Site Visit QA_FINAL Consolidated Responses.pdf

PDF 302 KB Posted

Attached to
56 CS FOC to Flightline and Wx Equipment, Luke AFB
Solicitation number
F3YCFA6173AC01
Issued by

About this file

This is a Site Visit Questions and Answers document for a federal fiber-optic cable installation project at Luke Air Force Base. The document addresses 53 technical and administrative questions submitted by prospective contractors regarding scope clarification, installation methods, materials, testing requirements, labor standards, subcontracting limitations, and proposal submission procedures.

Key technical requirements include: installation of armored fiber-optic cable (double armored with corrugated steel tape or galvanized steel wire armor for rodent resistance) using direct burial methods or conduit; Schedule 80 PVC or 2-inch SDR-11 HDPE conduit as acceptable alternates with detectable geotextile fabric; non-armored riser-rated fiber for indoor transitions; LC connectors with 12-strand capacity; trench backfill compaction testing at 100-200 linear foot intervals per ASTM D1557 standards; and Luke AFB-specific fiber optic testing standards (OTDR and bi-directional). The contractor must obtain Blue Stake utility location requests and AF Form 103 approval (estimated 4-week lead time), maintain utility markings throughout construction, and treat all existing manholes as confined spaces. Asbestos-containing floor tiles exist at Building 979, requiring OSHA-compliant drilling procedures when anchoring the new network cabinet. The project is set aside under the Women-Owned Small Business (WOSB) program with NAICS code 335921 (Fiber Optic Cable Manufacturing), carrying a 1,000-employee small business size standard and a 50-percent subcontracting limitation on the supply portion only. Authorized working hours are 7:30 AM to 4:30 PM standard; airfield work may require nighttime hours outside the 0630-2230 Monday-Thursday and 0630-1830 Friday flying schedule, with temporary construction waiver and FAA 7460-1 submission required 45 days prior. The proposal deadline has been extended to November 30, 2026, with no further extensions or questions to be answered. Award date, Notice to Proceed, and final completion date will be determined post-evaluation; however, the Government may modify the period of performance based on material lead times. Proposals must be limited to 25 pages with separate technical and pricing volumes, excluding lump-sum pricing, and are evaluated on technical capability (management and installation personnel qualifications per SOW Section 2.1.8.4), past performance (Prime Contractor SPRS records only; contractors with no SPRS score receive neutral rating and remain eligible), and pricing factors. First-tier subcontractor personnel may satisfy staffing requirements under the same evaluation criteria. Base access requires a Real ID or government-issued passport, with requests submitted through the Contracting Officer to the Security Force Squadron for processing and approval or denial.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Site Visit Q&A

1. ATCT (B998): Can we use armored fiber optic cabling inside from the transition point instead of running non-armored fiber in innerduct. The use of armored fiber will eliminate the need for innerduct. Or would you like it to be non-armored and in innerduct? Does the existing chase have enough space on each floor for a ¾” innerduct?

Answer: Engineer recommends a transition splice and installing riser/planum cable inside the building. There should be plenty of space in the existing chase.

2. Are we boring under the two runways between LOC B1059 & FMQ-19 (Primary) and between TACAN & FMQ-19 (Backup). If so, are we installing conduit under these runways?

Is this considered a unique situation that requires schedule 80? Are we encasing the pipe with concrete/slurry?

Answer: SCHD-80 conduit is required. CE does not currently require concrete, grout, or slurry encasement for the proposed Schedule 80/HDPE directional bore crossing beneath the runway.

HDD drilling fluid utilized during the installation process is considered incidental to the bore operation and is not a separate encasement requirement.

Please provide the proposed bore profile showing the minimum vertical separation between the top of the conduit and the bottom of the runway pavement structure, including base and subbase layers.

3. For direct burial fiber, can you provide a trenching detail? I.E. trench depth, shade material needed, backfill soil required (native or fill).

Answer: Direct buried fiber is required to be double armored unless an alternate solution is proposed and approved by the government. CE concurs with the engineer’s recommendation regarding the conduit material. The conduit or direct buried fiber shall be installed with a minimum of 3 to 4 inches of shading material completely surrounding the direct buried fiber/pipe to provide adequate protection and support. The remainder of the trench backfill may consist of existing native materials.

