Detailed Bid Tab.xlsx
XLSX spreadsheet 43 KB Posted
- Solicitation number
- S-63400-00007968
- Issued by
- Wasco County, Oregon
About this file
The document is an Excel bid tabulation sheet for Bid ITB #9964 for the Boating Facility Improvements at Mayer State Park project issued by the Oregon Parks and Recreation Department. The project involves various construction activities such as demolition, excavation, paving, concrete work, and other site improvements. The bid tabulation sheet shows the unit costs and total costs for the line items bid by four contractors: TAPANI, INC., CASCADE CIVIL, BEAM EXCAVATING, and CRESTLINE CONSTRUCTION. The bid opening is scheduled for 2:00 PM on 9/20/2023. The contract is for the state of Oregon, specifically Wasco County.
The bid tabulation sheet provides detailed pricing information for 44 line items, including items such as mobilization, materials testing, survey work, erosion control, demolition, earthwork, paving, concrete work, steel rail system, precast planks, dock installation, piping, and landscaping. The total bid amounts range from $1,419,434.75 to $1,795,059.00 across the four bidders. The contract will be awarded to the lowest responsive and responsible bidder.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment D DSL Permit.pdf | ||
| Clarification to questions~1.docx | DOCX document | |
| Justification - RTI.pdf | ||
| Attachment A Technical Specifications~11.pdf | ||
| Attachment D DEQ Permit.pdf | ||
| BID TAB~3.docx | DOCX document | |
| Attachment B Drawings~8.pdf | ||
| Attachment D USACOE Permit.pdf | ||
| Attachment D Wascoe County Permit.pdf | ||
| ITB 9964 Boating Facility Improvements at Mayer State Park~1.pdf | ||
| Addendum 1 to ITB 9964 Boating Facility Improvements at Mayer State Park.docx | DOCX document | |
| Exibit 1 Bid Pricing Page REVISED 9-15-2023.xlsx | XLSX spreadsheet | |
| Exibit 1 Bid Pricing Page~11.xlsx | XLSX spreadsheet | |
| Intent to Award~8.docx | DOCX document |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
BID TABULATION
| Oregon Parks and Recreation Department |
| 725 Summer St. NE, Ste C |
| PROJECT TITLE: | Boating Facility Improvements at Mayer State Park | PROJECT TITLE: | Boating Facility Improvements at Mayer State Park |
| OregonBuys #: | S-63400-00007968 | ||
| ITB #: | 9964 | ||
| BID OPENING: | Time: 2:00 PM | Date: 9/20//2023 |
| TAPANI, INC. | CASCADE CIVIL | BEAM EXCAVATING | CRESTLINE CONSTRUCTION | ||||||||
| Line Items | Quantity | Unit | Unit Cost | Total Cost | Unit Cost | Total Cost | Unit Cost | Total Cost | Unit Cost | Total Cost | |
| 1 | Mobilization, Bonds & Insurance | 1 | LS | $ 140,000.00 | $ 140,000.00 | $ 160,000.00 | $ 160,000.00 | $ 16,665.00 | $ 16,665.00 | $ 300,000.00 | $ 300,000.00 |
| 2 | Materials Testing & Monitoring | 1 | LS | $ 33,250.00 | $ 33,250.00 | $ 52,000.00 | $ 52,000.00 | $ 10,487.00 | $ 10,487.00 | $ 30,000.00 | $ 30,000.00 |
| 3 | Project Layout & Survey Verification | 1 | LS | $ 25,000.00 | $ 25,000.00 | $ 27,000.00 | $ 27,000.00 | $ 16,953.00 | $ 16,953.00 | $ 32,000.00 | $ 32,000.00 |
