Attachment 2 - Statement of Work Bayfield CCTVs v2_20260916.pdf

PDF 178 KB Posted

Attached to
USSC Bayfield CCTVs
Solicitation number
FA251726QA020
Issued by

About this file

This is a Statement of Work (SOW) for the USSPACECOM CCTV Project at Bayfield, dated 16 September 2026, with a maximum performance period of 90 calendar days (120 days maximum onsite work). Work shall be conducted Monday through Friday, 0700-1600, excluding federal holidays, at 1110 Bayfield Drive, Building A, first and second floors.

The primary scope includes: (1) procurement and installation of seventeen (17) interior dome fixed-view CCTV cameras on the secure side of perimeter doors to monitor facility entrances, connected only to the internal secured CCTV system; (2) procurement and installation of one (1) interior dome 360-degree CCTV camera in the lobby area; (3) increased CCTV server backup storage to 90 days retention capacity; and (4) procurement, installation, integration, and testing of two (2) outdoor-rated continuous 360-degree panoramic and pan-tilt-zoom (PTZ) capable CCTV cameras on a designated parking lot support pole, plus complete re-termination and re-wiring of two (2) existing government-owned surveillance cameras. A priced option (CLIN 0002A) provides for replacement of up to two (2) outdoor-rated cameras if re-termination fails due to internal hardware failure, requiring written CO authorization.

All work must comply with UFC 1-200-01, National Counterintelligence and Security Center (NCSC) IC Tech Spec for ICD/ICS 705 (Version 1.5.1, 26 July 2021), and CNSSAM TEMPEST/01-13 (RED/BLACK Installation Guidance, 17 January 2014). Security requirements mandate fiber optic cabling with metal conduit for secure space penetrations, shielded Cat-x plenum cabling throughout, no wireless capabilities, equipment compliance with Section 889 of Public Law 115-232, U.S. citizen contractor personnel only, and IT equipment approval by USSC/J6 ISSM/ISSO and the Special Security Office prior to secure space access. All conduit pathways and penetrations must be documented in a Technical Security Draft and approved in writing by USSPACECOM/J2S before installation commencement. The contractor must support post-installation physical and electronic inspections for compliance verification. Green Procurement mandates apply, requiring recycled and recovered materials, bio-based products, and environmentally preferable products. All contractor personnel require unescorted access to Building 1 with security escort requirements within secure areas; an Employee Access List (EAL) must be provided through the Contracting Officer with 3-5 working day processing time. The contractor furnishes all tools, personnel, transportation, and test equipment; all products become government property. Government points of contact are Mr. Darin Ziegler (COR, 719-552-1676) and Mr. Jason Dietrick (Technical Advisor, 552-1337).

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Project #: CBR

Project Title: USSPACECOM CCTV Project - Bayfield 16 September 2026

1. REQUIREMENTS:

1.1. Conduct all work in accordance with the specifications, all applicable codes, and the construction drawings and details. The Contractor shall comply with the UFC 1-200-01.

1.2. All Revisions to Statement of Work will be depicted with highlighted, bold, underlined text in red.

1.3. The Contractor shall follow all Green Procurement mandates and submittal requirements.

The Government requires the use of recycled and recovered materials, bio- based products, energy and water saving products, and environmentally preferable products.

1.4. Dispose of all waste generated by this project according to all applicable regulations.

1.5. The Contractor is responsible to verify site conditions, measurements, quantities, and materials needed to complete this project prior to submitting a proposal.

1.6. See the submittal schedule for required submittals. Other submittals required per specifications may apply.

1.7. High-Visibility Standards: This project will be a high-visibility project. Quality of finished.

project is very important. Adherence to the schedule is critical.

1.8. All IT equipment must be approved by USSC/J6 ISSM and coordinated with the assigned Office of Security representative prior to being brought into the secure space.

2. PROJECT SCOPE:

2.1. Period of Performance: Contractor shall complete all work within a maximum of ninety (90) days.

Work shall be completed on Monday through Friday, 0700-1600 schedule, apart from federal holidays.

The maximum number of days of onsite work shall be 120 days.

2.2. General: Task Order is to provide various components of work in different locations within the first and second floors of 1110 Bayfield Dr, interior of the building. Portions of work within or on the perimeter envelop of secured spaces to include physical protection requirements shall comply with the most current version of the National Counterintelligence and Security Center (NCSC) IC Tech Spec for ICD/ICS 705, current version is 1.5.1 dated 26 July 2021 and CNSSAM TEMPEST/01-13 (RED/BLACK Installation Guidance), published on 17 January 2014.

