Q and A.xlsx
XLSX spreadsheet 12 KB Posted
- Attached to
- DAMAS Kit Airlift Shoring
- Solicitation number
- F2BDAP4220A004
About this file
This document contains a set of questions and answers regarding a federal contract opportunity for a DAMAS Kit Airlift Shoring. The key details are:
The contract is for the procurement and delivery of one DAMAS kit to support C-130 loading for the AN/TPY-4(V)1 radar. The contractor will be responsible for ensuring the kit conforms to the manufacturer's specifications and the Statement of Work (SOW). The SOW specifies requirements such as weight capacity, ramp pedestal dimensions, and loading/towing capabilities. The government has provided clarification on several technical questions, including the use of aluminum pedestal shoring, the trailer configuration, and the scope of the contract (product only versus product and service). This is a new requirement, not an incumbent contract. The solicitation is being issued by the Department of the Air Force Materiel Command Lifecycle Management Center at Hanscom Air Force Base.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| # | Question | Government Response/Answer | |
| 1 | On the SOW, paragraph 3. it states “weight capacity of 20,000 lbs. per axle and must interface with C-130 aircraft.”, and it has the Ramp Pedestal dimensions as, “Length 18” Width 30 …”. The maximum axle capacity of the C-130 is only 13,000lbs, and the C-130 Ramp Pedestal only requires an 18”x18” area. Is this also to be used for C-17 loading? If so you might want to include C-17 Loading in paragraph 1. | We are receiving a C-130 axle load waiver for greater than 13,000 lbs. The shoring is not required for loading on the C-5 or C-17. | |
| 2 | Without seeing the ATTLA certification for the AN/TPY-4(V)1 Radar, it is difficult to determine the characteristics based solely on the combined synopsis. (No classified info is allowed on ATTLA certs, so you could include it in the solicitation on SAM.gov). | ||
| a. | Some trailers that are being winched into an aircraft require a center runway to support a tongue wheel. Is this solicitation for 2-runways or 3-runways? | ||
| b. | Some trailers have very small diameter wheels/tires, smaller than normal “highway-sized” tires. This is commonly found on helicopters, AGE equipment, or caster wheels. Does this trailer have smaller than normal tires/wheels? | ||
| c. | Will the trailer be towed into the aircraft or winched. If it will be towed, what is the expected prime mover? How heavy are the axles of the prime mover (towing vehicle)? | a. 2 runways. The PG is on Mobilizers, this allows Roll On/Roll Off (RO/RO) |
b. Large tires, max tire pressure less than 100psi
c. The PG will be winched in
| 3 | What is meant by “support contract C-130 Loading” in paragraph 1 of the SOW (and again in paragraph 10 of the combined synopsis/solicitation file)? Also in paragraph 10 of the combined synopsis file it states, “The contractor shall be responsible for ensuring all services and parts…”. It can be construed that the contract will not only be for the DAMAS shoring kit, but also includes setting it up at the time of loading/deployment. Will this be a contract for only a product (e.g. shoring kit), or will it include a service to “Support Contract Loading”? | The contract is only for the shoring kit. AirForce personal will deploy the shoring. |
| 4 | On “Figure 42” it shows a box (TPY-4 System Equipment) in front of an item with wheels. How is that item loaded? Is it palletized or floor loaded? I just want to know about any other items that may transverse across the shoring | The item with wheels is the Mobilizer used for loading the TG (Transceiver Group – radar antenna). |
| 5 | There are two products we offer for Pedestal Shoring stack. a. Lightweight western red cedar. Patterned off of the "old school" wooden shoring, but much lighter, and naturally resistant to mold, mildew, and insect infestion. b. Aluminum Pedestal Shoring. Which would you prefer? | Aluminum Pedestal Shoring |
| 6 | Will the government please clarify if there is an incumbent providing service on this contract or is this level of effort a new need? | This a new need/requirement. |