This document is the submittal requirements section (Section 013300) from a construction subcontract related to a federal contract opportunity. It specifies the general methods and requirements for project submittals, including shop drawings, material samples, and operation and maintenance manuals. Key details include:

The subcontractor must submit all materials and assemblies used on the project, as well as project schedules, in electronic PDF format. Submittals will be reviewed by the government (FRA) within 10 working days and returned with one of several response actions, such as "No Exception Taken," "Revise & Resubmit," or "Rejected." Substitutions for specified products will be considered but must include a comparison to the original product and indicate any related design changes required. The subcontractor must maintain a set of as-built drawings at the job site and provide a final marked-up set to FRA upon completion.

The related federal contract opportunity is for the removal and replacement of roofing systems, including one low roof and one high bay roof, at an existing building at the Fermi National Accelerator Laboratory site in Illinois. The work includes all required labor, materials, and equipment to remove and dispose of existing roofing and insulation, and install a new SBS Asphalt 4CID CR G roofing system, as well as associated work such as relocating roof equipment and installing a new ballasted roof edge railing system.

View the file

Other files

File Type Posted
Amendment No. 1 Fermilab Removal Systems.pdf PDF
Exhibit T 10-4-101_Site 40 LLRW_V2024_Roof-G02-REV1.pdf PDF
Exhibit S Request For Clarifications v1.pdf PDF
Exhibit 1- REQUEST FOR PROPOSAL (RFP) INSTRUCTIONS TO OFFERORS Roof Replacement_Site40 v2.pdf PDF
Exhibit Q 10-4-101_Site 40 LLRW_Roof Replacement drawing set_240913.pdf PDF
Exhibit D FL-41 (Rev 12.22) - Bid Bond.pdf PDF
Exhibit M Site40_013100_ESH_Requirements_3-2022.pdf PDF
Exhibit F Performance Bond FL-40 (Rev 12.22).pdf PDF
Exhibit G Fermilab Subcontractor Safety Information Questionnaire.pdf PDF
Exhibit I Proposal Certifications Form PUR 466 Rev. 1 (10142021).pdf PDF
Exhibit R Proposal Form.pdf PDF
Exhibit O Sample Subcontract.pdf PDF
Exhibit P Wage Determinations.pdf PDF
Exhibit J Subcontractor Annual Representations Certifications (SARC) Form SARC (Rev. 3) (04082022).pdf PDF
Exhibit H Statement and Acknowledgment (Standard Form 1413) (Rev 42013).pdf PDF
Exhibit A FRA General Terms and Conditions for Construction (03.2024).pdf PDF
Exhibit B 2022 Construction Insurance Requirements.pdf PDF
Exhibit E Payment Bond FL 42 (Rev 12.22).pdf PDF
Exhibit C SOW Site40_LLRW Roof Replacement_240913.pdf PDF
Exhibit K FAR 52-219-9-Small-Business-Subcontracting-Plan-.pdf PDF
Exhibit L Site40 010010_General_Requirements_3_2022_240913.pdf PDF
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FRA Submittals November 2019

SUBMITTALS 013300 - 1

SECTION 013300 – SUBMITTALS

PART 1 GENERAL

1.1 PURPOSE

This section specifics general methods and requirements of project work related submittals. Additionally detailed submittal requirements may be found in the bid design and/or technical specification sections.

1.2 REFERENCES

The publications listed below form a part of this subcontract to the extent referenced.

010010 General Requirements 013100 Environment, Safety, and Health Requirements

1.3 SHOP DRAWINGS, MATERIAL SAMPLES, AND OPERATIONS MAINTENANCE

MANUALS

Subcontractor shall submit for all materials and assemblies used on the project which are normally required in the construction industry. In addition, project schedules shall be submitted using the “Submittal for Review Transmittal” found in Attachment A and logged as part of the submittal file.

All submittals shall be electronic PDF format. Calculations shall be native format and electronic PDF format.

Refer Construction Subcontract Terms and Conditions, for additional information on shop drawing submittals.

The Subcontractor shall supply electronic PDF version of all operation and maintenance manuals, and an electronic PDF version for equipment furnished by the Subcontractor or their Sub-tier contractor prior to final acceptance of the project by FRA.

The Subcontractor shall complete the "Submittal for Review Transmittal" form for each shop drawing submittal, reference Attachment A.

Submittals, shop drawings and schedules of all trades shall be submitted by the Subcontractor, who shall indicate by signed stamp on the drawings, that he has checked the shop drawings and that the work shown is in accordance with the Subcontract requirements and that it has been checked for dimension and relationship with the work of all trades. These drawings shall be submitted not later than the approved schedule for shop drawing transmittal, shall contain all required detailed information, and shall be submitted in logical order to facilitate proper review.

Shop drawings which relate to a complete assembly, structure or system with various parts shall not be submitted until all drawings required to completely detail that assembly, structure or system are complete, so that they may be checked in relation to each other.