2.3. Access internal to the facility is controlled. Contractors will require escorting throughout the Secured Space. All phones, laptops, PDAs, smart watches, and similar devices will need to be left outside the secured portions of the facility. All workers must be U.S. citizens. Work includes procurement/installation of new power, equipment and cabling, connecting to existing equipment, and movement of some existing equipment; specifically: 1) Bayfield perimeter doors; purchase and installation of seventeen (17) internally mounted, fixed-view CCTV cameras providing video feed of each controlled area entrance door into facility. Display feeds only on internal secured area CCTV system. 2)

Bayfield Lobby area, purchase and install one (1) internally mounted CCTV camera providing coverage of lobby area and display of video feed on existing CCTV system. 3) Increase Bayfield CCTV server back-up storage capability to 90 days. 4) The Contractor shall provide all labor, materials, equipment, and supervision necessary to deliver, install, and integrate two (2) new exterior surveillance cameras providing a simultaneous 360-degree panoramic view and pan-tilt-zoom (PTZ) capability, and completely re-terminate and re-wire two (2) existing surveillance cameras on the designated camera support pole.

2.4. Project Site Specifics:

Installation Bayfield, Bldg. A (First and Second Floors)

A. Overall Security Installation Requirements

1. Door cameras should provide a clear view of the secure area doors but not enable the viewer to observe access control components that would enable them to identify PINs.

2. Equipment must not contain any wireless capabilities.

3. Equipment must be purchased IAW prohibitions outlined in Section 889 of Public Law 115-232

4. Shielded Cat-x plenum or fiber optic cabling shall be used in all spaces.

5. Cable penetrations into secure/controlled spaces shall be fiber optic and installed in metal conduit and sealed/infilled on both sides at perimeter IAW IC Tech Spec for ICD/ICS 705, seal both sides of perimeter penetrations with an acoustical foam or sealant finished to match adjacent wall. Conduit must on the secure side of the wall penetration.

Conduit penetrations must be integrated into existing Radio Frequency shielding, on secure side of penetration, and shielding/RF tape overlapped onto conduit a minimum of seven-times (7)x the diameter of the conduit opening.

6. All IT equipment must be approved by USSC/J6 ISSM/ISSO and coordinated with the assigned

Special Security representative (SSR) and Special Security Office (SSO) prior to being brought into secure spaces.

7. Any deviations to security installation requirements shall be approved by the Government Security

POC.

Installation Bayfield, Building A (CCTV Additions Secure Area):

1. The contractor shall procure and install seventeen (17) new indoor dome fixed-view CCTV cameras and associated mounting hardware, power receptacles, cabling, and conduit. CCTV camaras shall be installed on the interior (secure/controlled) side of the doors providing a fixed, clear view of individuals entering the facility doors. Video feed of CCTVs shall only connect to the currently installed internal secure/controlled CCTV system. No video feeds shall feed to the CCTV monitors outside of the secure/controlled area. See CCTV drawing attachment; CCTV cameras identified in red as 2-8 on upper level and 1-10 on lower level.

Installation Bayfield, Building A (CCTV Additions - Lobby):

1. The contractor shall procure and install one (1) new indoor dome, 360-degree view, CCTV camera and associated mounting hardware, power receptacles, cabling, and conduit as identified on the Newport CCTV attachment with a green number 1. The CCTV camera identified will connect to the current Bayfield CCTV server. The CCTV camera will provide a fixed, clear, 360-degree view of the lobby area.

Installation Bayfield, Building A (CCTV Server Storage):

1. The contractor shall procure and install CCTV server hard drive storage to increase the currently installed CCTV server back-up storage to 90 days of retention and storage of all CCTVs camera feeds.

Installation Bayfield, Building A (Parking lot):

1. The Contractor shall procure, install, integrate, and test two (2) outdoor-rated, continuous 360-degree panoramic view and PTZ capable CCTV cameras and all associated mounting hardware, weather-proof power receptacles, shielded outdoor cabling, and protective conduit to the designated camera support pole on Slide 3 of the 'Newport CCTV' Attachment. The cameras must be natively interoperable with the existing Bayfield CCTV Server footprint to include all necessary camera connection licenses, software integration, and streaming protocol matching without requiring hardware or software upgrades to the host server. The cameras shall deliver a continuous, unobstructed, high-definition 360-degree field of view covering the specified parking lot area 24/7 along with the capability to PTZ at the same time/simultaneously.

2. The Contractor shall re-terminate, re-wire, and integrate two (2) existing government-owned surveillance cameras mounted on the designated camera support pole. This scope shall include the replacement of all associated mounting hardware, weather-proof power receptacles, external outdoor-rated cabling, and protective conduit as identified on Slide 3 of the 'Newport CCTV' Attachment. The Contractor shall ensure these existing cameras are fully interoperable and tied into the existing Bayfield CCTV Server to provide a fixed, unobstructed, clear view of the designated parking lot area.

2a. CLIN 0002A (Priced Option): Camera Replacement (If Required) In the event that re-termination and re-wiring fails to restore full operational capability to either of the two (2) existing cameras due to internal hardware failure, the Contractor shall immediately notify the Contracting Officer (CO) and Contracting Off (COR). Upon written authorization from the CO, the Contractor shall procure, install, configure, and integrate up to two (2) replacement outdoor-rated 360-degree and PTZ capable cameras, ensuring a complete and fully functional visual assessment feed to the Bayfield CCTV Server.

