Exibit 1 Bid Pricing Page REVISED 9-15-2023.xlsx
XLSX spreadsheet 15 KB Posted
- Solicitation number
- S-63400-00007968
- Issued by
- Wasco County, Oregon
About this file
This document is an Exhibit 1 Pricing Submittal Form for ITB #9964, a state contract opportunity issued by the Oregon State Parks for Boating Facility Improvements at Mayer State Park. The solicitation includes a detailed list of 44 bid items, such as mobilization, erosion control, excavation, piling removal, concrete work, paving, utilities, landscaping, and other related items. Quantities are provided for each item, and bidders are instructed to provide unit pricing. The contract will be awarded based on the total bid amount, and the owner reserves the right to adjust quantities or delete items as needed. Payments will be made based on actual measured quantities.
The pricing form specifies that the contractor shall furnish all temporary facilities and incidental work at no additional cost to the owner. The contract documents state that the quantities provided are for bid purposes only and are not a guarantee. The solicitation is open to all qualified bidders, and there is no mention of any set-asides or incumbent contractors. Funding for the project is provided by the state of Oregon, and the contract term is not explicitly stated.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment D DSL Permit.pdf | ||
| Clarification to questions~1.docx | DOCX document | |
| Justification - RTI.pdf | ||
| Attachment A Technical Specifications~11.pdf | ||
| Attachment D DEQ Permit.pdf | ||
| BID TAB~3.docx | DOCX document | |
| Detailed Bid Tab.xlsx | XLSX spreadsheet | |
| Attachment B Drawings~8.pdf | ||
| Attachment D USACOE Permit.pdf | ||
| Attachment D Wascoe County Permit.pdf | ||
| ITB 9964 Boating Facility Improvements at Mayer State Park~1.pdf | ||
| Addendum 1 to ITB 9964 Boating Facility Improvements at Mayer State Park.docx | DOCX document | |
| Exibit 1 Bid Pricing Page~11.xlsx | XLSX spreadsheet | |
| Intent to Award~8.docx | DOCX document |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| EXHIBIT 1 |
| PRICING SUBMITTAL FORM - REVISED 9/15/2023 |
| ITB #9964 |
| OregonBuys Solicitation # S-63400-07968 |
| Mayer State Park - Boating Facility Improvements |
| PRICING SUBMITTAL INSTRUCTIONS: |
| Offerors shall enter pricing and other required information for all Bid Items listed in this Pricing Submittal Form. If this Pricing Submittal Form is replaced by Addenda then Offerors shall use the Addenda forms to provide pricing and other required information. If the Pricing Submittal Form is only modified by Addenda, then Offerors shall follow the instructions in the Addenda for making modifications to the Pricing Submittal Form. Failure to supply the required information in the Pricing Submittal Form or subsequent Addenda may result in Bid rejection as non-responsive. |
The undersigned has carefully examined the Contract Documents and the site of the work, and agrees to furnish all necessary plant, labor, equipment, accessories, materials, permits, and perform all operations shown and specified in accordance with the Contract Documents for the price(s) set below. All Work described in the Contract Documents but not specifically itemized in the Pricing below is considered incidental to the Work, and Offeror agrees to furnish all necessary plant, labor, equipment, accessories, materials, permits, and perform all incidental Work at no additional cost to the Owner.
Contractor shall furnish all temporary facilities such as power, lights, heat, telephone, potable water, portable toilets and job office as needed to perform the Work at no additional charge to Owner.
| The quantities listed in Pricing Submittal Form are intended to serve only as a guide to Bidders and are not to be construed as a guarantee. All quantities are estimated and are for Bid purposes only. All quantities are "in place" or "installed". OPRD reserves the right to adjust quantities or delete items as needed. Payment will be made based on actual, measured quantities. | |||||
| Line Items | Quantity | Unit | Unit Cost | Total Cost | |
| 1 | Mobilization, Bonds & Insurance | 1 | LS | $ - 0 | |
| 2 | Materials Testing & Monitoring | 1 | LS | $ - 0 | |
| 3 | Project Layout & Survey Verification | 1 | LS | $ - 0 | |
| 4 | Erosion Control | 1 | LS | $ - 0 | |
| 5 | Floating Silt Curtain | 500 | LF | $ - 0 | |
| 6 | Existing Structures Removal & Disposal | 1 | LS | $ - 0 | |
| 7 | Wood Piling Removal & Disposal | 30 | EA | $ - 0 | |
| 8 | Remove Wheel Stops | 32 | EA | $ - 0 | |
| 9 | Unclassified Excavation | 1410 | CY | $ - 0 | |
| 10 | Geotextile - Subbase Uplands | 24500 | SF | $ - 0 | |
| 11 | Geotextile - Subbase In-Water | 2000 | SF | $ - 0 | |
| 12 | Geotectile - Riprap | 5600 | SF | $ - 0 | |
| 13 | Aggregate Base - Open-Graded - REVISED Addendum 1 | 665 | TON | $ - 0 | |
| 14 | Aggregate Base - Dense-Graded | 1780 | TON | $ - 0 | |
| 15 | Riprap - Class 700 | 925 | TON | $ - 0 | |
| 16 | Capped Cobble | 190 | CY | $ - 0 | |
| 17 | Riprap - Class 100 | 25 | TON | $ - 0 | |
| 18 | Dive Team | 1 | LS | $ - 0 | |
| 19 | Steel Rail System | 1 | LS | $ - 0 | |
| 20 | Precast Planks | 2332 | SF | $ - 0 | |
| 21 | Cast-In-Place Concrete Launch Ramp | 745 | SF | $ - 0 | |
| 22 | Concrete Dock Abutment | 1 | LS | $ - 0 | |
| 23 | Traffic Delineators | 1 | EA | $ - 0 | |
| 24 | Boarding Dock Installation (Owner Furnished/Contractor Installed) | 1 | LS | $ - 0 | |
| 25 | 12" Steel Piles | 4 | EA | $ - 0 | |
| 26 | Sidewalk, Monolithic | 675 | SF | $ - 0 | |
| 27 | Sidewalk, Reinforced | 315 | SF | $ - 0 | |
| 28 | Detectable Warning Pad | 2 | EA | $ - 0 | |
| 29 | Cast-In-Place Concrete Curb | 325 | LF | $ - 0 | |
| 30 | Concrete Pavement, Reinforced | 2120 | SF | $ - 0 | |
| 31 | Trench Drain | 20 | LF | $ - 0 | |
| 32 | Asphalt Pavement | 695 | TON | $ - 0 | |
| 33 | Piping | 66 | LF | $ - 0 | |
| 34 | Inlet | 2 | EA | $ - 0 | |
| 35 | Water Line | 60 | LF | $ - 0 | |
| 36 | Water Appurtenances | 1 | EA | $ - 0 | |
| 37 | Stormwater Basin | 5687 | SF | $ - 0 | |
| 38 | Plantings | 1 | LS | $ - 0 | |
| 39 | Pavement Striping, Symbols, & Lettering | 1 | LS | $ - 0 | |
| 40 | Kiosk | 2 | EA | $ - 0 | |
| 41 | Concrete Wheel Stops (Reinstall) | 10 | EA | $ - 0 | |
| 42 | Concrete Wheel Stops (New) | 38 | EA | $ - 0 | |
| 43 | Signs (Owner Furnished/Contractor Installed) | 1 | LS | $ - 0 | |
| 44 | Over-Excavation and Subgrade Stabilization | 150 | CY | $ - 0 | |
| TOTAL BID (Lines 1-44) | $ - 0 |
By (Bidder Name Date