S01_Attachment_II-BPA_Call_Order_1_SOW.docx
DOCX document 24 KB Posted
- Attached to
- CommScope Cabling and Networking Project Federal contract opportunity
- Solicitation number
- EXIM17Q0056
- Issued by
- Export Import Bank of the US
About this file
Attachment II-BPA Call Order #1 SOW
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| EXIM17Q0056_Amendment_0001.pdf | ||
| S10_Addendum_to_52212-1_Instructions_to_Offerors.docx | DOCX document | |
| S01_Attachment_III-Data_Drawings_-_Base_Package_001_-_EXIM_COMMScope_Data_Drops.pdf | ||
| S10_Addendum__EXIM17Q0056__Terms_and_Conditions.docx | DOCX document | |
| S01_Wage_Determinations.txt | TXT text file | |
| S01_Attachment_I-BPA_SOW.docx | DOCX document | |
| S10_EXIM17Q0056-Combined_Synopsis-Solicitation.doc | DOC document | |
| S10_Attachment_IV-Past_Performance_Questionnaire.docx | DOCX document | |
| S10_Addendum_to_52212-2_Evaluation-Commercial_Items.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment II-BPA Call Order 1 SOW Statement of Work EXIM BPA Call Order #1 for CommScope Cabling and Networking Project
General Overview
The first BPA call order will require the contractor to provide CommScope cabling and networking services to the following EXIM Bank locations. EXIM Bank anticipates the following project milestone completion dates:
| Milestone # |
| Floor |
| Milestone Date |
| 1 |
| 1st Floor Health Unit |
| August-September 2017 |
| 2 |
| 10th Floor Transportation |
| June-July 2017 |
| 3 |
| 11th Floor Export Finance |
| October-November 2017 |
| 4 |
| 11th Floor Admin. Services |
| July-August 2017 |
| 5 |
| 12th Floor Vice Chair |
| June 2017 |
| 6 |
| 12th Floor EEO |
| July 2017 |
| 7 |
| 12th Floor Lactation Room |
| January-February 2018 |
| 8 |
| 9th Floor North- Credit |
| December 2017 – March 2018 |
| 9 |
| 9th Floor North East- Engineering |
| December 2017 – March 2018 |
The contractor will have a one year period of performance to complete this task, beginning on or about June 12, 2017 and ending on or about June 11, 2018; however, it is anticipated that the contractor can do the by the end of March 2018 in accordance with the aforementioned schedule.
A blueprint of each floor is provided as Attachment III-Data Drawings - Base Package 001 - EXIM COMMScope Data Drops.pdf and should be referenced by contractors when preparing their technical and price proposals.
An overview and an estimate of the work required for each milestone number is provided below:
1. 1st Floor Health Unit
Overview:
Export Import Bank (EXIM) is looking for a contractor to perform data and cable installations and adjustments at the Lafayette building on the Health Unit space. EXIM is replacing rental furniture with purchased furniture throughout their occupied space. The area within EXIM’s occupied space to receive new furniture is the (1,816 SF),1st Floor Health Unit. In order to accommodate the new furniture, installation of power and data cabling that will support furniture functions are required in the space.
Work to be completed: (Refer to Drawing ISK-016 for counts and locations)
· Install 13 new data drops
· Install new CommScope 24-port patch panel
· Test and label cabling in workstations to CommScope specifications.
2. 10th Floor Transportation
Overview:
Export Import Bank (EXIM) is looking for a contractor to perform data and cable installations and adjustments at the Lafayette building on the Transportation space. EXIM is replacing rental furniture with purchased furniture throughout their occupied space. The area within EXIM’s occupied space to receive new furniture is the (2,550 SF),10th Floor Transportation Unit. In order to accommodate the new furniture, EXIM requires installation of power and data cabling that will support furniture functions that are required in the space.
Work to be completed: (Refer to Drawing labeled Transportation for counts and locations)
· Install 10 new data drops
· Test and label cabling in workstations to CommScope specifications.