3. The Contractor shall ensure that the installation, physical routing, penetration, shielding, and network integration of all CCTV cameras and associated cabling conform strictly to the following security standards:

1. IC Tech Spec for ICD/ICS 705 (Version 1.5.1, dated 26 July 2021): Specifically regarding perimeter penetrations, physical security protection of CCTV transmission lines, and the security integrity of the facility boundary.

2. CNSSAM TEMPEST/01-13 (RED/BLACK Installation Guidance, dated 17 January 2014): Specifically regarding electromagnetic emission isolation, proper physical separation between RED (classified) and BLACK (unclassified) pathways, and 360-degree RF shielding and grounding.

All conduit pathways, penetrations through the secure facility envelope, and cable terminations must be documented in a Technical Security Draft and approved in writing by USSPACECOM/J2S prior to the commencement of physical installation. Post-installation, the Contractor shall support a physical and electronic inspection to verify compliance before final system acceptance.

REQUIREMENTS:

REQUIREMENT 1: Compliance with National Counterintelligence and Security Center (NCSC) IC Tech Spec for ICD/ICS 705, version 1.5.1. Government can provide publication to Contractor at award.

REQUIREMENT 2: As active work locations, coordination with facility managers and security personnel is a must.

REQUIREMENT 3: The Contractor shall dispose of all waste generated by this project according to all applicable regulations.

REQUIREMENT 4: The Contractor is responsible to verify site conditions, measurements, quantities, and materials needed to complete this project prior to submitting a proposal.

REQUIREMENT 5: This project will be a high-visibility project. It will receive additional scrutiny from Senior Leaders. The quality of the finished project is very important. Adherence to the schedule is critical.

REQUIRMENT 6: Any work within the secure perimeter shall require the Government provide appropriate cleared escorts, at all times.

REQUIREMENT 7: The contractor must ensure that all new and modified camera feeds are fully compatible with your current security operations center footprint and installed in the same manner.

GOVERNMENT PROVIDED MATERIAL:

The COR and Technical Advisors shall be available for technical exchanges with the Contractor.

The COR and Technical Advisors shall provide technical input, answer questions, review and accept completed work, and provide feedback regarding contractor efforts. Where specified above in this document GFE items shall be found at this location: The Government will provide access (stored adjacent to Bldg. 1 on PSFB) to the materials at contract award.

GENERAL INFORMATION:

SECURITY REQUIREMENTS:

The Contractor shall not possess classified material. All contractor personnel proposed to work on this task order must be U.S. citizens.

ACCESS TO GOVERNMENT PROPERTY AND FACILITIES:

Government shall assist with daily access to building 1 and assist with scheduling into the secure space areas. All other contractor employees shall be required to work at contractor facilities. The Contractor shall be allowed unescorted access to building 1, consistent with task requirements.

Access to Government facilities, documents, and systems shall be in accordance with the

DD254.

INSTALLATION ACCESS:

Contractor shall provide an EAL through the CO for all workers to facilitate access to the workspaces. The EAL may be updated periodically through the project, but Contractor shall be aware that the list will take 3-5 working days to become updated. Former lists will be completely removed and only the new list will be processed.

CONTRACTOR FURNISHED MATERIALS:

Unless otherwise specified in the SOW, the Contractor shall provide all tools, personnel, transportation, and test equipment required to perform any product installation as called for by the contract. All tools and testing equipment shall remain the property of the Contractor.

PRODUCT OWNERSHIP:

All products produced by the Contractor in the performance of this SOW are the property of the Government.

PROPRIETARY DATA:

The Contractor shall request Government approval prior to the use of any proprietary data or software tools to fulfill the requirements of this contract. The Government will provide the Contractor access to information required to accomplish assigned tasks commensurate with security clearance and on a need-to-know basis.

The Contractor shall return all data pertaining to this contract to the Government upon contract expiration. The Contractor shall not retain classified or unclassified material generated or received under this contract after the contract ends without approval of the appropriate office of primary responsibility.

The Government has unlimited rights to all deliverables developed under this SOW. The Contractor shall not use any materials pertaining to this contract for business development or any other vendor strategic purposes. However, the Contractor is authorized to include summary performance information in proposals to be submitted to the Government to satisfy past performance information requirements.

WORK HOURS:

Contractor shall request approval from the Contracting Officer/COR prior to working outside of normal duty hours (0700-1600 Monday Friday). As active work locations, coordination with facility managers and security personnel is a must. Work may require a phased approach, with after hours and weekend work a strong possibility. If approved, the COR will notify SSO.

The Contractor shall not provide services on the following Federal Holidays (or the actual day

Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, Christmas Day, any executive ordered days off and USSPACECOM Family Days/Down Days.

SNOW DELAY/BASE CLOSURE:

The Contractor shall adhere to the snow delay and base closure policy of the installation.

Installation snow delay information can be found by calling the PSFB Snow Call Line at 719-

556-SNOW (7669).

GOVERNMENT POINTS OF CONTACT:

CONTRACTING OFFICER REPRESENTATIVE (COR):

Mr. Darin Ziegler, 719-552-1676

TECHNICAL ADVISORS:

Mr. Jason Dietrick, 552-1337 Mr. Darin Ziegler, 719-552-1676