Question and Answers Updated.xlsx
XLSX spreadsheet 24 KB Posted
- Attached to
- PACA Special Audits RFQ
- Solicitation number
- F41999-27-Q-0007
About this file
This is a Questions and Answers document providing clarifications to offerors for the Air Force Services Center (AFSVC) Public Accountant Contract Audit (PACA) Program RFQ (F41999-27-Q-0007). The contract requires comprehensive audit services across Air Force Nonappropriated Fund (NAF) operations worldwide, including financial statement audits of Morale, Welfare and Recreation (MWR), Lodging, and Cadet Dining funds; performance audits of the centralized Shared Services Center in San Antonio; and audits of the Department of the Air Force Gaming/Slot Program across multiple installations including overseas locations. The contractor must be a licensed CPA firm performing all work with direct W-2 employees only—subcontractors, teaming partners, and joint ventures are prohibited to ensure direct accountability and data security for sensitive Controlled Unclassified Information (CUI) and Personally Identifiable Information (PII). On-site fieldwork is limited to four weeks maximum per engagement, with remote work authorized for preparation, data analysis, and report drafting; physical presence is required only for procedures such as inventory counts, cash observations, staff interviews, and entrance/exit briefings.
Deliverables include independent auditor reports with formal audit opinions for financial statement audits (one per individual fund), management letters, and detailed performance audit reports for operational audits, all priced as firm-fixed-price amounts per individual task order on Attachment 05. The Government will provide necessary system extracts, prior audit reports, and slot accounting data centrally; contractors must establish their own NIST SP 800-171-compliant secure repositories for data storage. Travel reimbursement follows the Federal Travel Regulations (FTR), with military charter transportation provided only to Pituffik Space Base in Greenland; all other travel is the contractor's responsibility. Task orders will be issued no later than 15 days prior to scheduled on-site fieldwork start dates, with a minimum of 30 days' advance notice for ad hoc Commander's Special Interest Audits. All audits must comply with the 2024 revision of Government Auditing Standards (GAGAS/Yellow Book), and dual-year audits shall deliver a single consolidated comparative report with separate opinions per fiscal year. The solicitation is not set-aside for small business; all qualified licensed CPA firms meeting technical criteria are encouraged to submit proposals.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1 Question / Clarification Requested VF Response
| Does the Air Force expect offerors to hold a specific CMMC level, or a NIST SP 800-171 self-assessment score in the SPRS at proposal or award time? | No | |
| Shared Services Center audit type: Clarify if it is a financial statement and compliance audit, or an economy/efficiency performance audit. | SSC requries a performance audit; no financial statement audit | |
| Can an unprotected copy of the 'Installation Listing' spreadsheet be provided? | Yes; VP has listing | |
| Option Year 2: Confirm the planned fiscal year schedule across all five years (SOO 4.5 labels Option Year 2 as auditing FY26, while other years refer to task orders). | SOO updated to remove specific FY callouts; FY will be identified in individual task orders | |
| Background investigations: Confirm which audit roles require Tier 1 vs. Tier 3 investigations, and whether work can begin on an interim determination. | Tier 1; work may begin with favorable fingerprint and SF-85 submission | |
| Travel cost structure: Confirm whether JTR or FTR governs travel reimbursement. | FTR | |
| Travel details: Request a travel estimate or not-to-exceed travel amount by task order so offerors can plan staffing. | vendor to provide estimate | |
| SOO 6.3 requires all fieldwork on-site while RFI Q2a asks how to minimize on-site presence. Clarify how much remote fieldwork is allowed. | 6.3.1. | To ensure thorough data gathering and direct operational insight prior to forming an audit opinion, all audit fieldwork, entrance briefings, and exit briefings will be conducted on-site at the respective installation or activity being audited. On-site fieldwork at the designated installations will not exceed a maximum duration of four (4) weeks per audit. Remote work is authorized only for audit preparation, data analysis, and report drafting, which may be completed at the Contractor’s office facilities. |
| Option Year 2 labels 'Auditing Fiscal Year 2026' while others say 'as defined in individual task orders'. Recommend consistent wording. | SOO updated to remove specific FY callouts; FY will be identified in individual task orders | |
| Can more on-site time be allowed for dual-year task orders, or confirm if substantial testing can be done remotely? | Total on-site fieldwork not to exceed 4 weeks. Substantial testing may be completed remotely | |
| Since the notice cites JTR but the SOO cites FTR, clarify the governing travel regulation. | FTR | |
| Will a not-to-exceed travel ceiling be set for each task order, and what is the lead time for travel orders? | Yes; task orders to be issued NLT 15 days prior to scheduled on-site fieldwork start date. | |