3. 11th Floor Export Finance
Overview:
· Export Import Bank (EXIM) is looking for a contractor to perform data and cable installations and adjustments at the Lafayette building on the Export Finance space. EXIM is replacing rental furniture with purchased furniture throughout their occupied space. The area within EXIM’s occupied space to receive new furniture is the (1,304 SF), 11th Floor Export Finance Unit In order to accommodate the new furniture, EXIM requires installation of power and data cabling that will support furniture functions that are required in the space.
Work to be completed: (Refer to Drawing labeled Export Finance for counts and locations)
· Install 6 new data drops
· Test and label cabling in workstations to CommScope specifications.
4. 11th Floor Admin. Services
Overview:
Export Import Bank (EXIM) is looking for a contractor to perform data and cable installations and adjustments at the Lafayette building on the Administrative Services space. EXIM is replacing rental furniture with purchased furniture throughout their occupied space. The area within EXIM’s occupied space to receive new furniture is the (1040 SF),11th Floor Administrative Services Unit. In order to accommodate the new furniture, EXIM requires installation of power and data cabling that will support furniture functions that are required in the space.
Work to be completed: (Refer to Drawing labeled Admin Svcs for counts and locations)
· Install 4 new data drops
· Test and label cabling in workstations to CommScope specifications.
5. 12th Floor Vice Chair
Overview:
Export Import Bank (EXIM) is looking for a contractor to perform data and cable installations and adjustments at the Lafayette building on the Vice Chair office. EXIM is replacing rental furniture with purchased furniture throughout their occupied space. The area within EXIM’s occupied space to receive new furniture is the (1055 SF),12th Floor Vice Chairman’s office. In order to accommodate the new furniture, EXIM requires installation of power and data cabling that will support furniture functions that are required in the space.
Work to be completed: (Refer to Drawing labeled Vice Chair for counts and locations)
· Install 5 new data drops
· Test and label cabling in workstations to CommScope specifications.
6. 12th Floor EEO
Overview:
· Export Import Bank (EXIM) is looking for a contractor to perform data and cable installations and adjustments at the Lafayette building on the EEO space. EXIM is replacing rental furniture with purchased furniture throughout their occupied space. The area within EXIM’s occupied space to receive new furniture is the (653 SF),12th Floor EEO Unit. In order to accommodate the new furniture, EXIM requires installation of power and data cabling that will support furniture functions that are required in the space.
Work to be completed: (Refer to Drawing EEO for counts and locations)
· Install 2 new data drops
· Test and label cabling in workstations to CommScope specifications.
7. 12th Floor Lactation Room
Overview:
· Export Import Bank (EXIM) is looking for a contractor to perform data and cable installations and adjustments at the Lafayette building on the Lactation space. EXIM is replacing rental furniture with purchased furniture throughout their occupied space. The area within EXIM’s occupied space to receive new furniture is the (455 SF),12th Floor Lactation Unit. In order to accommodate the new furniture, EXIM requires installation of power and data cabling that will support furniture functions that are required in the space.
Work to be completed: (Refer to Drawing labeled Lacation Room for counts and locations)
· Install 4 new data drops
· Test and label cabling in workstations to CommScope specifications.
8. 9th Floor North- Credit
Overview:
Export Import Bank (EXIM) is looking for a contractor to perform data and cable installations and adjustments at the Lafayette building on the Credit space. EXIM is replacing rental furniture with purchased furniture throughout their occupied space. The area within EXIM’s occupied space to receive new furniture is the (3,187 SF),9th Floor Credit Unit. In order to accommodate the new furniture, EXIM requires installation of power and data cabling that will support furniture functions that are required in the space.
Work to be completed: (Refer to Drawing labeled 9th Fl. North for counts and locations)
· Install 23 new data drops
· Install new CommScope 24-port patch panel
9. 9th Floor North East- Engineering
Overview:
Export Import Bank (EXIM) is looking for a contractor to perform data and cable installations and adjustments at the Lafayette building on the Engineering space. EXIM is replacing rental furniture with purchased furniture throughout their occupied space. The area within EXIM’s occupied space to receive new furniture is the (5,080 SF),9th Floor Engineering Unit. In order to accommodate the new furniture, EXIM requires installation of power and data cabling that will support furniture functions that are required in the space.
Work to be completed: (Refer to Drawing labeled 9th Fl. East for counts and locations)
· Install 17 new data drops
· Install new CommScope 24-port patch panel