About this file
This is a Construction Safety and Phasing Plan exhibit for the County of Volusia, Florida's Invitation for Bid (ITB No. 26-B-77IF) for taxiway improvements at Daytona Beach International Airport. The document provides a detailed site plan and phasing layout for the Taxiway P3 and P4 Improvements project, illustrating the geometric configuration of Runway 7L-25R, taxiways P, B, and N, and associated infrastructure at the 700 Catalina Drive airport location. The project encompasses 58 line items of work including pavement demolition and reconstruction, excavation and grading, asphalt placement, drainage infrastructure, sodding, and comprehensive electrical work with cable and duct installation, lighting fixtures, and signage. The mandatory pre-bid conference is scheduled for April 2, 2026 at 1:30 PM with virtual attendance available via Microsoft Teams, and electronic bid submission through the County's eProcurement Portal is due by 3:00 PM on April 24, 2026. The contractor must achieve substantial completion within 216 days after Notice to Proceed and final completion within 246 days, with liquidated damages of $2,000 per calendar day assessed for delays beyond the substantial completion date.
The estimated construction cost is $4,851,000.00 with mobilization capped at 10 percent of the construction subtotal. The project is funded through FAA Airport Improvement Program (AIP) funding and FEMA-funded construction, requiring compliance with Buy American preferences and Davis-Bacon prevailing wage requirements ranging from approximately $15.54 to $33.61 per hour depending on labor classification. Disadvantaged Business Enterprise (DBE) participation requirements apply under 49 CFR Part 26, with contractors required to demonstrate good faith efforts for small, minority-owned, and women-owned business enterprise subcontracting. Bidders must submit a Bid Bond equal to five percent of the total bid amount, and upon award, provide a Payment and Performance Bond equal to 100 percent of the contract price. Comprehensive insurance requirements include Workers Compensation, Commercial General Liability ($1,000,000 per occurrence/$5,000,000 aggregate), Auto Liability ($1,000,000 combined single limits), Contractors Pollution Liability ($1,000,000), and an Installation Floater. The County will process payment on undisputed invoices within 20 business days from receipt with five percent retainage withheld pursuant to Florida Statute 255.078 and released upon final project acceptance. No incumbent contractor is identified for this project.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ST
ST
ST
ST ST
ST
ST
ST
ST
T
AC
AC
WV
RUNWAY 7L-25R
TAXIWAY P
TA
XI
W A
Y P4
TA
XI
W A
Y B
TA
XI
W A
Y B
TAXIWAY N
TA
XI
W A
Y N
TA
XI
W A
Y N
TA
XI
W A
Y N
TA
XI
W A
Y N
TA
XI
W A
Y N
TA
XI
W A
Y P5
BELLEVUE AVE
BELLEVUE AVE
TA
XI
W A
Y P3
2024.199.05
DRAWING
APRIL 2026
SS
NO. DATE BY DESCRIPTION
DRAWN BY:
APPROVED BY:
CHECKED BY:
DESIGNED BY:
DATE:
REVISIONS:
TW P3 AND TW P4
IMPROVEMENTS
DAYTONA BEACH
INTERNATIONAL
AIRPORT
2419905005G100CADD
PROFESSIONAL SEAL
FDOT FM:
FAA AIP: XXXX
XXXX
ENGINEERS & PLANNERS
5555 E. MICHIGAN ST., SUITE 200 - ORLANDO, FL 32822-2779
OFFICE: (407) 599-1122 - FAX: (407) 599-1133 CORPORATE
CERTIFICATE OF AUTHORIZATION NUMBER: 5057
www.avconinc.com
AVCON PROJECT NO.
SHEET OF 60
B
ID
D O
C U
M
EN
TS
GRAPHIC SCALE (FT)
400200100
NORTH
PROJECT SCHEDULE AND SEQUENCE LEGEND PHASING NOTES HAUL ROUTE NOTE
This item has been electronically signed and sealed by using an SHA-1 authentication code. Printed copies of this document are not considered signed and sealed and the SHA-1 authentication code must be verified on any electronic copies.
CONSTRUCTION
SAFETY AND
PHASING PLAN
RDH
UO
RKH
G100
SEAL on 2/18/2026