Backfill shall be placed in maximum 8\-inch loose lifts and compacted to not less than 95 percent of the maximum dry density as determined by ASTM D1557. Moisture content shall be maintained within the range necessary to achieve the specified density. Compaction shall be performed in accordance with the contract specifications and verified through field density testing as required. Disturbed areas shall be restored to their original grade and condition upon completion of the work.

4. Will we need compaction tests on trench backfill? What intervals are they needed at?

Answer: UFGS 31 23 00.00 20 Excavation and Fill for Utilities and UFGS 31 00 00 Earthwork, in-place nuclear or sand-cone compaction testing for utility trenches in unpaved airfield infields is required at a minimum interval of one test per 100 to 200 linear feet.

5. FMQ-19 Primary (Sketch 20) – Does the pad that’s supporting the tower structure need to be cut and repaired in order to bring the new conduit from the NEMA box to below grade?

Or are those weather heads stubbing below grade already?

Answer: Engineer indicates their belief that it can be brought up and jog the connection or use liquid-tight without disturbing the existing pad; however, if cutting the pad is absolutely necessary then it is the contractor’s responsibility to repair/fix it and restore it to the original condition.

6. FMQ-19 Back Up (Sketch 21) – Does the pad that’s supporting the tower structure need to be cut and repaired in order to bring the new conduit from the NEMA box to below grade?

Or are those weather heads stubbing below grade already?

Answer: Engineer indicates their belief that it can be brought up and jog the connection or use liquid-tight without disturbing the existing pad; however, if cutting the pad is absolutely necessary then it is the contractor’s responsibility to repair/fix it and restore it to the original condition.

7. 1.0 Scope says 12 Strand (ST) but 2.2.3.7 Cable Terminations spec in LC Connectors. Is it LC or ST connectors?

Answer: ST is “Strand”, connections are LC.

8. What is the spec on the preferred rack for RAPCON?

Answer: Full size NW cabinet installed adjacent to existing NW cabinet with side panels removed.

9. ATCT (B998) Sketch 12 – The photo at the top of Sketch 12 is showing a rack with an arrow pointing to it suggesting a new backer board location and FODP. The arrow is pointing at a rack. Expand on how/where you would like this terminated; we can’t install a backer board in a rack. Is the FODP going inside the rack? Is there at least 1U available in the rack for an

LIU (FODP)?

Answer: Rack mounted FODP.

10. GATR (B1040) – Sketch 14 – Can we free run the fiber on the cable tray once inside the building? Or would you like innerduct from the 4” Stub Ins to the rack where the fiber will terminate?

Answer: Innerduct is preferred, but if the space is limited, free run on the cable tray is acceptable.

11. (SOW 2.2.4.2, Note 2; Sketch 12) For the fiber transition from the ATCT ground-floor entrance facility/mechanical room to the 8th-floor cabinet, what indoor cable construction is required: interlocking-armored CMP, non-armored tight-buffered CMP, or another specified cable type? Please confirm strand count, plenum/riser rating, armor requirement, fire rating, and whether a transition splice enclosure and indoor-rated cable are required at the ground floor.

Answer: Non-armored riser rated.

12. (SOW 2.1.5; 2.2.3.3; Q&A Nos. 9 and 50) Must the Contractor submit the Arizona 811/Blue Stake request and coordinate any additional utility locating required within Luke AFB? Published Q&A indicates that the Contractor coordinates Blue Stake and submits AF Form 103, while the Government performs locating for Government-owned base utilities.

Please confirm the required sequence, lead times, fees, responsibility for re-marks, and any additional locating that must be included in the Contractor price.

Answer: The Contractor shall be responsible for contacting 811/Blue Stake, submitting the utility locate request, and coordinating all actions required to initiate the utility locate process.

The Contractor shall provide the applicable Blue Stake ticket number on the front of the AF Form 103 and include a site/location map identifying all proposed excavation areas.

The Government will process the AF Form 103 and return the completed form to the Contractor. The estimated lead time for processing and approval of a dig permit is approximately four (4) weeks.

Once utility locations have been marked by Civil Engineering (CE), the Contractor shall be responsible for maintaining, protecting, and reestablishing all utility markings as necessary throughout the duration of construction activities. Any remarking required due to disturbed, damaged, or removed markings shall be the responsibility of the Contractor.