| For overseas locations, confirm country clearance, SOFA, passport requirements, and on-base lodging availability. | On-base lodging will be coordinated by respective installation POCs. All Contractor personnel assigned to perform services at OCONUS installations must be U.S. citizens. | |
| What are the names of the POS and shared services systems, typical extract formats, and volumes? | Air Force NAF operations utilize Oracle for finanical reporting; POS systems include ALOHA, RecTrac with excel .xlsx, .csv, and adobe pdf extract formats. Volume varies based on installation and activity size. | |
| What is the annual revenue, expenses, and total assets for each NAFI, plus trial balances? | AFSVC is not providing base-by-base financial data at this time | |
| What is the number of revenue outlets, POS terminals, and inventory locations per activity, and annual transaction volumes? | AFSVC will not provide specific, facility-by-facility counts of revenue outlets, POS terminals, inventory locations, or annual transaction volumes for individual activities across all installations. Compiling and releasing granular terminal and inventory mapping at this stage is administratively prohibitive and outside the scope of this solicitation | |
| Venture Gaming: What are the slot machine counts per location, net revenues, and the slot accounting system used? | AFSVC will not provide specific machine counts for individual facilities during the soliciation period. Refer to Slot Locations attachment for location/activity. Net revenues per location are proprietary NAFI operational data and will not be released during this solicitation. Venture Gaming utilizes automated Slot Accounting and Management Systems (SMS). | |
| What is the expected frequency and typical scope of Special Interest Audits? | Cadet Dining - Annual financial statement |
Slots at installations - rotatation between USAFE and PACAF installations Shared Services Center - not annual Other Commander's Interest Items - ad hoc as requested Please clarify the exact mix of financial statement audits, GAGAS performance audits, and agreed upon procedures by activity and task order, including which require an audit opinion. AFSVC clarifies that Agreed-Upon Procedures (AUPs) are not required or contemplated under this contract. The scope of this agreement is strictly limited to two distinct audit types:
Financial Statement Audit: These require the Contractor to test general ledgers and issue a formal Independent Auditor’s Report (Audit Opinion) per individual fund audit.
Performance/Operational Audits: These are risk-based or ad hoc investigations (such as Commander's Special Interest Audits) that do not require an audit opinion. The final deliverable is a detailed performance report containing actionable recommendations.
The exact mix and frequency of these audits will vary annually based on AFSVC mission requirements, available funding, and DoDI 1015.15 thresholds. The specific audit type, location, and scope for each engagement will be defined in individual Task Orders.
| Please identify the applicable accounting basis, NAF specific guidance, financial reporting framework, and audit reporting templates for each fund. | all applicable guidance is listed within the SOO |
| Please provide task order specific schedules, dual year deliverable deadlines, review periods, and the Government’s expected response time for draft reports. | refer to SOO deliverables section IV for standardized timelines and review periods |
| Please confirm the anticipated number of locations, overseas sites, gaming devices, and on site verification events; provide current system and slot location inventories. | AFSVC will not provide specific, real-time machine-level inventories, slot system software configurations, or physical base maps during the solicitation period. A list of overseas slots locations in included as an attachment to this solicitation. |
| Please clarify access to prior year audit workpapers, electronic records, POS data, shared services systems, and whether Government furnished secure repositories will be available. | The succesful offeror will be provided the most recent prior audit reports will be provided; direct, independent network logins will not be provided to contractors. The Shared Services Cetner and local installations will pull, compile, and deliver system extracts directly to the contractor; The Government does not provide a dedicated secure cloud workspace for contractors to host files. The Contractor is responsbile for providing their own secure, NIST SP 800-171-compliant file repository to receive and host data. Files may be transferred utilizing DODSAFE. |
| Please distinguish CUI handling obligations from any contractor owned system assessment, certification, or security clearance requirements. | CUI and PII Handling Obligations: Standard and mandatory. The Contractor is contractually obligated to safeguard and protect all NAFI financial data, operational metrics, and employee record information as Controlled Unclassified Information (CUI) and Personally Identifiable Information (PII) in accordance with DoD guidelines and federal regulations. |
AFSVC will not require or conduct any formal independent IT system assessments, audits, or government-issued security certifications (such as an Authority to Operate / ATO) for Contractor-owned IT networks or platforms.
The Contractor is expected to self-comply with the safeguarding standards set forth in NIST SP 800-171 to secure CUI data on their internal systems.
Please clarify whether the 15–30-day mobilization window is mandatory for all special interest audits and whether task order ceilings or minimum notice will be established. AFSVC confirms that the Contractor is responsible for proposing the on-site fieldwork start dates as part of the initial Audit Plan (Deliverable 1) during the planning phase.
Because ad hoc Commander's Special Interest Audits are subject to formal review and approval by the DAF Services Audit Committee prior to task order authorization, the Government anticipates having ample advance visibility of these requirements.
To ensure the Contractor has sufficient time to coordinate resources and execute the planning phase, the Government will provide the Contractor with a minimum of thirty (30) calendar days' advance written notice (via a formal Task Order or written Call) prior to the required Audit Plan submission deadline.
The Contractor will then propose the specific, on-site fieldwork dates within their Audit Plan, ensuring all travel is booked cost-effectively in accordance with the FTR, and the 15-day advance PBC document list is coordinated with the local installation POCs
| Please clarify whether financial statement and performance audit engagements may be staffed by different specialized teams under one prime contractor. | financial statement and performance audit engagements may be staffed by different specialized teams under one prime contractor. |
| Please revise Section 3.4 to accept a most recent peer review rating of 'Pass with Deficiencies' when all deficiencies have been satisfactorily addressed and the corrective actions have been accepted by the appropriate peer review committee. Please specify the documentation required. | Only a rating of 'Pass' is acceptable. A rating of 'Pass with Deficiencies' or 'Fail' on the most recent peer review report is not acceptable and will result in the proposal being deemed technically unacceptable. |
| Please clarify whether travel reimbursement follows the Joint Travel Regulations in all locations and how exceptional overseas travel costs are approved. | all travel is in accordance with FTR |
| Clarify whether a Government hosted compliant environment satisfies the requirement or whether a contractor-owned assessed environment is mandatory. | The contractor is required to maintain their own secure, NIST SP 800-171 compliant environment to store, host, and process audit files. Files may be transferred utilizing DOD SAFE |
| Clarify advance travel approval, lodging and per diem ceilings, cancellations, visas, and whether travel administration time is included in the fixed price labor effort. | All travel must be approved in writing by the COR prior to booking. All travel reimbursements are in accordance with FTR;Government will not pay for visas or personal travel documents. Time spent coordinating, booking, or managing travel is considered standard administrative overhead and is not separately billable and must be included in the firm fixed delivrable based pricing. |
| Clarification on dual-year baseline work and whether the Government will provide prior year workpapers, as applicable. | AFSVC will provide the most recent prior financial statement reports to the succesful offeror. |
| Is AFSVC considering a prohibition on subcontractors because it expects a single large firm to perform the full scope? | AFSVC does not expect a single 'large' firm, nor is the subcontractor prohibition designed to restrict competition. All qualified, licensed CPA firms capable of meeting the technical criteria are encouraged to submit proposals. |
The prohibition on subcontractors and teaming partners is a requirement established strictly to ensure robust contract management, individual accountability, and enterprise-level data security.
Because this specialized contract covers highly sensitive, centralized Air Force operations—including the AFSVC Shared Services Center, the Department of the Air Force Gaming/Slot Program, and ad hoc Commander's Special Interest Audits—the Government must maintain a direct, un-broken line of legal and operational accountability with the performing personnel.
