Repair Lift Station Pumps Bldgs. 650 and 1497 & Replace Lift Station Bldg. 943, Patrick AFB, FL
Solicitation number
FA252120B0001
Issued by

About this file

This solicitation seeks proposals to repair lift station pumps at Buildings 650 and 1497, and replace the lift station at Building 943, at Patrick Air Force Base in Florida. Offerors must inspect the work sites and submit any questions to the primary or alternate points of contact by January 14, 2020. Proposals are due by January 22, 2020 at 9:00 AM EST and should be sent to the primary and alternate contacts listed. The work must be completed within 180 calendar days of notice to proceed. Funds are not presently available and no award will be made until funding is secured, though the government reserves the right to cancel the solicitation before or after the closing date without obligation to reimburse offerors for any costs. The Department of the Air Force Space Command is the issuing agency.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Section F - Deliveries or Performance

The delivery information for the following CLIN(s) / SLIN(s) were modified:

0001 - Provide all materials, labor, equipment and management necessary to repair lift station pumps BLDG 650, BLDG 1497 & replace LIFT STATION 943. All work performed shall be in accordance with the Drawings (dated April, 2016) and Specifications (dated April, 2016).

Service Performance Site - F3K3DD - F3K3DD 45 CES CEN

INFORMATION FROM TO

Delivery 120 Calendar Days, From Date of Notice to Proceed Receipt to completion of performance

180 Calendar Days, From Date of Notice to Proceed Receipt to completion of performance

Miscellaneous text in this section has been modified to:

DELIVERIES AND PERFORMANCE:

F-1 NOTICE TO PROCEED (NTP): An NTP will be issued within 30 days after contract award.

F-2 PERIOD OF PERFORMANCE: The period of performance for this project is one hundred and eighty (180) calendar days including non-access days beginning at NTP. Non-Access Period: Any period of time, during normal established duty hours, that a contractor and/or its subcontractors, to include deliveries are denied access to the worksite by the appropriate Government authority.

NOTE: There are zero (0) Non-Access Days for this project.

F-3 AVAILABILITY OF UTILITIES: Electric and water hook-up is available to the contractor and shall be furnished at no charge. Contractors shall carefully and responsibly conserve usage of these utilities.

FAR Clauses Incorporated by Reference

52.242-14 Suspension of Work. (1984-04)

52.246-21 Warranty of Construction. (1994-03)

52.247-34 F.o.b Destination (1991-11)

The following clauses were modified:

52.211-10 - Commencement, Prosecution, and Completion of Work. Mar 1984 hereby reads as follows:

Commencement, Prosecution, and Completion of Work (Apr 1984)

The Contractor shall be required to (a)commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b)prosecute the work diligently, and

(c) complete the entire work ready for use not later than 180 calendar days. The time stated for completion shall include final cleanup of the premises.

FA252120B00010003

IDCode:
Page: 1
Pages: 2
AmendNo: 0003
EffDate: 1/24/2020
ReqNo: F3K3DD9189A001
ProjNo: SXHT 11-1055
IssCode: FA2521
AdmCode:
IssuedBy: FA2521 45 CONS LGC

1201 EDWARD H WHITE II ST MS 7200

ADMINISTRATIVE ONLY NO REQUISITIONS

PATRICK AFB, FL 32925-3237

United States Donna Fowler, Email: donna.fowler.2@us.af.mil Telephone: 321-494-9944

AdminBy:
ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: FA252120B0001
SolDate: 12/18/2019
AwardChg:
AwardNo:
AwardDate:
Amended: 1
OffrExt:
OffrNoEx: 1
NoCopies: 1
ApprData: See Section G
ChgeOrd:
ChgeOrder:
Modify:
SuppAgre:
SuppAuth:
ModOthr:
OthrSpec:
NoReq: 1
Require:
Copies:
Descript: The purpose of this Amendment is to reconcile information in the solicitation with the answer (A23) provided for Question 23 (Q23) in Attachment 12 (Questions and Answers dated 23 Jan 2020).

Refer to the Summary of Changes.

ContNameTitle:
CoNameTitle: Patricia Bates

Email: patricia.bates@us.af.mil Telephone: 321-494-7121

ContDate:
CODate:

File details come from the government source that posted it. Updated .