Exhibit_H,_BRIDGE_PRE-CONSTRUCTION_CHECKLIST,_26-B-92SR.pdf
PDF 298 KB Posted
- Solicitation number
- 26-B-92SR
- Issued by
- Volusia County, Florida
About this file
This is a Bridge Pre-Construction Checklist/Notice form issued by the US Coast Guard Southeast District Bridge Administration Branch in coordination with Sector Jacksonville Waterways. The form is designed to document requirements and obtain necessary clearances before construction activities begin on the Main Street Bridge (Bridge #794004) over Halifax River in Volusia County, Florida. The project involves full-depth concrete replacement on the eastbound deck, sidewalk, and railing on Span 47, along with associated work including traffic control, removal and disposal of materials, installation of fabric-formed concrete revetment, functional checks, operations and maintenance manuals, and as-built surveys and drawings. The checklist requires contractors to identify all in-water equipment, petroleum products, and hazardous materials to be used on site, as well as any proposed channel restrictions, closures, or vertical clearance restrictions with specific dates and times. A mandatory 60-day advance notice is required prior to project start, with an additional 30-day advance notice required before any channel obstructions, closures, or opening restrictions are implemented.
For movable spans, contractors must specify whether a complete closure, single leaf opening, limited openings, or advance notice protocol is being requested, and provide details on equipment placement, advance notice requirements for full openings or equipment relocation, and a point of contact responsible for managing these operations. All notifications must be submitted to Sector Jacksonville Waterways and Southeast District Bridge Administration. Additional requirements include submission of a hurricane plan for projects occurring between June and November. The checklist serves as a critical permitting and notification tool to ensure Coast Guard oversight and waterway safety compliance during bridge construction activities.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BRIDGE PRE-CONSTRUCTION NOTICE/REQUEST
Roadway/Bridge:
Waterway:
Bridge Owner:
Contractor Primary/24-Hour POC:
Project: Start Date/Time: Finish Date/Time:
Brief Project Description:
The Coast Guard requires all in-water equipment to be properly lighted. List any in-water equipment to be used:
Describe type/quantity of petroleum products or hazardous materials stored/transferred on site (if any):
Describe any proposed channel restrictions or closures and/or vertical clearance restrictions. Include dates/times of restriction(s):
On a movable span, are you requesting: Complete Closure, Single Leaf Opening, Limited Openings, Advance Notice.
Please Explain:
If Applicable:
Hurricane plan submitted for projects between June & November: Y/N How many hours advance notice needed for a full opening:
How many hours advance notice needed to move equipment to provide access to full channel:
Will in-water equipment remain in place or moved at end of workday:
POC for full opening/moving equipment:
60 days advance notice required prior to starting a project. 30 days advance notice required prior to any channel obstructions, closures, or opening restrictions. Make all notifications to Sector Jacksonville Waterways (D07-DG- SECJAX-WATERWAYS@uscg.mil) and to Southeast District Bridge Administration (Jennifer.N.Zercher@uscg.mil)
US Coast Guard Southeast District ꞏ Bridge Administration Branch (dpb) ꞏ 909 SE 1st Ave. ꞏ Miami, FL 33131