SUBMITTALS 013300 - 2

1.4 IN LIEU OF THE AS-BUILT SHOP DRAWINGS

As specified in FRA Construction Subcontract Terms and Conditions, the Subcontractor shall furnish As-Built drawings as outlined below.

The Subcontractor shall maintain a set of prints of the Subcontract drawings in the construction office at the job site. A daily record, in red, shall be kept on these prints of the work installed with all modifications or changes thereon. This set of prints shall be available to FRA for inspection at all times and print copies provided upon request to FRA within 24 hours of the request being made. The CMO and the Subcontractor's superintendent shall review the as-built drawings, and the scheduling of a progress payment update will be contingent on whether the as-built mark-up set is current and accurate.

Upon completion of all work, the Subcontractor shall transmit the above set of marked-up prints to FRA. Prior to submittal, the Subcontractor shall sign them to indicate that the work was installed as shown thereon.

1.5 FRA’S ROLES

FRA shall be the final judge of the acceptability of any and all drawings. Final acceptance of the work is contingent on the receipt and FRA's approval of the complete set of As-Built prints.

The Following distribution of drawing and technical specifications will be made by FRA to the Subcontractor:

After the award of the Subcontract and prior to Notice to Proceed, FRA will make available one electronic PDF of conformed Drawings and Technical Specifications.

Additional copies of either the conformed bid documents or any revised documents issued under the "Changes" provision shall be the responsibility of the Subcontractor.

1.6 USING THE SUBMITTAL FOR REVIEW FORM

Submittals shall be submitted to FRA, reference 010010 for contact information.

1.7 SUBMITTAL PROCESS

FRA will review the submittals and return one copy of all shop drawings within 10 (ten) working days with one of the following actions:

“No exception Taken” response on the Subcontractor’s shop drawings submittal and “NET” as shown on the Submittal for Review Transmittal form indicates the Subcontractor may proceed with procurement, fabrication, manufacture and installation of the material and/or product;

“Revise & Resubmit – Fabrication May Proceed” on the Subcontractor’s shop drawing submittal and “R/R” as shown on the Submittal for Review Transmittal form indicates the Subcontractor may proceed with procurement, fabrication, and manufacture of the material and/or product assuming the noted items on the submittal are incorporated into the final design and/or product. The Subcontractor will revise the shop drawings and resubmit them

SUBMITTALS 013300 - 3

to FRA for approval, but will not be able to erect and/or install any material until he has received either the “No Exception Taken (NET)” or the “Make Corrections and Proceed (MCP)” action by FRA;

“Make Corrections & Proceed” response on the Subcontractor’s shop drawing submittal and “MCP” as shown on the “Submittal for Review Transmittal” form indicates the Subcontractor may proceed with procurement, fabrication, manufacture and installation of the material and/or product assuming the noted items on the submittal are incorporated into the final design and/or product;

With the “Rejected” response on the Subcontractor’s shop drawing submittal and “R” as shown on the “Submittal for Review Transmittal” form, the reasons for the disapproval will be stated on the shop drawing submittal.

The Subcontractor will revise the shop drawing submittal to conform to the drawings and specifications and resubmit them to FRA for approval. No procurement, fabrication, manufacture or installation shall be performed by the Subcontractor until one of the above actions listed above is received;

“For Information Only” response on the Subcontractor’s shop drawing submittal and “FIO” on the “Submittal for Review Transmittal” form acknowledges receipt of such items as test results, professional engineering calculations, welding certificates and inspection reports.

1.8 MATERIAL SUBSTITUTIONS

Products or materials which are equal to, or the equivalent of, those specified will be considered for approval by FRA. The submittal procedure will be the same as above, with the following additional conditions: In addition to the required information for the substitute material, the submittal shall contain the same information pertaining to a product named in the specification for purposes of comparison.

The submittal shall explain fully the differences, if any, between the proposed product and those named in the specification.

Any change to the drawings or specifications for related work required for proper installation of the proposed substitute product shall be indicated in the submittal.

If the proposed substitute product requires alterations of any kind to other equipment or to the building or necessitates any engineering design changes for its proper installation, such alterations and engineering design changes shall be accomplished at no cost to

FRA.

PART 2 PRODUCTS - Not Used

PART 3 EXECUTION – Not Used

END OF SECTION

013300 -ST- 1

ATTACHMENT A

013300 -ST- 1

Subcontractor Submittal Transmittal

Submittal ID No.:

10-4-101

(spec section) (sub pkg #) (Review #) (Fermi proj #.)

TO: Fermi National Accelerator Laboratory

P.O. Box 500, MS-214

Batavia, Illinois 60510

FROM: xxxx xxxx xxxx

Date: Project No.: 10-4-101

Attn: Construction Manager Jackie Dragovich jdragovi@fnal.gov cc Construction Coordinator: TBD TBD cc: Design Coordinator Jackie Dragovich jdragovi@fnal.gov

Project Name: SITE 40 LOW LEVEL WASTE HANDLING BUILDING

Submittal

Item No.

Paragraph # and

Type of

Submittal

Product

Paragraph No.

Description

Subcontractor Review & Comments: