Detailed Bid Tab.xlsx

XLSX spreadsheet 43 KB Posted

Attached to
ITB 9964 Boating Facility Improvements at Mayer State Park
Solicitation number
S-63400-00007968
Issued by
Wasco County, Oregon

About this file

The document is an Excel bid tabulation sheet for Bid ITB #9964 for the Boating Facility Improvements at Mayer State Park project issued by the Oregon Parks and Recreation Department. The project involves various construction activities such as demolition, excavation, paving, concrete work, and other site improvements. The bid tabulation sheet shows the unit costs and total costs for the line items bid by four contractors: TAPANI, INC., CASCADE CIVIL, BEAM EXCAVATING, and CRESTLINE CONSTRUCTION. The bid opening is scheduled for 2:00 PM on 9/20/2023. The contract is for the state of Oregon, specifically Wasco County.

The bid tabulation sheet provides detailed pricing information for 44 line items, including items such as mobilization, materials testing, survey work, erosion control, demolition, earthwork, paving, concrete work, steel rail system, precast planks, dock installation, piping, and landscaping. The total bid amounts range from $1,419,434.75 to $1,795,059.00 across the four bidders. The contract will be awarded to the lowest responsive and responsible bidder.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

BID TABULATION

Oregon Parks and Recreation Department
725 Summer St. NE, Ste C
PROJECT TITLE:Boating Facility Improvements at Mayer State ParkPROJECT TITLE:Boating Facility Improvements at Mayer State Park
OregonBuys #:S-63400-00007968
ITB #:9964
BID OPENING:Time: 2:00 PMDate: 9/20//2023
TAPANI, INC.CASCADE CIVILBEAM EXCAVATINGCRESTLINE CONSTRUCTION
Line ItemsQuantityUnitUnit CostTotal CostUnit CostTotal CostUnit CostTotal CostUnit CostTotal Cost
1Mobilization, Bonds & Insurance1LS$ 140,000.00$ 140,000.00$ 160,000.00$ 160,000.00$ 16,665.00$ 16,665.00$ 300,000.00$ 300,000.00
2Materials Testing & Monitoring1LS$ 33,250.00$ 33,250.00$ 52,000.00$ 52,000.00$ 10,487.00$ 10,487.00$ 30,000.00$ 30,000.00
3Project Layout & Survey Verification1LS$ 25,000.00$ 25,000.00$ 27,000.00$ 27,000.00$ 16,953.00$ 16,953.00$ 32,000.00$ 32,000.00
4Erosion Control1LS$ 25,000.00$ 25,000.00$ 13,000.00$ 13,000.00$ 3,608.00$ 3,608.00$ 10,000.00$ 10,000.00
5Floating Silt Curtain500LF$ 85.00$ 42,500.00$ 15.00$ 7,500.00$ 25.00$ 12,500.00$ 45.00$ 22,500.00
6Existing Structures Removal & Disposal1LS$ 35,500.00$ 35,500.00$ 40,762.60$ 40,762.60$ 65,759.00$ 65,759.00$ 57,000.00$ 57,000.00
7Wood Piling Removal & Disposal30EA$ 5,250.00$ 157,500.00$ 1,970.00$ 59,100.00$ 2,964.00$ 88,920.00$ 2,825.00$ 84,750.00
8Remove Wheel Stops32EA$ 50.00$ 1,600.00$ 30.00$ 960.00$ 80.00$ 2,560.00$ 125.00$ 4,000.00
9Unclassified Excavation1410CY$ 53.00$ 74,730.00$ 51.00$ 71,910.00$ 35.00$ 49,350.00$ 67.00$ 94,470.00
10Geotextile - Subbase Uplands24500SF$ 0.35$ 8,575.00$ 0.50$ 12,250.00$ 0.33$ 8,085.00$ 0.50$ 12,250.00
11Geotextile - Subbase In-Water2000SF$ 1.80$ 3,600.00$ 0.60$ 1,200.00$ 6.32$ 12,640.00$ 1.00$ 2,000.00
12Geotectile - Riprap5600SF$ 1.80$ 10,080.00$ 0.60$ 3,360.00$ 1.45$ 8,120.00$ 1.00$ 5,600.00
13Aggregate Base - Open-Graded - REVISED Addendum 1665TON$ 63.00$ 41,895.00$ 48.00$ 31,920.00$ 58.30$ 38,769.50$ 110.00$ 73,150.00