13. (SOW 2.1.5; 2.2.3.3; Q&A No. 50) After the Contractor submits the Arizona 811/Blue Stake ticket and AF Form 103, will Luke AFB locate and mark all Government-owned utilities that are not covered by Arizona 811? Please identify any utility systems excluded from the Government locating service and state whether the Contractor must include private utility locating, ground-penetrating radar, electromagnetic locating, potholing, vacuum excavation, or other subsurface investigation in its price.

Answer: All Government-owned utilities will be covered under the AF Form 103 process. CES does not require the Contractor to perform private utility locating, ground-penetrating radar (GPR), electromagnetic locating, potholing, vacuum excavation, or other subsurface investigations. Any additional utility investigation is at the Contractor's discretion and expense.

14. (SOW 2.2.2; 2.2.4.1.4; Sketch 11; Q&A No. 17) Is a specific manufacturer or cabinet series required for the new full-size RAPCON network cabinet? If not, please provide the minimum acceptable dimensions, rack-unit capacity, door configuration, seismic criteria, and lock/key standard. Published Q&A identifies lockable Vertiv/Great Lakes cabinets for Luke AFB standardization. Please confirm whether this is a mandatory requirement or a preference and identify the approved series or minimum performance requirements.

Answer: SOW references in the question indicate a 7-Feet (full-size) network cabinet installed next to the existing cabinet. The existing cabinet is a full-size Great Lakes cabinet.

Preference is a Vertiv/Great Lakes cabinet or equivalent with side panels removed. Luke AFB is not in a Seismic zone, but the facility is mission critical. These are square racks (not 2-post) so no overhead anchor is required. Bolts should be ICC-ES Seismic-Qualified Expansion/Undercut/Screw Anchor rated for Cracked Concrete (e.g., Hilti KB-TZ2, Simpson Strong-Bolt 2).

15. (SOW 2.2.4.1.4; Sketch 11) Is the Contractor required to install a new 4-inch conduit from the hard-lid ceiling to the new RAPCON cabinet, similar to the pathway serving the existing cabinet? Please confirm conduit material, length, supports, penetrations, firestopping, routing, and whether ceiling removal/restoration is included.

Answer: Luke AFB is not in a Seismic zone, but the facility is mission critical. These are square racks (not 2-post) so no overhead anchor is required. Bolts should be ICC-ES Seismic-Qualified Expansion/Undercut/Screw Anchor rated for Cracked Concrete (e.g., Hilti KB-TZ2, Simpson Strong-Bolt 2).

16. (SOW 2.1.4; 2.2.4.1.4; Sketch 11 Note 2; Environmental Guide Part 3.1; Q&A Nos. 19 and 35) Please confirm whether existing floor tile, mastic, or other materials that may be disturbed during cabinet anchoring or related work at RAPCON contain asbestos or other regulated materials. If regulated material is present, will the Government complete the required survey and abatement before Contractor installation? If not, please define the Contractor responsibilities for sampling, controlled drilling, abatement, disposal, regulatory notifications, permits, schedule impacts, and associated costs. Please provide the current survey or test report, if available, and identify the approved anchoring method.

Answer: The floor tiles are asbestos. Contractor is required to use proper drilling and disposal methods.

17. (SOW 2.2.4.2) Please first confirm whether SOO 1.1.2 and 3.1.6 on pages 62–79 remain applicable to this procurement. If applicable, is the Contractor required to furnish fiber patch cords between Contractor-furnished FOTS equipment and Government-furnished FODPs? If this scope remains applicable, please provide the quantity by location, length, fiber type, jacket rating, polarity, and connector configuration, including LC-LC, LC-ST, LC- SC, or other interfaces. Please also identify any patch cords required for spares or testing.

If this scope is excluded, please confirm that no patch cords associated with the excluded SOO are required.

Answer: This is part of the vendor’s design.

18. (SOO 1.1.1-1.1.4; 3.1; 3.1.6; Table 2; Figure 3 (pages 62-79)) Please first confirm whether SOO pages 62–79, including the FOTS analog voice, dial-up modem, STATUS, and CONTROL requirements, remain part of this procurement. If they remain applicable, please provide a location-by-location scope matrix identifying exactly what the Contractor must furnish, install, terminate, cross-connect, configure, test, and document. If this scope remains applicable, please identify module types and quantities, FXS/FXO/E&M assignments, 24-AWG cable pair counts and lengths, 66-block quantities, demarcation points, outage and cutover responsibilities, and acceptance testing. Please also reconcile references to Government-furnished equipment, FODPs, wallboards, rack space, circuits, and demarcation facilities with the current SOW statement that the Contractor must provide all equipment, supplies, and materials and that no equipment, supplies, or materials will be furnished by the Government. If pages 62–79 are excluded, please confirm that no pricing or technical submission for this work is required.