Allowing third-party subcontractors introduces unacceptable complexities in contract management, personnel tracking, and base security. Restricting performance strictly to the prime Contractor's direct W-2 employees is necessary to ensure the Government can hold the contracting firm directly accountable for the conduct, qualifications, and security clearances of every individual auditing these critical central programs.
| Does AFSVC have a specific contractor profile or delivery model in mind for this requirement? | AFSVC has no pre-determined contractor profile in mind (all licensed CPA firms in good standing that meet the technical requirements are encouraged to bid). |
| Would travel be allowed for in the pricing and budget? | travel is priced seprarately |
| Would not allowing subcontractors be restrictive? | AFSVC has determined that the prohibition on subcontractors is NOT unduly restrictive of competition, but is a necessary and justified operational control requirement. |
Under federal procurement principles, an agency possesses the legal authority to define its minimum requirements based on legitimate mission and security needs. For this specialized contract, prohibiting subcontractors is directly tied to the following essential Government interests:
Direct Accountability & Privity of Contract: Because this contract audits centralized enterprise programs (the AFSVC Shared Services Center, the Air Force Gaming/Slot Program, and sensitive Commander’s Special Interest Audits), the Government must maintain direct contractual privity and complete supervisory oversight over all personnel performing the work. Subcontracting creates fragmented lines of authority and diminishes direct accountability.
Data Security & Privacy: Accessing centralized general ledgers and employee payroll records involves handling sensitive Controlled Unclassified Information (CUI) and Personally Identifiable Information (PII). Restricting access strictly to direct W-2 employees of the prime Contractor preserves a continuous, verifiable chain of custody for all financial data.
GAGAS Quality Control: Under professional auditing standards, the prime CPA firm is directly liable for the integrity of the audit opinions. Direct-hire performance ensures uniform quality control, peer-review compliance, and strict auditor independence.
There are numerous licensed, qualified CPA firms in the commercial marketplace capable of performing this scope of work entirely with their own direct staff. Therefore, competition remains robust, and the requirement stands as written Place of performance (SOO 6.3.1): Will AFSVC authorize remote document inspection and walkthrough interviews, with on-site time reserved for procedures that require physical presence? Yes. AFSVC authorizes and expects the Contractor to utilize remote procedures (such as electronic document inspection) to the maximum extent feasible.
In accordance with the SOO, the Contractor shall perform all preliminary data gathering, general ledger reviews remotely.
The physical, on-site fieldwork standard is strictly reserved for procedures that require physical presence, such as:
Physical inventory counts.
Staff interviews Independent cash counts and locked-drawer inspections.
Direct observation of physical internal controls.
Formal on-site Entrance (In-Brief) and Exit (Out-Brief) presentations.
| Fieldwork duration (SOO 4.3.1): For dual-year audits, does the four-week fieldwork limit apply per fiscal year or per task order? (Recommends 5 weeks or 2 site visits for dual-year audits). | Per task order |
| Funds in scope (SOO 4.1.1): Please list the individual funds that will receive financial statement audits and state whether SOO 2.2.3 calls for an opinion on consolidated statements. | All financial statement audits will be executed and reported as standalone, indivdiual fund audits (MWR, Lodging, Cadet Dining). No consolidated opinion. |
| Venture Gaming locations: Please confirm whether PACAF slot locations and Pituffik Space Base are in scope, and whether each installation visit is a separate deliverable under SOO 4.1.2. | Refer to Slot location attachment. Yes PACAF and Pituffik are within scope. Each installation visit is a seprate engagement with separate deliverables. |
| Venture Gaming procedures: Will auditors observe drop and count at each slot location, and will AFSVC provide slot accounting system reports, meter histories, and W-2G records from the central program office? | 1. Centralized Data Access: Yes, the AFSVC central program office will provide the Contractor with the necessary Slot Accounting System (SMS) reports, centralized meter histories, and W-2G records as requested in the approved PBC list to facilitate remote financial reconciliations. |
2. On-Site Observations and Drop Schedules: Physical observations of electronic gaming machine drop and count procedures are not required at every single location for every audit.