14Aggregate Base - Dense-Graded1780TON$ 53.00$ 94,340.00$ 52.50$ 93,450.00$ 46.00$ 81,880.00$ 45.00$ 80,100.00
15Riprap - Class 700925TON$ 90.00$ 83,250.00$ 88.00$ 81,400.00$ 69.00$ 63,825.00$ 100.00$ 92,500.00
16Capped Cobble190CY$ 85.00$ 16,150.00$ 88.00$ 16,720.00$ 96.00$ 18,240.00$ 102.00$ 19,380.00
17Riprap - Class 10025TON$ 85.00$ 2,125.00$ 85.00$ 2,125.00$ 138.00$ 3,450.00$ 163.00$ 4,075.00
18Dive Team1LS$ 28,000.00$ 28,000.00$ 65,000.00$ 65,000.00$ 60,235.00$ 60,235.00$ 63,250.00$ 63,250.00
19Steel Rail System1LS$ 39,000.00$ 39,000.00$ 41,000.00$ 41,000.00$ 66,544.00$ 66,544.00$ 55,000.00$ 55,000.00
20Precast Planks2332SF$ 39.00$ 90,948.00$ 45.70$ 106,572.40$ 101.00$ 235,532.00$ 57.00$ 132,924.00
21Cast-In-Place Concrete Launch Ramp745SF$ 21.00$ 15,645.00$ 51.00$ 37,995.00$ 55.00$ 40,975.00$ 53.00$ 39,485.00
22Concrete Dock Abutment1LS$ 7,250.00$ 7,250.00$ 21,000.00$ 21,000.00$ 44,880.00$ 44,880.00$ 11,200.00$ 11,200.00
23Traffic Delineators1EA$ 600.00$ 600.00$ 150.00$ 150.00$ 268.00$ 268.00$ 575.00$ 575.00
24Boarding Dock Installation (Owner Furnished/Contractor Installed)1LS$ 16,000.00$ 16,000.00$ 20,000.00$ 20,000.00$ 31,125.00$ 31,125.00$ 36,000.00$ 36,000.00
2512" Steel Piles4EA$ 18,100.00$ 72,400.00$ 56,600.00$ 226,400.00$ 58,536.00$ 234,144.00$ 20,000.00$ 80,000.00
26Sidewalk, Monolithic675SF$ 25.00$ 16,875.00$ 15.00$ 10,125.00$ 58.00$ 39,150.00$ 21.00$ 14,175.00
27Sidewalk, Reinforced315SF$ 20.00$ 6,300.00$ 15.00$ 4,725.00$ 63.00$ 19,845.00$ 20.00$ 6,300.00
28Detectable Warning Pad2EA$ 425.00$ 850.00$ 270.00$ 540.00$ 2,232.00$ 4,464.00$ 650.00$ 1,300.00
29Cast-In-Place Concrete Curb325LF$ 135.00$ 43,875.00$ 49.00$ 15,925.00$ 76.00$ 24,700.00$ 68.00$ 22,100.00
30Concrete Pavement, Reinforced2120SF$ 16.75$ 35,510.00$ 19.70$ 41,764.00$ 53.00$ 112,360.00$ 15.00$ 31,800.00
31Trench Drain20LF$ 340.00$ 6,800.00$ 500.00$ 10,000.00$ 158.00$ 3,160.00$ 410.00$ 8,200.00
32Asphalt Pavement695TON$ 125.00$ 86,875.00$ 148.00$ 102,860.00$ 141.00$ 97,995.00$ 132.00$ 91,740.00
33Piping66LF$ 63.00$ 4,158.00$ 88.00$ 5,808.00$ 40.00$ 2,640.00$ 105.00$ 6,930.00
34Inlet2EA$ 525.00$ 1,050.00$ 1,700.00$ 3,400.00$ 39.00$ 78.00$ 775.00$ 1,550.00
35Water Line60LF$ 78.00$ 4,680.00$ 88.00$ 5,280.00$ 34.00$ 2,040.00$ 70.00$ 4,200.00
36Water Appurtenances1EA$ 4,000.00$ 4,000.00$ 2,600.00$ 2,600.00$ 1,506.00$ 1,506.00$ 1,600.00$ 1,600.00
37Stormwater Basin5687SF$ 6.25$ 35,543.75$ 11.00$ 62,557.00$ 4.25$ 24,169.75$ 15.00$ 85,305.00
38Plantings1LS$ 35,000.00$ 35,000.00$ 41,000.00$ 41,000.00$ 40,771.00$ 40,771.00$ 46,000.00$ 46,000.00
39Pavement Striping, Symbols, & Lettering1LS$ 26,000.00$ 26,000.00$ 70,000.00$ 70,000.00$ 8,127.00$ 8,127.00$ 67,000.00$ 67,000.00
40Kiosk2EA$ 6,500.00$ 13,000.00$ 3,900.00$ 7,800.00$ 17,477.00$ 34,954.00$ 4,000.00$ 8,000.00
41Concrete Wheel Stops (Reinstall)10EA$ 115.00$ 1,150.00$ 75.00$ 750.00$ 143.00$ 1,430.00$ 550.00$ 5,500.00
42Concrete Wheel Stops (New)38EA$ 285.00$ 10,830.00$ 170.00$ 6,460.00$ 143.00$ 5,434.00$ 550.00$ 20,900.00
43Signs (Owner Furnished/Contractor Installed)1LS$ 4,000.00$ 4,000.00$ 3,000.00$ 3,000.00$ 16,021.00$ 16,021.00$ 17,500.00$ 17,500.00
44Over-Excavation and Subgrade Stabilization150CY$ 120.00$ 18,000.00$ 144.00$ 21,600.00$ 37.00$ 5,550.00$ 85.00$ 12,750.00
TOTAL BID (Lines 1-44)$ 1,419,434.75$ 1,608,969.00$ 1,659,909.25$ 1,795,059.00