Answer: This is part of the vendor’s design.

19. (SOO 3.1.5 Glideslope 1081) If the Government confirms that the cited SOO requirements on pages 62–79 remain applicable, is an existing dedicated 110/120 VAC receptacle and circuit available at Glideslope Building 1081 for the specified 1 kVA UPS?

Please confirm voltage and frequency. The SOO states 110 VAC, 50 Hz, which appears inconsistent with typical U.S. 60 Hz power. Identify receptacle type, breaker capacity, distance from the wallboard, and whether electrical work is included. If the cited SOO scope is excluded, please confirm that no related equipment, cabling, power, cross-connect, programming, testing, or documentation is required.

Answer: This was a typo in the original SOO. The outlets are 120V 60Hz, 20A NEMA 5-20R.

20. (SOO 3.1.5 RAPCON 979; 3.1.5.1) If the Government confirms that the cited SOO requirements on pages 62–79 remain applicable, please define the complete Contractor scope for the RAPCON copper interface, including all required furnish, installation, termination, cross-connect, testing, and documentation responsibilities. Confirm the number and type of 66 blocks, whether underfloor cable racking exists or must be installed, cable type and estimated footage, pair counts, cross-connects, voice-demarc location, and the final location of the GFE LC FODP for Glideslope, Localizer, and TACAN circuits. If the cited SOO scope is excluded, please confirm that no related equipment, cabling, power, cross-connect, programming, testing, or documentation is required.

Answer: This is part of the vendor’s design.

21. (SOO 3.1; Table 2; Figure 3) If the Government confirms that the cited SOO requirements on pages 62–79 remain applicable, for each circuit shown in Table 2 and Figure 3, please identify the equipment, modules, cabling, cross-connects, programming, testing, training, and cutover work required in addition to the outside-plant fiber. Please also confirm whether Table 2 and Figure 3 remain part of this procurement. Please distinguish Contractor-furnished equipment and labor from Government-furnished equipment, information, circuits, rack space, wallboards, and demarcation facilities. If the cited SOO scope is excluded, please confirm that no related equipment, cabling, power, cross-connect, programming, testing, or documentation is required.

Answer: This is part of the vendor’s design.

22. (SOO 1.1.1-1.1.2; 3.1.1-3.1.5) If the Government confirms that the cited SOO requirements on pages 62–79 remain applicable, are the 66 blocks Contractor-furnished, and how many are required at each ILS/TACAN location and at RAPCON? Are UPS units required only at the two Glideslopes, two Localizers, and TACAN, or also at RAPCON?

Please confirm UPS quantity, rating, voltage/frequency, mounting, runtime, receptacle availability, dedicated circuit requirements, and responsibility for new electrical circuits. If the cited SOO scope is excluded, please confirm that no related equipment, cabling, power, cross-connect, programming, testing, or documentation is required.

Answer: This is part of the vendor’s design.

23. (SOW 3.1; Solicitation delivery schedule; Q&A No. 14) ACG has received preliminary supplier information indicating that compliant fiber-optic cable may have an extended manufacturing lead time that could affect the required completion date. Please confirm the anticipated award date, Notice to Proceed, required substantial and final completion dates, and the controlling period of performance. If compliant cable cannot be delivered within the required period despite timely procurement, please confirm whether the Government will consider an approved equivalent cable, a schedule extension, or another contractual remedy. ACG can provide manufacturer or distributor lead-time documentation if requested.

Answer : Anticipated award date is not available at this time due to unknowns associated with technical evaluations required on proposals. NTP, final completion date and Period of Performance will be determined once evaluations are complete. No cost period of performance extensions will be reviewed and discussed with awardee should the need arise.