Where physical observations are required for testing, they must be conducted in strict coordination with the installation's pre-scheduled, existing NAF cash drop and count schedules.
| Shared Services Center scope (SOO 1.2.A): Please release the project assignment document for the SSC performance audit, including the services, service level agreements, and metrics in scope. | AFSVC will not release specific internal SSC Project Assignment documents, Service Level Agreements (SLAs), or detailed operational system metrics during the solicitation period. These documents contain sensitive, non-public operational data and internal control processes. |
| Installation Listing: Please confirm which entries are expected to receive audits in the base year and the estimated number of audits per year by program and region. | Audit Locations list will be attached to this solicitation; The specific locations and activities selected for audits during the Base Year (and each subsequent Option Year) will be designated in individual Task Orders based on annual risk assessments and DoDI 1015.15 financial thresholds |
| Fiscal years (SOO 4.5): Option Year 2 deliverables reference Fiscal Year 2026, while other years reference fiscal years designated in task orders. Please confirm the planned fiscal year for each period. | SOO updated to remove specific FY callouts; FY will be identified in individual task orders |
| Management comment period (SOO 6.2.5.1): Installations have 30 days to return comments on the preliminary draft. Will the 10-business-day draft report clock start after AFSVC returns consolidated comments? | refer to SOO deliverables section IV for standardized timelines and review periods |
| Government dependencies: How will delivery dates adjust when records, installation access, system access, or management comments arrive after the scheduled dates? | Refer to SOO section IV for notification of delays. In the event of a verified Government-caused delay (such as late delivery of core PBC records, delayed base visitor pass processing, or Government review times exceeding the established thirty-day window), the Contractor will receive corresponding, day-for-day schedule relief to adjust the subsequent deliverable deadlines |
| System access (SOO 6.6): Will auditors receive read-only access to NAF accounting, POS, and slot systems, or will activities produce all extracts? Which investigation tier and DoDM 8140.03 qualifications apply to read-only access? | Contractors will not be provided system access. All documents will be provided by activity POC |
| Security requirements: Please confirm that the work involves unclassified information, specifically CUI and PII, and identify any facility or personnel security requirements beyond SOO Sections 6.6 and 7. | No facility or personnel security requirements beyond what is identified in the SOO. Unclassified, CUI/PII |
| Commander's Special Interest audits (SOO 1.2.D): What response time will these task orders require, and will CLIN 0003 include defined labor categories and ceiling hours? | When AFSVC identifies a requirementn for an ad hoc Commander's Special Interest Audit, the Government will provide written notification to the contractor to initiate the task order. All Special Interest Audits will be ordered and invoiced againt flat-rate deliverable CLINs established in ATCH 05. |
| Prior audits (SOO 2.1.6.7): Will the COR provide prior PACA reports and corrective action status with the solicitation, so offerors can size repeat-finding follow-up work? | Prior audit reports will be provided IAW the SOO |
| Travel regulation (SOO 6.4.1): Please confirm whether the Joint Travel Regulations, cited in the RFI, or the Federal Travel Regulation, cited in SOO 6.4.1, govern CLIN 0004. | Federal Travel Regulations |
| Subcontracting: intent: Is AFSVC considering a prohibition on subcontractors because it expects a single large firm to perform the full scope? If so, how does AFSVC keep this requirement open to small business participation and competition? | AFSVC does not expect a single 'large' firm, nor is the subcontractor prohibition designed to restrict competition. All qualified, licensed CPA firms capable of meeting the technical criteria are encouraged to submit proposals. |
The prohibition on subcontractors and teaming partners is a mandatory requirement established strictly to ensure robust contract management, individual accountability, and enterprise-level data security.
Because this specialized contract covers highly sensitive, centralized Air Force operations—including the AFSVC Shared Services Center, the Department of the Air Force Gaming/Slot Program, and ad hoc Commander's Special Interest Audits—the Government must maintain a direct, un-broken line of legal and operational accountability with the performing personnel.
Allowing third-party subcontractors introduces unacceptable complexities in contract management, personnel tracking, and base security. Restricting performance strictly to the prime Contractor's direct W-2 employees is necessary to ensure the Government can hold the contracting firm directly accountable for the conduct, qualifications, and security clearances of every individual auditing these critical central programs.
