FA2521-17-B-0008_-_Q&As.pdf
PDF 74 KB Posted
- Attached to
- Repair Hanger U, FAC 1744 Federal contract opportunity
- Solicitation number
- FA2521-17-B-0008
About this file
FA2521-17-B-0008 - Repair Hangar U, FAC 1744 Questions and Answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA2521-17-B-0008_Attendees.pdf | ||
| FA2521-17-B-0008_Abstract.pdf | ||
| FA2521-17-B-0008_Amendment_05.pdf | ||
| Amend_04.pdf | ||
| FA2521-17-B-0008_Amendment_03.pdf | ||
| FA2521-17-B-0008_Q&As.pdf | ||
| FA2521-17-C-0008_Amendment_2.pdf | ||
| Attch_4_-_DBWD_FL170001_4_Aug_17.pdf | ||
| Site_Visit_Attendees.pdf | ||
| Attch_6_-_Haz_Waste_Form.doc | DOC document | |
| Attch_8-__Q&A_Template.docx | DOCX document | |
| Attch_5_-_CECC_Form_3052.xls | XLS spreadsheet | |
| FA2521-17-B-0008.pdf | ||
| Attch_1_-_DBEH_13-1523,_Repair_Hangar_U,_Fac_1744_(100__Design_Specs).pdf | ||
| Attch_2_-_DBEH_13-1523_Rpr_Hangar_U_FAC_1744_Dwgs.pdf | ||
| FA2521-17-B-0008_Rpr_Hangar_U_-_Conformed_Copy.pdf | ||
| Attch_4_-_DBWD_FL170001_14Jul2017.pdf | ||
| Amendment_01_.pdf | ||
| Attch_7_-_45_SFS_Badge-Visitor_Request_Form.pdf | ||
| Attch_3_-_DBEH_13-1523_RPR_Hgr_U,Fac_1744_CCAFS_GPP_Form.pdf |
Show all 20
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA2521-17-B-0008 – Hangar U, FAC 1744
QUESTION AND ANSWER
Question 1: After obtaining waste classification results for the oil absorbant material (Flag Note
2), will this material be collected and turned over to the Hangar U satellite location for disposal in accordance with OPLAN 19-14 Annex D & E?
Ref: SOW/Technical Specification/Drawings paragraph/page _Sheet H-101 Flag Notes 2
Other (Specify): 45 SW OPLAN 19-14
Answer: 1 If contractor anticipates multiple drums of oily absorbent wastes, then that will be directed to a site other than Hgr U. If less than a drum of waste, yes classified oily absorbent pads can be placed in that waste stream. Either disposition needs to be coordinated with Rebecca Fafard, 321-853-6988.
Contractor will need to provide drum and blue nonhaz label for pickup.
Question 2: The Wicket Door Schedule on Sheet A102 note the door and frame to be mill finish.
However, in the remarks column it notes "door/frame shall be shop primed and field painted to match existing". It appears these conflict each other.
Reference: SOW/Technical Specification/Drawings paragraph/page _Sheet A-102
Answer 2a: Primed and painted to match existing
SOW/Technical Specification/Drawings paragraph/page _Sheet A-102
Other (Specify) _45 SW OPLAN 19-14
Question 2b: A proposed door company, Cline Doors, does not manufacture mill finish aluminum doors and frames. They are either anodized or painted. Would this be acceptable?
Answer 2b: Primed and painted to match existing