| 4 | Erosion Control | 1 | LS | $ 25,000.00 | $ 25,000.00 | $ 13,000.00 | $ 13,000.00 | $ 3,608.00 | $ 3,608.00 | $ 10,000.00 | $ 10,000.00 |
| 5 | Floating Silt Curtain | 500 | LF | $ 85.00 | $ 42,500.00 | $ 15.00 | $ 7,500.00 | $ 25.00 | $ 12,500.00 | $ 45.00 | $ 22,500.00 |
| 6 | Existing Structures Removal & Disposal | 1 | LS | $ 35,500.00 | $ 35,500.00 | $ 40,762.60 | $ 40,762.60 | $ 65,759.00 | $ 65,759.00 | $ 57,000.00 | $ 57,000.00 |
| 7 | Wood Piling Removal & Disposal | 30 | EA | $ 5,250.00 | $ 157,500.00 | $ 1,970.00 | $ 59,100.00 | $ 2,964.00 | $ 88,920.00 | $ 2,825.00 | $ 84,750.00 |
| 8 | Remove Wheel Stops | 32 | EA | $ 50.00 | $ 1,600.00 | $ 30.00 | $ 960.00 | $ 80.00 | $ 2,560.00 | $ 125.00 | $ 4,000.00 |
| 9 | Unclassified Excavation | 1410 | CY | $ 53.00 | $ 74,730.00 | $ 51.00 | $ 71,910.00 | $ 35.00 | $ 49,350.00 | $ 67.00 | $ 94,470.00 |
| 10 | Geotextile - Subbase Uplands | 24500 | SF | $ 0.35 | $ 8,575.00 | $ 0.50 | $ 12,250.00 | $ 0.33 | $ 8,085.00 | $ 0.50 | $ 12,250.00 |
| 11 | Geotextile - Subbase In-Water | 2000 | SF | $ 1.80 | $ 3,600.00 | $ 0.60 | $ 1,200.00 | $ 6.32 | $ 12,640.00 | $ 1.00 | $ 2,000.00 |
| 12 | Geotectile - Riprap | 5600 | SF | $ 1.80 | $ 10,080.00 | $ 0.60 | $ 3,360.00 | $ 1.45 | $ 8,120.00 | $ 1.00 | $ 5,600.00 |
| 13 | Aggregate Base - Open-Graded - REVISED Addendum 1 | 665 | TON | $ 63.00 | $ 41,895.00 | $ 48.00 | $ 31,920.00 | $ 58.30 | $ 38,769.50 | $ 110.00 | $ 73,150.00 |
| 14 | Aggregate Base - Dense-Graded | 1780 | TON | $ 53.00 | $ 94,340.00 | $ 52.50 | $ 93,450.00 | $ 46.00 | $ 81,880.00 | $ 45.00 | $ 80,100.00 |
| 15 | Riprap - Class 700 | 925 | TON | $ 90.00 | $ 83,250.00 | $ 88.00 | $ 81,400.00 | $ 69.00 | $ 63,825.00 | $ 100.00 | $ 92,500.00 |
| 16 | Capped Cobble | 190 | CY | $ 85.00 | $ 16,150.00 | $ 88.00 | $ 16,720.00 | $ 96.00 | $ 18,240.00 | $ 102.00 | $ 19,380.00 |
| 17 | Riprap - Class 100 | 25 | TON | $ 85.00 | $ 2,125.00 | $ 85.00 | $ 2,125.00 | $ 138.00 | $ 3,450.00 | $ 163.00 | $ 4,075.00 |
| 18 | Dive Team | 1 | LS | $ 28,000.00 | $ 28,000.00 | $ 65,000.00 | $ 65,000.00 | $ 60,235.00 | $ 60,235.00 | $ 63,250.00 | $ 63,250.00 |
| 19 | Steel Rail System | 1 | LS | $ 39,000.00 | $ 39,000.00 | $ 41,000.00 | $ 41,000.00 | $ 66,544.00 | $ 66,544.00 | $ 55,000.00 | $ 55,000.00 |
| 20 | Precast Planks | 2332 | SF | $ 39.00 | $ 90,948.00 | $ 45.70 | $ 106,572.40 | $ 101.00 | $ 235,532.00 | $ 57.00 | $ 132,924.00 |
| 21 | Cast-In-Place Concrete Launch Ramp | 745 | SF | $ 21.00 | $ 15,645.00 | $ 51.00 | $ 37,995.00 | $ 55.00 | $ 40,975.00 | $ 53.00 | $ 39,485.00 |
| 22 | Concrete Dock Abutment | 1 | LS | $ 7,250.00 | $ 7,250.00 | $ 21,000.00 | $ 21,000.00 | $ 44,880.00 | $ 44,880.00 | $ 11,200.00 | $ 11,200.00 |
| 23 | Traffic Delineators | 1 | EA | $ 600.00 | $ 600.00 | $ 150.00 | $ 150.00 | $ 268.00 | $ 268.00 | $ 575.00 | $ 575.00 |