Subcontracting: contractor model: Does AFSVC have a specific contractor profile or delivery model in mind for this requirement? Knowing the intended model allows industry to propose the teaming structure that best fits AFSVC's needs. AFSVC has no pre-determined contractor profile in mind (all qualified, licensed CPA firms in good standing that meet the technical requirements are encouraged to bid).
However, the use of subcontractors, teaming partners, or joint ventures is strictly prohibited under this contract. All audit services, fieldwork, and reports must be performed entirely by the prime Contractor’s direct, W-2 employee staff.
Firm-Fixed-Price by Deliverable: Performance is priced and invoiced strictly against the approved, flat-rate deliverables (CLINs) established on ATCH 05 per engagement.
To maximize cost efficiency and minimize base disruption, the Contractor shall utilize a hybrid audit model. This involves conducting the vast majority of planning, data-extraction, transaction testing, and report drafting remotely, while conducting on-site fieldwork to conduct physical counts, observations, and key face-to-face interviews.
Sequential / Coordinated Scheduling: The Contractor is expected to manage their staffing pool to execute these audits sequentially throughout the 12-month performance year, in accordance with the collaboratively developed Audit Plan (Deliverable 1) Subcontracting: auditor independence: If subcontracting is restricted, how will AFSVC preserve the independent auditor's authority to determine the audit plan, materiality, staffing, and specialists needed to support each opinion, consistent with GAGAS independence in fact and in appearance? AFSVC confirms that the prohibition on subcontractors does NOT impair or restrict the independent auditor's authority under GAGAS standards.
The Contractor retains complete, independent professional authority to establish the audit plan, determine materiality thresholds, design transaction testing sample sizes, and assign qualified direct-hire staff to support each engagement, in strict accordance with GAGAS and AICPA standards. Requiring all audit personnel to be direct W-2 employees of the contracted prime firm is a standard contractual, privity, and data-security control, which does not interfere with the firm's professional auditing judgment.
Furthermore, the Government’s intent is for the awarded prime Contractor to execute both the financial statement audit and any scheduled performance audits at the same installation. Under GAGAS, performing both audit types for the same client does not impair independence, as the performance audit is strictly an advisory evaluation of operational efficiency, and the Contractor does not perform management functions or design internal controls. Conducting both scopes under a single prime firm maximizes operational continuity, shared travel efficiencies, and comprehensive oversight for the installation Subcontracting: concurrent execution: If subcontracting is excluded, how does AFSVC expect a single firm to staff simultaneous financial statement, Shared Services Center performance, Venture Gaming, Cadet Dining, and Commander's Special Interest audits across the United States, Europe, Greenland, and the Pacific? AFSVC does NOT expect or require simultaneous, concurrent execution across all worldwide locations.
The Contractor will not be required to deploy audit staff to multiple domestic and overseas installations at the same time; The Government seeks sequential/staggered scheduling across the contract performance period.
Subcontracting: safeguards: Would clear prime accountability for audit leadership, independence, supervision, and reporting—combined with appropriate specialist qualifications and Government consent where required—meet AFSVC’s objective without imposing a blanket subcontracting prohibition? AFSVC has evaluated the proposed oversight model and has determined that a blanket prohibition on subcontractors and teaming partners remains a mandatory security and operational control requirement for this contract.
While 'prime accountability' is a standard contracting framework, the specialized nature of these enterprise-level audits—specifically involving centralized general ledgers at the Shared Services Center, automated electronic gaming systems, and ad hoc Commander's Special Interest investigations—demands a direct, un-broken relationship of privity and physical security control with every individual auditor.
Allowing third-party subcontractors, even with Government consent, introduces unacceptable administrative complexities in security-clearance vetting, DISS adjudication, and physical base access tracking. To ensure uncompromised data integrity, protect sensitive CUI/PII on direct systems, and maintain clear, single-point accountability for the Air Force, all work must be performed exclusively by the direct W-2 employee staff of the prime Contractor. The requirement stands as written.
Past performance: Will past performance on audits of public entities and hospitality, food service, entertainment, or gaming operations be considered relevant, and will subcontractor past performance count toward the prime's assessment? 1. Relevance of Commercial Past Performance: Yes, past performance involving audits of commercial entities, public agencies, or enterprises operating in the hospitality, food service, recreation, entertainment, or gaming sectors will be considered directly relevant.
In accordance with SOO paragraphs 3.1 and 3.3, experience auditing entities similar in nature to Air Force Nonappropriated Fund Instrumentalities (NAFIs) directly demonstrates the necessary technical capabilities to execute this contract.
2. Subcontractor Past Performance: No, subcontractor past performance will NOT be evaluated or considered.
Because the use of subcontractors, teaming partners, or joint ventures is strictly prohibited under this contract, all submitted past performance references must demonstrate the direct past performance of the bidding prime Contractor. Any past performance references submitted for third-party entities or subcontractors will be deemed non-responsive and excluded from evaluation.
| Set-aside: Does AFSVC plan a small business set-aside under NAICS 541211? | No, per DAFMAN paragraph 2.8.2 NAF Procurement Exemptions |
| Geographic scope: Does AFSVC anticipate a single worldwide contract, region-specific task orders, or an initial USAFE-focused requirement? Please identify the expected installations and task order quantities by program and region. | Audit locations listing to be attached to this solicitation; The specific locations and activities selected for audits during the Base Year (and each subsequent Option Year) will be designated in individual Task Orders based on annual risk assessments an |
| Deliverables and pricing units (SOO 4.1): How many financial statement opinions, management letters, and performance audit reports does AFSVC anticipate each year? | AFSVC does not provide a guaranteed or anticipated annual number of financial statement opinions or management letters, as the volume of financial audits is driven dynamically by the mandatory gross revenue thresholds ($10M or more) established in DoDI 1015.15. Audit locations listing is provided within the solicitation. |
Financial Statement Audits: Each ordered financial statement audit will require one (1) Independent Auditor's Report (Audit Opinion) and one (1) Management Letter per individual fund.
Performance Audits : Each ordered performance audit engagement requires one (1) consolidated Final Performance Audit Report (with recommendations).
All audits will be ordered on an as-needed basis via individual Task Orders, and no minimum or maximum quantities of opinions are guaranteed.
| Independence and conflicts: Where one firm performs financial statement audits, performance audits, and special interest audits for related funds, how will AFSVC address independence evaluations and conflict disclosures? | AFSVC's intent is for the awarded prime Contractor to execute both financial and performance audits. Under GAGAS, performing both audit types for the same client does not impair independence, as the performance audit is strictly an advisory evaluation of operational efficiency, and the Contractor does not perform management functions or design internal controls. Conducting both scopes under a single prime firm maximizes operational continuity, shared travel efficiencies, and comprehensive oversight for the installation |
| Pre-proposal technical exchange: Will the planned pre-proposal conference include technical questions on NAF accounting, AFSVC systems, historical workload, and performance expectations? | AFSVC does not plan to host a live pre-proposal conference or technical exchange for this solicitation. All technical inquiries regarding NAF accounting, systems, historical workload, and performance expectations must be submitted in writing to the designated Contracting points of contact prior to the established question deadline. |
All submitted questions will be answered formally and distributed to all potential offerors via a written solicitation amendment to ensure a fair, transparent, and equal procurement process.
| Clarify whether confirmations, analytics, testing of electronically provided support, and video interviews may be counted as remote work. | analytics and testing of provided support may be done remotely. Interviews should be conducted on-site as part of fieldwork |
| Whether the performance audit of the SSC, a centralized function in San Antonio, may be performed partly remotely. | all fieldwork must be conducted on-site; |
| Whether the 2018 revision or 2024 revision of Yellow Book GAGAS applies to the base-year dual-year audits. | AFSVC confirms that the 2024 Revision of Government Auditing Standards (GAGAS / Yellow Book) shall apply to all audits performed and reports issued under this contract, including the dual-year Base Year audits. |
In accordance with GAO implementation guidelines, the Contractor shall utilize their GAGAS 2024-compliant Quality Management systems and reporting formats for all deliverables.