24. (SOW 2.2.3.10; 2.2.4.2; Q&A No. 49) May the Contractor install conduit by trenching or horizontal directional boring in designated direct-burial segments instead of placing armored cable directly in earth? Please confirm whether an all-dielectric cable in an approved conduit is acceptable, required conduit size/material, handhole spacing, cost responsibility, and approval process for route deviations.

Answer: Yes, direct buried armored cable or dielectric cable inside conduit is acceptable.

25. (SOW 2.2.12.1-2.2.12.2; Figure 4/Sheet 50; Q&A Nos. 15 and 39) Will the Government provide existing butterfly drawings for all existing manholes and handholes included in the new cable routes? If drawings are only available after award, please identify the proposal assumption for duct orientation, occupancy, rack condition, and required field documentation.

Answer: Relevant butterfly drawings for all existing manholes and handholes will be provided after award. SOW contains sketches that provide information needed to develop a design/proposal.

26. (SOW 2.2.3.4-2.2.3.5; 2.2.4.2 route tables and splice notes) Will the Government issue a definitive fiber splice diagram and strand-assignment schedule? Please provide splice locations, incoming/outgoing cable counts, active/dark strand assignments, tray capacities, closure requirements, connector assignments, and required labeling for each splice point.

Answer: This is part of the vendor’s design.

27. (SOW 2.2.3.10.8; Sketches 20 and 21; Q&A No. 11) What dimensions and configuration are required for the new NEMA 4X enclosures at the FMQ-19 primary and backup sites?

Please confirm enclosure material, minimum size, mounting method, internal backboard dimensions, FODP model/port count, conduit entries, grounding, environmental rating, and whether the new enclosure connects to an existing box or directly to the FMQ equipment.

Answer: This is part of the vendor’s design.

28. (SOW 2.2.4.1.3 Note 3; Environmental Guide Part 3.2) What disposition is required for the abandoned 25-pair copper cable removed from the conduit between HH-705-2 and New HH-1? Please confirm whether the cable becomes Contractor property for recycling, must be delivered to a Government-designated scrap area, or requires a recycling receipt and credit to the Government. Identify required weight tickets, manifests, or monthly recycling reports.

Answer: SOW para 2.2.5 addresses disposal of project residue.

29. (Solicitation Q&A No. 8; FAR/DFARS clauses; SOW civil and installation requirements) The solicitation characterizes this procurement as a commodity requirement with incidental construction. The stated work includes fiber installation using existing and new pathways, manholes and handholes, direct-buried cable segments, restoration, testing, and other field installation activities. Depending on the Government responses to the preceding questions, the work may also include trenching, boring, new conduit, electrical work, building penetrations, or regulated-material controls. Please clarify the contractual treatment of the field installation and civil portions of the work. Please confirm whether the Davis-Bacon and Related Acts labor standards, Service Contract Labor Standards, or another wage requirement applies. If a wage determination applies, please identify the controlling determination and the covered work activities and labor classifications. Please also identify applicable bonding, insurance, certified-payroll, construction-clause, and licensing requirements, and the basis offerors should use to separate commodity or material pricing from field installation and construction pricing.

Answer: Asked and answered in Q&A document, question 8. This is not a construction project, rather it is a commodity with incidental construction.

30. (FAR 52.219-14) Please confirm the limitation-on-subcontracting category applicable to this combined supply, installation, civil, testing, and commissioning requirement. Please identify whether supplies, services, general construction, special-trade construction, or another category governs and provide the applicable percentage, calculation basis, material/equipment treatment, and similarly situated entity treatment.

Answer: Per Federal Acquisition Regulation (FAR) 19.505(b) and FAR Clause 52.219-14 (Limitations on Subcontracting), the applicable limitation-on-subcontracting category is Supplies. This is determined by the single NAICS code assigned to the solicitation, which is 335921 (Fiber Optic Cable Manufacturing), carrying an SBA small business size standard of 1,000 employees.

Applicable Percentage and Calculation Basis: Under FAR 52.219-14(e)(2), for a mixed contract assigned a NAICS code for supplies, the limitation on subcontracting applies only to the supply portion of the contract. The Prime Contractor must not pay more than 50 percent of the amount paid by the Government for the supply portion of the contract to subcontractors that are not similarly situated entities. Because the civil, installation, testing, and commissioning elements are incidental to the fiber optic cable procurement, payments to subcontractors for these non-supply elements are excluded from the 50 percent limitation calculation.

Material and Equipment Treatment: In accordance with FAR 52.219-14(e)(2), the "cost of materials" is excluded from the 50 percent calculation. However, if the Offeror is a reseller rather than the manufacturer of the fiber optic cable, they must comply with FAR 52.219-33 (Nonmanufacturer Rule). This means they must furnish fiber optic cable manufactured by a domestic small business, unless an SBA waiver applies. Offerors should note that an active SBA Class Waiver exists for "Overhead Fiber Optic Groundwire & Ancillary Hardware Components" under NAICS 335921. If the specific items being procured fall under the scope of this Class Waiver, the requirement to supply the product of a small business manufacturer is waived, though the prime contractor must still comply with the overall 50 percent subcontracting limit for the supply portion.

31. (FAR 52.219-14 and FAR 52.219-30) Please confirm whether work performed by a first-tier subcontractor that independently qualifies as a WOSB and is small under the NAICS assigned to its subcontract will be treated as work performed by a similarly situated entity.

Please identify required SBA certification, SAM representations, NAICS designation, commitment documentation, subcontract information, and workshare disclosure.

Answer: Per FAR 52.219-14(b) and (e), first-tier subcontracts issued to similarly situated entities—defined as subcontractors that hold the same small business program status required by the solicitation and are small under the NAICS code assigned to their subcontract—are excluded from the 50 percent calculation. Any work that a similarly situated entity further subcontracts to an entity that is not similarly situated will count toward the 50 percent subcontracting limit.

32. Subcontracting and WOSB performance requirements. Is the offeror required to disclose the anticipated percentage of work performed by the Prime Contractor and each proposed subcontractor? Please provide the calculation method, treatment of material/equipment costs, treatment of similarly situated entities, and required proposal location.

Answer:

1. Disclosure Requirement and Proposal Location:

No. Offerors are not required to disclose or submit an upfront percentage breakdown of the work to be performed by the Prime Contractor and each proposed subcontractor in their proposal. There is no designated or required proposal location for this information .

By submitting an offer, the contractor certifies and agrees that it will comply with the performance and subcontracting limitations during contract execution in accordance with FAR 52.219-14 and FAR 52.219-30. Compliance with these limitations is a matter of contractor responsibility and post-award contract administration. However, offerors are cautioned that if a proposal, on its face, explicitly indicates that the offeror does not intend to comply with the subcontracting limitations, the proposal will be deemed technically unacceptable and ineligible for award .

2. Calculation Method:

Because this requirement is set aside under the Women-Owned Small Business (WOSB) Program and assigned NAICS code 335921 (Fiber Optic Cable Manufacturing), it is governed by the Supplies category . Per FAR 52.219-14(e)(2), the limitation on subcontracting applies only to the supply portion of the contract. The Prime Contractor must not pay more than 50 percent of the amount paid by the Government for the supply portion of the contract to subcontractors that are not similarly situated entities. The civil, installation, testing, and commissioning elements are incidental services and are excluded from this 50 percent calculation.

3. Treatment of Material and Equipment Costs:

In accordance with FAR 52.219-14(e)(2), the "cost of materials" is excluded from the 50 percent calculation. However, if the Offeror is a reseller/nonmanufacturer of the fiber optic cable, they must comply with FAR 52.219-33 (Nonmanufacturer Rule). This requires them to furnish fiber optic cable manufactured by a domestic small business, unless an SBA waiver applies . Offerors are advised that an active SBA Class Waiver exists for "Overhead Fiber Optic Groundwire & Ancillary Hardware Components" under NAICS 335921. If the specific items being procured fall under the scope of this Class Waiver, the requirement to supply the product of a small business manufacturer is waived, though the prime contractor must still comply with the overall 50 percent subcontracting limit for the supply portion.

33. Proposal responsibility and subcontractor resource requirements. If the offeror relies on subcontractor personnel, qualifications, equipment, certifications, technical capabilities, or experience, is a formal teaming agreement required? Please confirm whether a commitment letter, MOU, letter of intent, conditional subcontract, or exclusive/non-exclusive teaming agreement is acceptable and identify the minimum required commitment.

Answer: No. The solicitation does not require the submission of a formal teaming agreement, letter of commitment, memorandum of understanding (MOU), or any other formal teaming documentation.

