and no sequence of operations detailing how/when this unit will be utilized. If this unit is required, please provide additional information concerning electrical and control schematics.
Government Response: Paragraphs 2.7.4 and 2.7.5 can be removed from spec section 23 64 10.
3. Block 11 of the RFP says 180 calendar days for construction. Paragraph 6.0 of the statement of work dated 8 May 2017 says 240 calendar days. Which is correct?
Government Response: 240 calendar days is the correct number of days.