For the historical fiscal years in scope (e.g., FY24), the Contractor shall evaluate the installation's financial transactions and compliance against the specific Air Force and NAF regulations that were active during those respective fiscal periods.
| Whether the 4-week fieldwork cap applies to each fiscal year or to the dual-year engagement as a whole. | 4-week fieldwork cap applies to the engagement as a whole |
| Whether each year of a dual-year audit will receive a separate opinion and report or a comparative report covering both years. | AFSVC confirms for dual year financial statement audits, the contractor shall deliver a single, consolidated comparative financial statement report with distinct and separate opinions. |
| Confirm whether passport, visa, and country clearance costs for overseas travel are reimbursable under CLIN 0004. | AFSVC will not pay for or manage contractor passports, visas, or personal travel documents; these are the sole responsibility of the contractor. |
| State whether Government transportation will be provided to remote sites (Pituffik Space Base, Clear Alaska). | Pituffik Space Base (Greenland): Because Pituffik is not accessible via commercial aviation, the Government will sponsor and provide military charter transportation (MilAir) for Contractor personnel from Joint Base McGuire-Dix-Lakehurst (JB MDL), New Jersey, directly to Greenland. |
The Contractor is responsible for booking and paying for commercial travel to JB MDL, which will be reimbursed under the Travel CLIN in accordance with the FTR.
The COR and Pituffik POCs will coordinate the flight sponsorships and scheduling during the Audit Plan phase (Deliverable 1).
2. Clear Space Force Station (Alaska): The Government will NOT provide military transportation to Clear SFS. Clear is accessible by road.
The Contractor is responsible for booking commercial travel to Fairbanks, Alaska, and securing a commercial rental car to drive to Clear SFS, which will be reimbursed under the Travel CLIN in accordance with the FTR
| Confirm whether offerors must have a current NIST SP 800-171 SPRS assessment or a particular CMMC level at proposal or award time. | AFSVC does not require offerors to hold current NIST SP 800-171 SPRS assessments. IAW with SOO offeror must possess and utilize a secure, compliant file repository and data transfer protocol capable of safeguarding controlled unclassifed informationa nd PII. |
| To size mobilization capacity, state the expected number of Commander's Special Interest Audits per year and their typical duration. | AFSVC does not have a historical baseline or expected annual quantity for Commander's Special Interest Audits, as these engagements are purely ad hoc and contingent upon unplanned, emergent operational needs identified by installation leadership or AFSVC. |
While gaming/slot locations and the Shared Services Center are known and fixed, an ad hoc Special Interest Audit may be requested for any activity or installation across the Air Force for reasons that cannot be predicted in advance.
2. Mobilization & Pricing Assumptions: Quoters shall not assume a guaranteed quantity of Special Interest Audits. To size mobilization capacity and price ATCH 05:
Quoters shall utilize the general baseline estimates provided in Attachment 012 - Historical Workload and Estimated Quantities to scale their administrative overhead.
Typical Duration: When a Special Interest Audit is ordered, quoters shall assume a typical on-site fieldwork duration of five (5) consecutive business days (one week) for standard activities, with the four (4) week limit serving strictly as a contract ceiling for complex multi-activity investigations.
All ad hoc audits will be ordered and invoiced against the flat-rate deliverable CLINs established in Section B of ATCH 05 upon formal Task Order issuance.
| Please clarify how many funds fall under each program (Venture Gaming, Cadet Dining, and the SSC). | Each activity is within a single fund (i.e. Slots = MWR, Cadet Dining = Cadet Dining) |
| Please clarify whether each fund needs a separate audit report and opinion, or if it will all be consolidated into a singular audit report and opinion. | Refer to SOO 4.1 |
| Can you provide the prior year audit report and associated opinion to determine materiality threshold? | AFSVC will not release prior PACA audit reports (in full or redacted) during the solicitation period. These reports contain sensitive internal control vulnerabilities and proprietary operational data that cannot be distributed publicly. |
| Please provide standardized labor categories and historical level of effort hours/pricing so offerors can understand the expected scope. | AFSVC will not release historical labor hours, labor category breakdowns, or predecessor contract pricing data. |
To ensure a fair and open competition that fosters independent pricing and operational efficiency, all quoters must develop their own Level of Effort (LOE) estimates based on the specific requirements of the SOO and the workload metrics provided.