34. Proposal submission and subcontractor commitment requirements. If teaming documentation is required, must it be submitted with the quotation? Please identify required legal names, UEI/CAGE data, scope allocation, workshare, personnel commitments, exclusivity, signatures, duration, and commitment to execute a subcontract. Please confirm whether a redacted agreement or summary is acceptable.

Answer: N/A. Teaming documentation is not required to be submitted with the quotation.

35. Technical Capability, Subfactor C. Please identify the security clearance, installation-access authorization, background screening, citizenship, or credential required for each management and installation labor category. Please confirm processing lead times, subcontractor requirements, escort availability, foreign-national restrictions, and treatment of access delays.

Answer: Base access requests will be submitted to the Contracting officer for processing. To obtain base access a Real ID or Government issued passport is required. The request will be submitted to SFS for processing, and the employees will receive an approval or denial letter stating reason for denial.

36. Technical Capability, Subfactor C. Please identify the minimum technical certifications required for proposed management and installation personnel. Please classify BICSI RCDD/Installer/Technician, manufacturer fiber, fusion splicing, fiber testing, OSHA 10/30, competent person, confined space, excavation, airfield driving, licensing, and TC Communications factory certification as mandatory, preferred, or informational.

Answer: SOW para 2.1.8.4 stipulates minimum contractor qualifications.

37. Technical Capability, Subfactor C. May first-tier subcontractor personnel satisfy management, technical, supervisory, or installation staffing requirements? If permitted, please confirm whether names, resumes, certifications, access eligibility, and commitment letters are required and whether these personnel are evaluated the same as Prime personnel.

Answer: Yes, first-tier subcontractor personnel may satisfy the management, technical, supervisory, or installation staffing requirements under Technical Capability, Subfactor C.

As this is a Simplified Acquisition, individual names, resumes, and Letters of Commitment are not required at the proposal stage. However, the Offeror must clearly demonstrate in their technical proposal how the proposed subcontractor's capabilities and certifications meet the requirements of Subfactor C.

Proposed subcontractor capabilities will be evaluated under the same criteria and standards as the Prime Contractor. The Prime Contractor remains solely responsible for ensuring all staff (including subcontractors) obtain and maintain required base access/security clearances and comply with FAR 52.219-14 (Limitations on Subcontracting).

38. Factor 2, Past Performance. Please confirm whether the Government will evaluate only the Prime Contractor SPRS record or may also consider first-tier subcontractor or teaming-partner SPRS records. Please identify whose SPRS record will be reviewed and whether subcontractor/team CAGE codes must be submitted.

Answer: The Government will pull SPRS reports for the Prime contractor.

39. Factor 2, Past Performance. If subcontractor or teaming-partner SPRS records may be considered, please explain how multiple ratings will be evaluated. Please confirm whether ratings are separate, collective, or workshare-weighted and whether one unacceptable team-member rating could make the quotation unacceptable.

Answer: The Government will pull SPRS reports for the Prime contractor.

40. Factor 2, Past Performance. Please confirm how the Government will evaluate an offeror with no applicable SPRS history, including whether the offeror will receive a Neutral rating and remain eligible for award. Please identify whether PPQs, CPARS records, project references, narratives, subcontractor history, or customer contacts may or must be submitted when the offeror has no applicable SPRS history.

Answer: Contractors who have “No Score” in the SPRS system will be rated neutral and still be able to participate in the procurement. Contractors may submit past performance if they wish to, however it is not required.

41. In reference to Question #6 of the previously released Q&A, could the Government please provide the complete proposal preparation and submission requirements, including required documentation, technical and pricing requirements, proposal organization, and submission procedures?

Answer: The proposal submitted should accurately cover all aspects of the requirements and information outlined in the subfactors to be addressed. Please limit proposals to 25 pages total. Proposal should contain a technical volume that addresses requirements listed in the solicitation, along with a pricing volume that details pricing for the requirement.

LUMP SUM PRICING WILL NOT BE ACCEPTED

42. Authorized Working Hours: Please confirm the authorized working hours for both non-airfield and airfield work, including any restrictions on workdays, access windows, or required coordination. Hours of operations stated are 7:30AM to 4:30PM, Flight line hours do not align with the hours of operation. Will nighttime work be required?

Answer: SOW para 3.3 provides standard base operating hours as well as procedures to request performing work outside of these hours. Temporary construction waiver will be required before work can be started on the airfield, as well as FAA 7460-1 submission NLT 45 days prior to the start of construction. Airfield flying hours are 0630-2230 M-Th & 0630-1830 on Fridays, however we highy encourage work to be completed outside of flying.

43. Fiber Cable Lead Time and Proposed Alternate Installation: Armored direct-burial fiber-optic cable currently has an estimated lead time of approximately 52 weeks, which exceeds the project’s 180-day period of performance.

a. Would the Government consider revising the scope to allow PVC or HDPE conduit with alldielectric outside-plant (OSP) fiber-optic cable at all locations designated to receive new fiber? The proposed conduit could be installed using horizontal directional drilling to reduce the time required to perform work within the airfield.

b. Please confirm whether this alternate installation method is acceptable.

Answer: Though the main reason for direct bury was due to gophers. 2” HDPE would address this. So, 2in SDR-11 HDPE or 2” Schedule 80 PVC would work. The strength requirement is due to being on the airfield. Such a change would also require pulling thru 3x1.25” detectable geotextile fabric such as MaxCell MXED32123. The government can modify the period of performance based on material lead times.

44. Fiber Cable Armor Requirements:

a. If armored fiber-optic cable is required, please confirm whether single-armored or double armored cable is required and identify the applicable cable construction requirements.

Answer: Double Armored. The goal is rodent resistance. Corrugated Steel Tape (CST/ECCS) or CST with galvanized Steel Wire Armor (SWA).

45. Hazardous Materials Abatement

a. Please confirm whether hazardous materials abatement will be required in any buildings affected by this project. If required, please identify the locations, materials, and extent of abatement, and confirm whether this work is included in the contractor’s scope.

Answer: Per SOW sketch 11, note 2, Bldg 979 floor tile and mastic contain asbestos, and contractor shall follow OSHA guidance when drilling to anchor the new cabinet.

46. Trenching and Surface Restoration

a. During the site visit, it was stated that all trenching for new fiber-optic cables would occur within dirt or gravel areas. Please confirm that no asphalt or concrete demolition, patching, or restoration is required under this contract. If such work is required, please identify the locations and applicable restoration requirements.

Answer: The information provided during the site survey is accurate to our knowledge.

There is no known asphalt or concrete demolition, patching, or restoration that is required under this contract.

47. Is the contractor responsible for private utility locating?

Answer: The Contractor shall be responsible for contacting 811/Blue Stake, submitting the utility locate request, and coordinating all actions required to initiate the utility locate process.

The Contractor shall provide the applicable Blue Stake ticket number on the front of the AF Form 103 and include a site/location map identifying all proposed excavation areas.

The Government will process the AF Form 103 and return the completed form to the Contractor. The estimated lead time for processing and approval of a dig permit is approximately four (4) weeks.

Once utility locations have been marked by Civil Engineering (CE), the Contractor shall be responsible for maintaining, protecting, and reestablishing all utility markings as necessary throughout the duration of construction activities. Any remarking required due to disturbed, damaged, or removed markings shall be the responsibility of the Contractor.

48. How many of the existing manholes are confined space?

Answer: All manholes are considered confined space. Handholes are not considered confined space.

49. Have the existing conduits been proofed? Is there mule tape in the existing conduits?

Answer: The existing conduits have not been proofed and it is unknown if the conduits have useable mule tape. Recommend your proposal includes installation of new mule tape.

50. Will an area be provided for a storage container and lay down yard?

Answer: SOW para 3.5 addresses base support including the process to request storage and lay down yard.

51. Please confirm the Luke AFB standards for Fiber optic testing OTDR & Bi-directional apply to this project.

Answer: The SOW provides fiber optic testing requirements.

52. Is it possible to extend the bid due date to one week after the RFI answers are available to the contractors?

Answer: Extension has already been granted to 30 November 2026. As stated in the SAM.gov posting there will be no additional questions answered and no extension to the due date issued.

53. The project currently specifies the installation of armored cable using direct burial install. However, extended procurement lead times for the specified armored cable may impact the project schedule and delay install activities. WOULD Gov. consider approving an alternate method utilizing standard osp rated fiber in conduit in lieu of specified direct burial armored fiber.

Answer: Yes, the concept/design is acceptable. One of the reasons direct buried cables were requested was to save money and installation time.