| 24 | Boarding Dock Installation (Owner Furnished/Contractor Installed) | 1 | LS | $ 16,000.00 | $ 16,000.00 | $ 20,000.00 | $ 20,000.00 | $ 31,125.00 | $ 31,125.00 | $ 36,000.00 | $ 36,000.00 |
| 25 | 12" Steel Piles | 4 | EA | $ 18,100.00 | $ 72,400.00 | $ 56,600.00 | $ 226,400.00 | $ 58,536.00 | $ 234,144.00 | $ 20,000.00 | $ 80,000.00 |
| 26 | Sidewalk, Monolithic | 675 | SF | $ 25.00 | $ 16,875.00 | $ 15.00 | $ 10,125.00 | $ 58.00 | $ 39,150.00 | $ 21.00 | $ 14,175.00 |
| 27 | Sidewalk, Reinforced | 315 | SF | $ 20.00 | $ 6,300.00 | $ 15.00 | $ 4,725.00 | $ 63.00 | $ 19,845.00 | $ 20.00 | $ 6,300.00 |
| 28 | Detectable Warning Pad | 2 | EA | $ 425.00 | $ 850.00 | $ 270.00 | $ 540.00 | $ 2,232.00 | $ 4,464.00 | $ 650.00 | $ 1,300.00 |
| 29 | Cast-In-Place Concrete Curb | 325 | LF | $ 135.00 | $ 43,875.00 | $ 49.00 | $ 15,925.00 | $ 76.00 | $ 24,700.00 | $ 68.00 | $ 22,100.00 |
| 30 | Concrete Pavement, Reinforced | 2120 | SF | $ 16.75 | $ 35,510.00 | $ 19.70 | $ 41,764.00 | $ 53.00 | $ 112,360.00 | $ 15.00 | $ 31,800.00 |
| 31 | Trench Drain | 20 | LF | $ 340.00 | $ 6,800.00 | $ 500.00 | $ 10,000.00 | $ 158.00 | $ 3,160.00 | $ 410.00 | $ 8,200.00 |
| 32 | Asphalt Pavement | 695 | TON | $ 125.00 | $ 86,875.00 | $ 148.00 | $ 102,860.00 | $ 141.00 | $ 97,995.00 | $ 132.00 | $ 91,740.00 |
| 33 | Piping | 66 | LF | $ 63.00 | $ 4,158.00 | $ 88.00 | $ 5,808.00 | $ 40.00 | $ 2,640.00 | $ 105.00 | $ 6,930.00 |
| 34 | Inlet | 2 | EA | $ 525.00 | $ 1,050.00 | $ 1,700.00 | $ 3,400.00 | $ 39.00 | $ 78.00 | $ 775.00 | $ 1,550.00 |
| 35 | Water Line | 60 | LF | $ 78.00 | $ 4,680.00 | $ 88.00 | $ 5,280.00 | $ 34.00 | $ 2,040.00 | $ 70.00 | $ 4,200.00 |
| 36 | Water Appurtenances | 1 | EA | $ 4,000.00 | $ 4,000.00 | $ 2,600.00 | $ 2,600.00 | $ 1,506.00 | $ 1,506.00 | $ 1,600.00 | $ 1,600.00 |
| 37 | Stormwater Basin | 5687 | SF | $ 6.25 | $ 35,543.75 | $ 11.00 | $ 62,557.00 | $ 4.25 | $ 24,169.75 | $ 15.00 | $ 85,305.00 |
| 38 | Plantings | 1 | LS | $ 35,000.00 | $ 35,000.00 | $ 41,000.00 | $ 41,000.00 | $ 40,771.00 | $ 40,771.00 | $ 46,000.00 | $ 46,000.00 |
| 39 | Pavement Striping, Symbols, & Lettering | 1 | LS | $ 26,000.00 | $ 26,000.00 | $ 70,000.00 | $ 70,000.00 | $ 8,127.00 | $ 8,127.00 | $ 67,000.00 | $ 67,000.00 |
| 40 | Kiosk | 2 | EA | $ 6,500.00 | $ 13,000.00 | $ 3,900.00 | $ 7,800.00 | $ 17,477.00 | $ 34,954.00 | $ 4,000.00 | $ 8,000.00 |
| 41 | Concrete Wheel Stops (Reinstall) | 10 | EA | $ 115.00 | $ 1,150.00 | $ 75.00 | $ 750.00 | $ 143.00 | $ 1,430.00 | $ 550.00 | $ 5,500.00 |
| 42 | Concrete Wheel Stops (New) | 38 | EA | $ 285.00 | $ 10,830.00 | $ 170.00 | $ 6,460.00 | $ 143.00 | $ 5,434.00 | $ 550.00 | $ 20,900.00 |
| 43 | Signs (Owner Furnished/Contractor Installed) | 1 | LS | $ 4,000.00 | $ 4,000.00 | $ 3,000.00 | $ 3,000.00 | $ 16,021.00 | $ 16,021.00 | $ 17,500.00 | $ 17,500.00 |
| 44 | Over-Excavation and Subgrade Stabilization | 150 | CY | $ 120.00 | $ 18,000.00 | $ 144.00 | $ 21,600.00 | $ 37.00 | $ 5,550.00 | $ 85.00 | $ 12,750.00 |
| TOTAL BID (Lines 1-44) | $ 1,419,434.75 | $ 1,608,969.00 | $ 1,659,909.25 | $ 1,795,059.00 |